Novak & Co. v. Travelers Indemnity Co.

56 A.D.2d 418, 392 N.Y.S.2d 901, 1977 N.Y. App. Div. LEXIS 10454
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 28, 1977
StatusPublished
Cited by9 cases

This text of 56 A.D.2d 418 (Novak & Co. v. Travelers Indemnity Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Novak & Co. v. Travelers Indemnity Co., 56 A.D.2d 418, 392 N.Y.S.2d 901, 1977 N.Y. App. Div. LEXIS 10454 (N.Y. Ct. App. 1977).

Opinion

Shapiro, J.

Upon defendant’s motion "for an order pursuant to CPLR 3211 dismissing the complaint upon the grounds that plaintiffs cause of action is barred by the statute of limitation and release and that the complaint fails to state a cause of action,” the Special Term of the Supreme Court, Kings County, made an order entered April 23, 1976 "that The Travelers Indemnity Company’s motion for an order dismissing the complaint herein on the grounds that the complaint fails to state a cause of action, is hereby granted and the Court treats said motion as one for summary judgment under CPLR 3212 and hereby grants summary judgment dismissing plaintiffs complaint.”1 We affirm.

THE ISSUE

May the plaintiff recover on the bond given by the defendant to the New York City Housing Authority (Authority) to guarantee performance by Wilaka Construction Co., Inc. (Wilaka) of the terms of its contract with the Authority?

THE FACTS

Plaintiff entered into a contract with the Authority for the performance of plumbing work in connection with a project known as Independence Houses (Project). Contemporaneously, Wilaka similarly entered into a contract with the Authority for the performance of concrete foundation and general construction work at the Project (the contract).

By virtue of the provisions of the contract Wilaka was obligated to furnish the Authority with two separate bonds, designated respectively as a performance bond and a payment bond, and each was to be in an amount equal to 100% of the bid price. The purpose of the bonds was to keep the Authority adequately secured at all times against Wilaka’s failure to perform faithfully the work and all other obligations imposed [421]*421upon it by the contract, including its obligation to indemnify the Authority and others against loss and claims arising out of the performance of the work. In accordance therewith, the defendant issued the necessary bonds to assure the good and faithful performance by Wilaka of its contract with the Authority. Each of the bonds was in the sum of $6,187,000. The performance bond contains the following language: "This undertaking is for the benefit of all Subcontractors, Material-men, and workingmen having just claims and for the beneñt of all other third persons having just claims arising out of or in connection with the said Contract and Work performed thereunder, as well as for the benefit of the Owner itself, but the rights and equities of all other beneficiaries or obligees hereunder shall be subject and subordinate to those of the Owner. Should any beneficiary or obligee hereunder, other than the Owner, file or make claims against the Principal or Surety, the said Principal and Surety shall promptly thereafter, or in any event at least fifteen (15) days prior to the payment of such claims, notify the Owner by registered mail of such claims.” (Emphasis supplied.)

The payment bond contains the following language: "All persons who have performed labor, rendered services or furnished materials and supplies, as aforesaid, shall have a direct right of action against the Principal and his, its or their successors and assigns, and the Surety herein, or against either or both or any of them and their successors and assigns. Such persons may sue in their own name and may prosecute the suit to judgment and execution without the necessity of joining with any other person as party plaintiff.”

Plaintiff’s and Wilaka’s contracts with the Authority provided that each "contractor shall lay out and install his work at such time or times and in such manner as not to delay or interfere with the progress of the work by each of the other contractors” and that "[i]f any other contractor * * * shall suffer loss, damage or delay through the acts or omissions on the part of the contractor herein * * * the contractor herein agrees to reimburse such other contractor * * * for his loss or damage.” This provision, subdivision b of section 10 of the contract, goes on: "If such other contractor * * * shall assert any claim against the Authority on account of any loss, damage, or delay alleged to have been sustained, the Authority shall notify the contractor who shall save the Authority harmless against all claims, losses, costs, expenses, fees and [422]*422all other liabilities of whatsoever kind”. Similarly, subdivision a of section 10 of the contract, which deals with loss caused by other contractors, declares that if the contractor should "sustain any loss, damage, or delay through any act or omission of any other contractor having a contract with the Authority for the performance of work * * * upon the site * * * which may be necessary to be performed in aid of the Work hereunder * * * the Contractor shall have no claim against the Authority for such loss, damage or delay, but shall have recourse solely to such other contractor.” Thus, both subdivisions a and b of section 10 of the contracts between the Authority and the plaintiff and the Authority and Wilaka make it clear that those provisions of the contract were intended to limit each contractor’s right of recourse for damage resulting from delay caused by another contractor to the contractor causing the delay and to absolve the Authority from liability.

Contending that Wilaka had failed to perform its work under the contract, the plaintiff sued Wilaka, the Authority and others to recover the damages which it thereby sustained. In that action plaintiff recovered a judgment against Wilaka in the amount of $390,875.75.

Thereafter plaintiff commenced this action against the defendant under both the performance bond and the payment bond to recover for the losses and damages which it sustained under the contract and the default of Wilaka thereunder.2

THE APPLICABLE LAW

The cases cited in the briefs are in agreement that the test [423]*423of whether a contractor’s bond, be it a performance bond or a payment bond, or both, is intended to grant a third party the right to sue upon it depends upon whether it manifests a clear intent to grant that right to the third party. Thus, in the leading case of Fosmire v National Sur. Co. (229 NY 44, 47-48), Judge Cardozo, speaking for the court, and holding that the plaintiff, a laborer employed by the principal who had contracted to build part of a State highway, and who sought to recover wages owed him by his employer, the contractor, from the issuer of his employer’s performance bond, could not recover on the bond, said: "In so holding, we put our decision upon the single ground that the bond, read in its entirety, is inconsistent with an intention that the plaintiff and others in like position should have the right to sue upon it. If that intention is absent, the right to sue will be denied (Simson v. Brown, 68 N.Y. 355).”

In McClare v Massachusetts Bonding & Ins. Co. (266 NY 371), the defendant bonded the Collar City Athletic Club of Troy, N.Y., which had been granted a license to conduct boxing and wrestling matches. The club was required by the State Athletic Commission to obtain a surety bond for faithful performance of the act providing for professional boxing bouts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Travelers Casualty & Surety Co. v. Dormitory Authority-State
735 F. Supp. 2d 42 (S.D. New York, 2010)
International Fidelity Insurance v. County of Rockland
98 F. Supp. 2d 400 (S.D. New York, 2000)
BIB Construction Co. v. Fireman's Insurance
214 A.D.2d 521 (Appellate Division of the Supreme Court of New York, 1995)
Huber Lathing Corp. v. Aetna Casualty & Surety Co.
132 A.D.2d 597 (Appellate Division of the Supreme Court of New York, 1987)
MGM Const. Corp. v. NJ Educ. Facilities Auth.
532 A.2d 764 (New Jersey Superior Court App Division, 1987)
Granite Computer Leasing Corp. v. Travelers Indemnity Co.
582 F. Supp. 1279 (S.D. New York, 1984)
Herbert F. Darling, Inc. v. City of Niagara Falls
69 A.D.2d 989 (Appellate Division of the Supreme Court of New York, 1979)
Kornblut v. Chevron Oil Co.
62 A.D.2d 831 (Appellate Division of the Supreme Court of New York, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
56 A.D.2d 418, 392 N.Y.S.2d 901, 1977 N.Y. App. Div. LEXIS 10454, Counsel Stack Legal Research, https://law.counselstack.com/opinion/novak-co-v-travelers-indemnity-co-nyappdiv-1977.