O. Ahlborg & Sons, Inc. v. Massachusetts Heavy Industries, Inc.

840 N.E.2d 977, 65 Mass. App. Ct. 385, 2006 Mass. App. LEXIS 34
CourtMassachusetts Appeals Court
DecidedJanuary 17, 2006
DocketNo. 04-P-608
StatusPublished
Cited by2 cases

This text of 840 N.E.2d 977 (O. Ahlborg & Sons, Inc. v. Massachusetts Heavy Industries, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O. Ahlborg & Sons, Inc. v. Massachusetts Heavy Industries, Inc., 840 N.E.2d 977, 65 Mass. App. Ct. 385, 2006 Mass. App. LEXIS 34 (Mass. Ct. App. 2006).

Opinion

Perretta, J.

Massachusetts Heavy Industries, Inc. (MHI), appeals from the entry of a separate and final judgment entered pursuant to Mass.R.Civ.P. 54(b), 365 Mass. 821 (1974), on a complaint brought by O. Ahlborg & Sons, Inc. (Ahlborg), seeking confirmation of an arbitrator’s award under G. L. c. 251, § 11. MHI argues that because the confirmation order did not resolve with finality a separate and distinct claim, the judge [386]*386erred in ordering the entry of a separate and final judgment and that the order sought to be confirmed was not that of an arbitrator. We affirm the judgment.

1. Background facts. In November, 1997, Ahlborg entered into a construction contract with MHI to do part of MHI’s work at a shipyard located in Quincy and Braintree. Section 5.1 of the contract allowed Ahlborg to submit monthly requisitions certifying the percentage and value of the work it had performed and to receive a progress payment commensurate with the work completed during the month. Requisitions were to be accompanied by lien waivers executed by Ahlborg and its subcontractors as well as certification by Ahlborg that amounts due and owing its subcontractors had been paid in full. MHI then had ten days to inspect the work or, in the event of a disputed item, to have the work subject to the requisition inspected by an “independent engineer” pursuant to section 10.1. As here pertinent, section 10.1 of the contract provides:

“Any controversy, dispute or claim between [Ahlborg] and [MHI] arising out of or relating to this Contract, or the breach thereof (a ‘Dispute’), shall first be referred to the Independent Engineer for mediation/arbitration. If either [party] is not satisfied with the determination made by the Independent Engineer and wishes to reserve its right to contest such determination, such party shall give notice to the other within twenty (20) days after the Independent Engineer delivers his written determination to the [parties], to set forth the portion of the Dispute being reserved for later arbitration . . . (the ‘Reservation Notice’). The determination of the Independent Engineer shall be conclusively binding upon [Ahlborg] or [MHI], or both, as the case may be, with respect to any portion of the Dispute that is not so reserved.. . . [A]ny Dispute or portion thereof that is reserved for the later arbitrator as set forth . . . above shall be reserved for decision until after Substantial Completion . . . .” (Emphasis in original.)

In July of 1999, with the contract work overdue and over budget, the parties came to an impasse in a dispute about the amount of a progress payment due Ahlborg, requisition number [387]*38712 (the requisition), for work that it claimed it had performed under the contract during the period May 1 through June 30, 1999. The primary but not sole bone of contention between the parties in respect to the requisition was the percentage of work that Ahlborg had completed under the terms of the contract.

On August 13, 1999, MHI requested Stone & Webster, Inc. (S&W), the designated Independent Engineer, to conduct “an impartial ‘top down’ review of the physical work percent complete of [Ahlborg’s] contractual ‘scope of the work.’ ” On August 27, 1999, S&W submitted a report of its “independent evaluation” to Ahlborg and MHI. S&W’s report was based on a “walk down of the entire facility to identify the work locations and to understand the status of the work completed to date,” a review with each of the parties’ representatives of the “schedules of values and individual pay items,” the assignment of a “percent complete” for each item set out in the requisition “based on each party’s interpretation of the ‘scope of the work’ and [its] status as of August 25, 1999.” S&W concluded that Ahlborg had completed eighty percent of the “scope of the work” covered in the requisition.

