N.P., Inc. v. Turboff

111 S.W.3d 40, 46 Tex. Sup. Ct. J. 698, 2003 Tex. LEXIS 66, 2002 WL 32098154
CourtTexas Supreme Court
DecidedMay 22, 2003
Docket01-1167
StatusPublished
Cited by4 cases

This text of 111 S.W.3d 40 (N.P., Inc. v. Turboff) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
N.P., Inc. v. Turboff, 111 S.W.3d 40, 46 Tex. Sup. Ct. J. 698, 2003 Tex. LEXIS 66, 2002 WL 32098154 (Tex. 2003).

Opinion

Justice ENOCH

In Olmos v. Pecan Grove Municipal Utility District, 1 the court of appeals held that the holder of title to utility facilities was entitled to the construction costs reimbursement for those facilities from the Municipal Utility District that agreed to buy the facilities when constructed. In that opinion, the court explained that title to the facilities had not been severed from the land otherwise conveyed, and thus, the right to reimbursement of the construction costs passed to the current property owner and did not remain with the original developer. 2 It is this discussion into which Jerald A. Turboff and his attorney, Julius Glickman, attempt to bring their complaint that though N.P., Inc. owns title to the utility facilities, Turboff and Glickman are entitled to the construction costs reimbursement because Turboff reserved the right to that reimbursement when he lost title to the facilities. The court of appeals agreed with the trial court that Turboff and Glickman prevail on their argument. 3 But we disagree. We reverse the court of appeals’ judgment and render judgment for N.P., Inc.

On February 29, 1984, Turboff, a real estate developer, entered into a contract with the Harris County Municipal Utility District No. 36 (the “MUD”) for the construction of water, sewer, and drainage facilities on a 135-acre tract of land Tur-boff was developing in north Houston. Under the terms of the contract, Turboff promised to build the utility facilities according to certain MUD-approved plans and specifications. In addition, Turboff agreed to convey the facilities to the MUD by “general warranty deed or other similar instrument” and to provide proof of title, “free and clear” of all hens. In exchange, the MUD promised to purchase the facilities upon receiving title to them if, among other things, the facilities were constructed according to the plans and completed in a “good and workmanlike manner.” Under the contract, the purchase price acted as a right of reimbursement for TurbofPs construction costs.

In 1983, Turboff borrowed $26 million from First Texas Savings Association to purchase and subsequently develop the tract. Of that $26 million, Turboff spent nearly $2 million installing the utility facilities. As security for the loan, First Texas received a hen on the property.

Before Turboff completed the construction and conveyed the facilities to the MUD as required under the contract, First Texas declared Turboff in default on his loan. Because Turboff claimed that First Texas wrongfully placed him in default, he sued First Texas. Attorney Julius Glick-man represented Turboff in the htigation, and Turboff assigned to Glickman, as a part of his fees, an interest in any MUD reimbursement payments Turboff would receive under his 1984 contract with the MUD. (Because Glickman’s claim is derivative of TurbofFs interest in the MUD proceeds from his MUD contract, we will hereafter refer to Turboff and Glickman as “Turboff.”) In June 1986, while the htigation was pending, First Texas foreclosed on the property.

On December 27, 1988, just thirty minutes before the Federal Savings and Loan *42 Insurance Corporation (“FSLIC”) placed First Texas in receivership, First Texas and Turboff settled all claims between them. According to the settlement agreement, First Texas retained title to the north Houston property, including the utility facilities, but gave up any claim it had in the construction costs reimbursement under Turboffs 1984 contract with the MUD. In addition, First Texas paid Tur-boff $400,000 for developing the property and released Turboff from any future claims by First Texas.

First Texas released its interest in the MUD reimbursement payments to Turboff not only in the settlement agreement but also in a separate document, the Stipulation of Interest. The Stipulation warranted that Turboff was the “sole owner[ ]” of the MUD receivable payments, and any proceeds due under the 1984 MUD contract would be payable to Turboff. First Texas also sent notice to the MUD, advising it of the settlement and its terms. After being declared insolvent by the FSLIC, First Texas’s assets were transferred to First Nationwide Bank.

On February 10, 1995, N.P., Inc., through its owner and trustee, Dr. C.N. Papadopoulos, purchased the property from First Nationwide, including the existing utility facilities. First Nationwide transferred title to the property, but in both the Real Estate Purchase Agreement and the Warranty Deed, First Nationwide expressly excluded from the conveyance any right to the MUD reimbursement payments. Upon taking possession of the property, N.P., Inc. repaired the existing utilities and constructed and installed additional facilities.

On February 25,1997, N.P., Inc. entered into its own contract with the MUD. In that contract, the MUD mentioned its pri- or 1984 contract with Turboff, but it stated that the “Developer [N.P., Inc.] is the current owner of ... all of the land within the Service Area.” Similar to the 1984 contract with Turboff, the MUD agreed to purchase the utility facilities upon certain conditions being met, and N.P., Inc. agreed to transfer ownership and possession of the facilities to the MUD. But the 1997 contract stated:

[A] controversy exists as to the rightful recipient of the Purchase Price for the Existing Facilities, and, notwithstanding the foregoing or any other part or provision hereof to the contrary, the [MUD] shall not be obligated hereunder to pay to [N.P., Inc.] all or any portion of the Purchase Price for the Existing Facilities unless and until such dispute covering the rightful payee of the Purchase Price is settled by mutual agreement, finally adjudicated or otherwise resolved to the reasonable satisfaction of the [MUD] such that payment of the Purchase Price for the Facilities can be made by the [MUD] without undue risk of wrongful or duplicate payments.

In 1998, Turboff sued N.P., Inc., seeking a declaratory judgment that Turboff, not N.P., Inc., was entitled to the MUD payments according to the terms of the 1984 contract. Turboff also asked the trial court to order N.P., Inc. to convey title to the facilities to the MUD. Both parties moved for summary judgment. After reviewing the summary judgment evidence, the trial court found as a matter of law that although N.P., Inc. owned the existing facilities, Turboff owned all sums due from the MUD. But the trial court also held that Turboff had no right to compel N.P., Inc. to convey the facilities to the MUD. Thus, all parties appealed.

On appeal, N.P., Inc., citing to Olmos, 4 , argued that as the owner of the facilities, it *43 was entitled to the MUD payments. But the court of appeals concluded that Tur-boff was entitled to the reimbursement not only because N.P., Inc. had notice of Tur-boffs claim to the MUD proceeds, reflected in both the Real Estate Purchase Agreement between N.P., Inc. and First Nationwide and in N.P., Ine.’s Warranty Deed, but also because Turboff specifically reserved the right to the reimbursement through his transactions with First Texas. 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hanover Ins v. Binnacle Development
57 F.4th 510 (Fifth Circuit, 2023)
Berbos v. Krage
2008 SD 68 (South Dakota Supreme Court, 2008)
Daniel Lee Alford, III v. James J. Alford
Court of Appeals of Texas, 2007

Cite This Page — Counsel Stack

Bluebook (online)
111 S.W.3d 40, 46 Tex. Sup. Ct. J. 698, 2003 Tex. LEXIS 66, 2002 WL 32098154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/np-inc-v-turboff-tex-2003.