Nstar Electric Company v. United States

CourtUnited States Court of Federal Claims
DecidedJanuary 6, 2026
Docket20-529
StatusPublished

This text of Nstar Electric Company v. United States (Nstar Electric Company v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nstar Electric Company v. United States, (uscfc 2026).

Opinion

In the United States Court of Federal Claims Nos. 20-529 & 22-771 (Consolidated) (Filed: December 19, 2025) (Reissued: January 6, 2026) 1

************************

NSTAR ELECTRIC COMPANY,

Plaintiff,

v.

THE UNITED STATES,

Defendant,

and

HOLTEC PILGRIM, LLC,

Defendant-Intervenor.

********************** **

Defendant.

1 This opinion was initially filed under seal to afford the parties an opportunity to propose appropriate redactions. They did not propose any redactions. This opinion thus appears in full. Richard J. Conway, Washington, D.C., for plaintiff, NSTAR Electric Company.

Adam Kent Israel, Birmingham, AL, for intervenor defendant, Holtec Pilgrim, LLC.

Evan Wisser, Senior Trial Attorney, United States Department of Justice, Civil Division, Commercial Litigation Branch, Washington, D.C., for defendant, the United States, with whom were Brett A Shumate, Acting Assistant Attorney General, Patricia M. McCarthy, Director, Lisa L. Donahue, Assistant Director, and Brighton Springer, Department of Energy, of counsel.

OPINION 2

BRUGGINK, Senior Judge.

Pending are the government’s and Holtec Pilgrim, LLC’s (“Holtec”) motions for summary judgment against plaintiff, NSTAR Electric Company (“NSTAR”), and NSTAR’s cross-motion for summary judgment. This case centers on the Pilgrim nuclear power plant in Plymouth, Massachusetts. Despite government promises to the contrary, spent nuclear fuel (“SNF”) has accumulated at the Pilgrim plant for decades. To cover SNF storage costs 2 This is the twelfth opinion from this court and the United States Court of Appeals for the Federal Circuit related to this dispute. See Boston Edison Co. v. United States, 64 Fed. Cl. 167 (2005) (“Boston Edison I”); Boston Edison Co. v. United States, 67 Fed. Cl. 63 (2005) (“Boston Edison II”); Boston Edison Co. v. United States, 80 Fed. Cl. 468 (2008) (“Boston Edison III”), appeal dismissed and remanded, Boston Edison Co. v. United States, 299 Fed. Appx. 956 (Fed. Cir. 2008) (“Boston Edison IV”); Boston Edison Co. v. United States, 93 Fed. Cl. 105 (2010) (“Boston Edison V”), aff’d in part, rev’d in part, and remanded, Boston Edison Co. v. United States, 658 F.3d 1361 (Fed. Cir. 2011) (“Boston Edison VI”); Boston Edison Co. v. United States, 106 Fed. Cl. 330 (2012) (“Boston Edison VII”); Entergy Nuclear Generation Co. v. United States, 130 Fed. Cl. 466 (2017) (“Entergy”); Boston Edison Co. v. United States, 152 Fed. Cl. 358 (2021) (“Boston Edison VIII”); Boston Edison Co. v. United States, 156 Fed. Cl. 632 (2021) (“Boston Edison IX”); Boston Edison Co. v. United States, 157 Fed. Cl. 772 (2022) (“Boston Edison X”).

2 incurred after the commencement of decommissioning at Pilgrim, the current owner—Holtec—has expended money from Pilgrim’s decommissioning trust fund (“decommissioning fund”).

Holtec has sued the government for damages related to the Department of Energy’s (“DOE”) failure to pick up Pilgrim’s SNF, including Holtec’s post-decommissioning SNF storage costs. NSTAR, Pilgrim’s former owner, has also sued the government for those same post- decommissioning SNF storage costs. Thus, both NSTAR and Holtec are basically seeking the same damages, creating a classic “two dogs, one bone” scenario.

This case is the third and latest iteration of NSTAR’s twenty-six-year legal battle with the government to recover damages caused by DOE’s original 1998 breach. This matter was transferred to the undersigned on October 1, 2024.

NSTAR claims that, when it sold Pilgrim to Holtec, 3 it retained a claim against the government for any money spent from the decommissioning fund on SNF storage costs incurred after decommissioning had begun. The damage to NSTAR allegedly flows from the fact that it funded the decommissioning fund, which it then transferred to Holtec. NSTAR’s claim thus extends and indeed is limited to funds that were expended from the decommissioning fund after closing on the sale of Pilgrim. According to NSTAR, it—not Holtec—is the proper plaintiff to sue the government for money currently being expended from the fund on post- decommissioning SNF storage at Pilgrim.