S&W acknowledged in its report that three factors had a “direct impact on the accuracy” of its conclusion: (1) both Ahlborg and MHI disputed the scope of the work to be performed by Ahlborg under their contract; (2) there was insufficient time to conduct an in-depth assessment; and (3) amendments to the contract had “skewed the schedule of values to the point where it [did] not appear to represent the actual value of scope of work items.”

A little over two weeks later, on September 13, 1999, and consistent with the provisions of section 10.1 of the contract, Ahlborg gave timely notice to MHI that (1) it was asserting its right to immediate payment on the requisition based on S&W’s conclusion that its work was eighty percent complete; (2) it was reserving its right under section 10.1 to further arbitration on that portion of S&W’s determination of the percentage of the work completed; and (3) it was demanding immediate arbitration of several disputed issues that would have an effect on [388]*388future requisitions.1 Unlike Ahlborg, MHI did not give any notice pursuant to section 10.1 that it was reserving its right to further arbitration on any disputed portion of S&W’s report of August 27, 1999.

Three days later, on September 16, 1999, Ahlborg brought the present action against MHI alleging, inter alla, that MHI had failed to make payments due under the contract, had refused to authorize payment for additional “scopes of work” performed by Ahlborg at MHI’s request, had intentionally and deceptively failed to inform Ahlborg that its (MHI’s) financing was inadequate to fund the contractual or increased scope of the work, and had failed to honor its (MHI’s) contractual obligations in connection with the default of its designated contractor. Based on these allegations, Ahlborg asserted claims for breach of contract, quantum meruit, and violations of G. L. c. 93A, § 11. In addition to its various requests for relief based on those claims, Ahlborg requested an order confirming S&W’s August 27, 1999, report, and ordering MHI to make payment on requisition number 12, as well as an order to compel MHI to proceed to arbitration.

MHI filed an answer and counterclaim for breach of contract, alleging that Ahlborg had failed through its own dereliction to achieve substantial and final completion of the work under the contract and that the work it had performed was defective. As for Ahlborg’s separate request for confirmation of S&W’s report, MH3 was silent.

In the meantime, on October 15, 1999, S&W issued a lengthy “Independent Engineer’s Report,” perhaps in response to Ahlborg’ s September 13, 1999, demand for arbitration on the issues set out in note 1, supra. S&W set out in this report its determination with respect to the scope of the work to be completed under the parties’ contract and an estimate of the cost to complete the remaining scope of work.

About six weeks thereafter, on December 2, 1999, Ahlborg [389]*389renewed its request for confirmation of S&W’s report of August 27, 1999, pursuant to G. L. c. 251, § 11. It accompanied the motion with a copy of the contract, S&W’s report of August 27, 1999, and the affidavit of its (Ahlborg’s) project director for the shipyard work, Michael Harrington. In his affidavit, Harrington states that eighty percent of the contract value of $22,848,176, less the amount which Ahlborg had been paid, $16,078,949, left the “undisputed amount” of $2,199,592 due and owing Ahlborg on the requisition. MHI opposed confirmation of S&W’s report of August 27, 1999.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O. Ahlborg & Sons, Inc. v. United States
74 Fed. Cl. 178 (Federal Claims, 2006)
MBNA America, NA v. Silva
2006 Mass. App. Div. 117 (Mass. Dist. Ct., App. Div., 2006)

Cite This Page — Counsel Stack

Bluebook (online)
840 N.E.2d 977, 65 Mass. App. Ct. 385, 2006 Mass. App. LEXIS 34, Counsel Stack Legal Research, https://law.counselstack.com/opinion/o-ahlborg-sons-inc-v-massachusetts-heavy-industries-inc-massappct-2006.