Nowicki Construction Co. v. Panar Corp., N.V.

492 A.2d 36, 342 Pa. Super. 8, 1985 Pa. Super. LEXIS 7253
CourtSupreme Court of Pennsylvania
DecidedApril 26, 1985
Docket2216
StatusPublished
Cited by23 cases

This text of 492 A.2d 36 (Nowicki Construction Co. v. Panar Corp., N.V.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nowicki Construction Co. v. Panar Corp., N.V., 492 A.2d 36, 342 Pa. Super. 8, 1985 Pa. Super. LEXIS 7253 (Pa. 1985).

Opinion

BECK, Judge:

In this appeal we are asked to determine the extent, if any, to which two written documents signed by authorized agents of appellant Panar Corporation, N.V. (Panar), and appellee Nowicki Construction Company, Inc. (Nowicki), limit the amount collectible under Nowicki’s mechanics’ lien claim against Panar. 1 For the following reasons, we affirm the trial court’s decision that neither document restricts Nowicki’s mechanics’ lien claim and that Nowicki is accordingly entitled to collect $37,460.99 on its lien claim.

*12 By a written contract of November 5, 1978, Nowicki undertook construction of a stone addition to a residence owned by Panar and occupied by Mr. and Mrs. Deutsch. In pertinent part, the contract provided that

[i]n no event shall the total cost of the [stone addition] project ... exceed the sum of $100,000. — (one hundred thousand dollars). Payment of all invoices for completed work or delivered materials shall be paid by Panar Corporation N.V. at the end of each week____ Labor invoices will also ... be paid at the end of each week in which they are presented.

In other words, the November 5 contract contemplated a “pay-as-you-go” arrangement with an aggregate cost of $100,000 or less.

Between November 6, 1978, and July 18, 1979, Nowicki submitted more than $100,000 in material and labor invoices which Panar partially paid in the amount of $122,327.13. In light of the unpaid balance on the submitted invoices, on July 23, 1979, Nowicki presented Panar with a written document that outlined certain work remaining to be done on the residential addition and stated that Nowicki’s “fee for the completion of [the outlined] work [was] $5,000.00” The document further declared that Nowicki had “discounted in excess of $30,000.00 to [Panar’s] account.” Finally, the document bore a handwritten addendum, to wit, “All work to be completed by Aug. 4, ’79 except gutters + drain spout, shutters, hand rail at steps for payment of $5,000— completion fee.” Authorized agents of Panar and Nowicki signed the document and initialled the addendum.

Thereafter, Panar did not pay Nowicki $5,000 pursuant to the parties’ July 23 agreement, and Nowicki filed a mechanics’ lien claim against Panar. On November 13, 1979, Nowicki instituted suit on the lien claim for $38,-529.12, 2 the balance due on the invoices tendered to Panar *13 for materials and labor supplied by Nowicki after the signing of the parties’ November 5 contract. Panar contended before the trial court, and again argues in this appeal, that Nowicki is not entitled to recover on its mechanics’ lien claim either because the parties’ November 5 contract restricted Nowicki’s potential payment to $100,000 which amount plus an additional $22,327.13 Nowicki has already received or, alternatively, because Nowicki failed to finish certain work outlined in the parties’ July 23 agreement which was a substituted contract that extinguished any prior agreement of the parties and limited Nowicki’s potential payment to $5,000. 3

“[A] mechanic’s lien is a statutory proceeding, the action in rem being in the nature of collateral security for the payment of the debt due for work done or materials furnished” in accordance with a contract, express or implied. Hoffman Lumber Co. v. Mitchell, 170 Pa.Super. 326, 331, 85 A.2d 664, 667 (1952), allocatur denied; Murray v. Zemon, 402 Pa. 354, 167 A.2d 253 (1961); Fisher Sprinkler Co. v. Ide, 305 Pa.Super. 554, 451 A.2d 1015 (1982); Sections 201, 301 & 503 of the Mechanics’ Lien Law of 1963, Act of August 24, 1963, P.L. 1175, 49 P.S. §§ 1201, 1301 & 1503.