The government and Holtec now move for summary judgment. They argue that NSTAR, when it sold Pilgrim to Holtec, gave up and did not retain any claims for damages arising after the sale because those claims had not yet accrued as required by the sale agreement. NSTAR responds that it retained claims arising from expenditure of money from the decommissioning fund on post-decommissioning SNF storage costs, irrespective of whether that money was spent before or after the sale. NSTAR primarily relies on a series of decisions by Judge Lettow—Boston Edison VII, 106 Fed. Cl. 330 (2012), Entergy, 130 Fed. Cl. 466 (2017), Boston

3 At the time of the sale in 1999, NSTAR was known as Boston Edison Company, and Holtec used the name Entergy Nuclear Generation Company. For clarity, we refer to both companies by their current names. 3 Edison VIII, 152 Fed. Cl. 358 (2021), and Boston Edison IX, 156 Fed. Cl. 632 (2021)—in which the late judge consistently found that NSTAR did, in fact, retain the right to bring the claim it now asserts. Critically, the government’s and Holtec’s respective motions for summary judgment explicitly call into question the correctness of those four decisions and ask that we put an end to NSTAR’s pursuit of compensation for breach.

For the reasons set out below, we agree with Holtec and the government and grant their respective motions for summary judgment.

BACKGROUND

I. PAST PROCEEDINGS

A. The Pilgrim Sale

1. NSTAR Prepares to Sell Pilgrim

In 1983, NSTAR contracted with DOE for DOE to collect SNF from NSTAR’s Pilgrim Nuclear Power Station, located in Plymouth, Massachusetts. 4 Boston Edison VI, 658 F.3d 1361, 1364 (Fed. Cir. 2011). As with other nuclear operators, DOE agreed to collect Pilgrim’s SNF no later than January 1998. Id. DOE did not, however, begin collecting SNF by the January 1998 deadline and has yet to do so. NSTAR, for its part, consistently paid fees to the government and maintained a decommissioning trust fund. Id.

NSTAR maintained a decommissioning trust fund to comply with the applicable regulatory scheme, which requires nuclear plant operators to choose between three options to “provide reasonable assurance that funds will be available for the decommissioning process”: (1) prepayment, (2) an external sinking fund, or (3) a surety, insurance, “or other guarantee method.” 10 C.F.R. § 50.75(a), (e)(1)(i)–(iii). Here, NSTAR opted to create an external sinking fund in the form of a trust. Holtec’s Mot. Summ. J. 3, ECF No. 164. The trust was “maintained by setting funds aside periodically in an account segregated from licensee assets and outside the administrative control of the licensee” such that “the total amount of funds would be sufficient to pay decommissioning costs.” 10 C.F.R. § 50.75(e)(1)(ii). Ratepayers funded the

4 The “Standard Contract” mandated by regulation is found at 10 C.F.R. pt. 961. 4 trust fund by paying decommissioning fees, 5 and NSTAR invested the funds until needed for decommissioning. See Holtec’s Mot. Summ. J. 3, ECF No. 164; Conn. Yankee Atomic Power Co. v. United States, 169 Fed. Cl. 531, 537 (2024).

In 1997, Massachusetts enacted legislation to restructure the State’s electric utility industry. Boston Edison VI, 658 F.3d at 1364. As part of that restructuring, NSTAR had to divest itself of the Pilgrim plant. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Resource Conservation Group, LLC v. United States
597 F.3d 1238 (Federal Circuit, 2010)
Ex Parte McCardle
74 U.S. 506 (Supreme Court, 1869)
Messenger v. Anderson
225 U.S. 436 (Supreme Court, 1912)
Montana v. United States
440 U.S. 147 (Supreme Court, 1979)
Arizona v. California
460 U.S. 605 (Supreme Court, 1983)
United States v. Mendoza
464 U.S. 154 (Supreme Court, 1984)
Arizona v. California
466 U.S. 144 (Supreme Court, 1984)
Christianson v. Colt Industries Operating Corp.
486 U.S. 800 (Supreme Court, 1988)
Richards v. Jefferson County
517 U.S. 793 (Supreme Court, 1996)
Taylor v. Sturgell
553 U.S. 880 (Supreme Court, 2008)
James L. Murphy v. The United States
993 F.2d 871 (Federal Circuit, 1993)
Fallini v. United States
56 F.3d 1378 (Federal Circuit, 1995)
Intergraph Corporation v. Intel Corporation
253 F.3d 695 (Federal Circuit, 2001)
United States v. Cinemark Usa, Inc.
348 F.3d 569 (Sixth Circuit, 2003)
Indiana Michigan Power Company v. United States
422 F.3d 1369 (Federal Circuit, 2005)
Whiteman v. Department of Transportation
688 F.3d 1336 (Federal Circuit, 2012)
Gabelli v. Securities & Exchange Commission
133 S. Ct. 1216 (Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Nstar Electric Company v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nstar-electric-company-v-united-states-uscfc-2026.