Minmar Builders, Inc. v. Beltway Excavators, Inc.

246 A.2d 784, 1968 D.C. App. LEXIS 214
CourtDistrict of Columbia Court of Appeals
DecidedOctober 24, 1968
Docket4209
StatusPublished
Cited by46 cases

This text of 246 A.2d 784 (Minmar Builders, Inc. v. Beltway Excavators, Inc.) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Minmar Builders, Inc. v. Beltway Excavators, Inc., 246 A.2d 784, 1968 D.C. App. LEXIS 214 (D.C. 1968).

Opinion

FICKLING, Associate Judge:

This is an appeal from a judgment of the trial court, sitting without a jury, awarding appellee $2,730.28 — the balance of the contract price — and dismissing appellant’s counterclaim.

Minmar Builders, Inc., appellant, entered into a contract with the District of Columbia Government for the construction of the West End Branch Library. Subsequently, appellant subcontracted excavation work to Beltway Excavators, Inc., appellee. This action was brought on the subcontract which provided that appellee would do the excavating on the project as “shown on the drawings and Section 2 of the specifications,” with certain specifically defined work included and excluded. A term of the subcontract was the requirement that, after the basement walls had been completed by appellant, appellee would return to the job and “[bjackfill the building supplying the M-l material as shown and directed in the specifications.”

After eighty-five percent of the subcontract had been completed and paid for, appellant requested appellee to return and proceed with the backfill operation around the perimeter of the walls. Appellee, although willing to perform, refused to proceed with the backfill until appellant fulfilled its obligation under the contract. Appellee contended that according to the plans and specifications a fine filter material (consisting of selected sands) was required to be placed by the appellant prior to or simultaneously with the M-l fill (a tight compacting fill consisting of sand, gravel, and clay), and that its contract expressly excluded from appellee’s duties the supplying of any fills other than M-l and M-2 and any work not shown in Section 2 of the specifications. Appellant disagreed and did not place the fine filter material around the walls, claiming that the plans and specifications did not require it. Subsequently, appellant itself placed M-1 fill around the perimeter of the wall, without using fine filter material. Appellee brought this action, claiming the balance of the contract price.

The trial court, after hearing extensive testimony and seeing many exhibits, found, among other things, that the drawings and specifications required appellant to install fine filter material around the perimeter of the basement walls; that the orders of appellant to appellee to complete the back-filling without prior or simultaneous placement of fine filter material by appellant constituted a material, substantial, and constructive change, requiring written approval by the District of Columbia Government; that appellee was legally justified in refusing to complete its subcontract because, *786 absent written approval of change, its duty of performance was dependent on the placement of the fine filter material by appellant, and appellant in failing to perform prevented appellee from proper performance.

Appellant makes three basic contentions. First, the trial judge applied the wrong criterion for his interpretation of what the plans and specifications called for. Second, the judge erred in failing to find an express, or at least implied, contractual obligation upon appellee to continue with performance even though it disputed appellant’s interpretation of the contract. Third, the court erred in permitting ap-pellee to abandon the contract.

As to appellant’s first contention, the plans and Section 2 of the specifications of the prime contract were expressly incorporated into the subcontract, and normal rules of interpretation of contracts should be employed in seeking to understand their provisions. The standard to be applied in such cases was well stated in Slice v. Carozza Properties, 215 Md. 357, 368, 137 A.2d 687, 693 (1958):

As we turn to the authorities, we may note first that the theory of “objective law” of contracts has been almost universally adopted by this time. The written language embodying the terms of an agreement will govern the rights and liabilities of the parties, irrespective of the intent of the parties at the time they entered into the contract, unless the written language is not susceptible of a clear and definite understanding, or unless there is fraud, duress or mutual mistake. “* * * where there has been an integration of an agreement, those who executed it will not be allowed to place their own interpretation on what it means or was intended to mean. The test in such a case is objective and not subjective. * * * Williston * * * Sec. 94, page 294, says: ‘It follows that the test of a true interpretation of an offer or acceptance is not what the party making it thought it meant or intended it to mean, but what a reasonable person in the position of the parties would have thought it meant.’ ” [Citations omitted.]