Indisputably, the parties’ original written contract of November 5 contained a $100,000 ceiling. However, the evidence of record clearly shows that the November 5 contract was not given strict adherence by either party. Nowicki submitted invoices totalling more than $100,000. Panar made partial payments of $122,327.13 on the ten *14 dered invoices but did not promptly pay the full amount of all invoices as they were presented. That is, Panar’s payments did not keep abreast of Nowicki’s requests for payment as the building work progressed. Reproduced Record at 40a-41a.

At trial, Nowicki’s president and sole shareholder, Allan J. Nowicki, explained that the discrepancies between Nowicki’s actions and the parties’ November 5 contract resulted from the parties’ subsequent oral modifications of the November 5 contract. E.g., Reproduced Record at 21a-31a, 158a. Mr. Nowicki testified, for example, that although the building plans designated vinyl flooring in the bathroom, Panar (acting through its agents Mr. and Mrs. Deutsch) later requested that imported Italian marble tiles be used. Reproduced Record at 27a, 353a. Mr. Nowicki stated that the use of marble tiles not only increased construction costs but also delayed completion of the work since the marble had to be specially ordered and installed. Reproduced Record at 44a, 353a. Regarding the marble tiles, Mrs. Deutsch indicated that she and her husband had always assumed that such flooring would be used in the bathroom but had never discussed the use of such materials until after the parties had signed the November 5 contract and work had begun on the residential addition. Reproduced Record at 234a. The architects who testified as expert witnesses for Panar and Nowicki both noted deviations between the building plans and the actual construction performed but lacked personal knowledge as to the reason for the deviations. Reproduced Record at 260a, 316a, 330a-333a.

Since there was evidence of record that the parties had made subsequent oral modifications of their November 5 contract by altering the building specifications and correspondingly, the building costs and building time, the trial court did not err in concluding that the $100,000 restriction in the November 5 contract did not bar Nowicki’s mechanics’ lien claim for materials and labor furnished beyond that amount.

*15 Next, we consider whether the parties’ July 23 written agreement prevents or limits Nowicki’s recovery under its lien claim. Panar regards the July 23 agreement as a substituted contract which discharged any prior agreement of the parties and exclusively established the conditions for Nowicki’s recovery against Panar. Nowicki views the July 23 agreement as an unperformed accord which did not discharge the previous obligations of the parties.

Whether an agreement constitutes a substitute contract or an accord is a matter of interpretation. Hydro-Flex, Inc. v. Alter Bolt Co., 223 Pa.Super. 228, 296 A.2d 874 (1972); Restatement (Second) of Contracts § 279 comment c (1979).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.C. Penney Corp. v. GFM 23
301 A.3d 927 (Superior Court of Pennsylvania, 2023)
Geesey v. Citimortgage, Inc.
135 F. Supp. 3d 332 (W.D. Pennsylvania, 2015)
Arcadia Petroleum Ltd. v. Sun International Ltd.
192 F. App'x 164 (Third Circuit, 2006)
Kripp v. Kripp
784 A.2d 158 (Superior Court of Pennsylvania, 2001)
Fleming v. CNA Insurance
52 F. Supp. 2d 499 (E.D. Pennsylvania, 1999)
Paramount Aviation v. Agusta
Third Circuit, 1999
Constitution Bank v. Kalinowski
38 F. Supp. 2d 384 (E.D. Pennsylvania, 1999)
Clemens v. West Milton State Bank (In Re Clemens)
197 B.R. 779 (M.D. Pennsylvania, 1996)
Occidental Chemical Corp. v. Environmental Liners, Inc.
859 F. Supp. 791 (E.D. Pennsylvania, 1994)
PNC Bank, National Ass'n v. Balsamo
634 A.2d 645 (Superior Court of Pennsylvania, 1993)
Graham v. Parkside Realty, Inc.
21 Pa. D. & C.4th 243 (Pike County Court of Common Pleas, 1993)
Nernberg & Laffey v. Patterson
601 A.2d 1237 (Superior Court of Pennsylvania, 1991)
In Re Chateaugay Corp.
116 B.R. 887 (S.D. New York, 1990)
LTV Corp. v. Aetna Casualty & Surety Co.
116 B.R. 887 (S.D. New York, 1990)
Kelly v. Hannan
566 A.2d 310 (Superior Court of Pennsylvania, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
492 A.2d 36, 342 Pa. Super. 8, 1985 Pa. Super. LEXIS 7253, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nowicki-construction-co-v-panar-corp-nv-pa-1985.