However, where there is some lack of clarity in the terms of the contract, other testimony regarding the intent of the parties and the meaning of the terms in that context may be required, and will properly be admitted in order to reach an objective interpretation. Homes Oil Realty Co. v. Hechinger Properties Co., D.C.Mun.App., 182 A.2d 62, 63 (1962); Curtis Builders v. General Floor Service Co., D.C.Mun.App., 107 A.2d 705 (1954) , 1

In the instant case, the trial judge emphasized frequently it was his intention to use these standards in interpreting the contractual obligations of the respective parties. The record indicates that he heard extensive testimony from various persons attempting to clarify the plans, looked to the documents themselves, and reached his finding only after a thorough review of all of the evidence. Appellant’s argument that the judge relied on any single part of the evidence before him 2 is not supported by the record, which reflects conflicting testimony.

Appellant’s second contention is that, because the provisions of the “changes” and “disputes” clauses of the prime contract were incorporated by reference through Section 2 of the specifications into the subcontract, appellee was required to continue with performance even if it disputed appellant’s interpretation of the contract. Even assuming, without deciding, that these clauses were incorporated by reference, we agree with the trial judge that *787 the “changes” clause, Article 3 of the prime contract, requires that any changes in the plans or specifications be made by written order of the government contracting officer. No such order was issued in this case. Secondly, the “disputes” clause, Article IS of the prime contract, 3 expressly provides that the procedure it sets forth will apply “[ejxcept as otherwise specifically provided in this contract, * Under the Special Stipulations to the prime contract, Paragraph 18 specifically deals with subcontracts, and subparagraph (e) of Paragraph 18 provides as follows:

(e) The Government of the District of Columbia will not undertake to settle any differences between the contractor and his subcontractor or between subcontractors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Howad B. Silverberg v. Joanne S. Becker
191 A.3d 324 (District of Columbia Court of Appeals, 2018)
Tillery v. District of Columbia Contract Appeals Board
912 A.2d 1169 (District of Columbia Court of Appeals, 2006)
Copeland v. Cohen
905 A.2d 144 (District of Columbia Court of Appeals, 2006)
Akassy v. William Penn Apartments Ltd. Partnership
891 A.2d 291 (District of Columbia Court of Appeals, 2006)
Washington Metropolitan Area Transit Authority v. Quik Serve Foods, Inc.
402 F. Supp. 2d 198 (District of Columbia, 2005)
Mick's at Pennsylvania Avenue, Inc. v. BOD, Inc.
389 F.3d 1284 (D.C. Circuit, 2004)
Booker v. Robert Half International, Inc.
315 F. Supp. 2d 94 (District of Columbia, 2004)
Geiger v. Crestar Bank
778 A.2d 1085 (District of Columbia Court of Appeals, 2001)
Capital City Mortgage Corp. v. Habana Village Art & Folklore, Inc.
747 A.2d 564 (District of Columbia Court of Appeals, 2000)
Adler v. Abramson
728 A.2d 86 (District of Columbia Court of Appeals, 1999)
Brown v. Union Station Venture Corp. No. P-5
727 A.2d 878 (District of Columbia Court of Appeals, 1999)
Webster v. Hope (In Re Hope)
231 B.R. 403 (District of Columbia, 1999)
Sagalyn v. Foundation for Preservation of Historic Georgetown
691 A.2d 107 (District of Columbia Court of Appeals, 1997)
Sutton v. Banner Life Insurance
686 A.2d 1045 (District of Columbia Court of Appeals, 1996)
Obelisk Corp. v. Riggs Nat. Bank of Washington, DC
668 A.2d 847 (District of Columbia Court of Appeals, 1995)
Isaac v. First National Bank of Maryland
647 A.2d 1159 (District of Columbia Court of Appeals, 1994)
Sacks v. Rothberg
569 A.2d 150 (District of Columbia Court of Appeals, 1990)
Reiman v. International Hospitality Group
558 A.2d 1128 (District of Columbia Court of Appeals, 1989)
Sadur v. Ellison
553 A.2d 651 (District of Columbia Court of Appeals, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
246 A.2d 784, 1968 D.C. App. LEXIS 214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/minmar-builders-inc-v-beltway-excavators-inc-dc-1968.