Nova Casualty Co. v. Turner Construction Co.

335 S.W.3d 698, 2011 Tex. App. LEXIS 996, 2011 WL 480599
CourtCourt of Appeals of Texas
DecidedFebruary 10, 2011
Docket14-09-00733-CV
StatusPublished
Cited by8 cases

This text of 335 S.W.3d 698 (Nova Casualty Co. v. Turner Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nova Casualty Co. v. Turner Construction Co., 335 S.W.3d 698, 2011 Tex. App. LEXIS 996, 2011 WL 480599 (Tex. Ct. App. 2011).

Opinion

SUBSTITUTE OPINION ON REHEARING

ADELE HEDGES, Chief Justice.

We deny appellant’s motion for rehearing en banc as moot, withdraw our opinion of January 11, 2011, and issue this substitute opinion on rehearing. In this performance bond dispute, Nova Casualty Company (“Nova”), the surety, challenges the summary judgment granted in favor of Turner Construction Company (“Turner”), the surety bond obligee. In three issues, Nova asserts that the trial court erred by (1) granting summary judgment because Turner failed to terminate the obligor, Box or Container Automation, Inc. (“BOCA”), from the underlying contract secured by *700 the performance bond; (2) granting summary judgment because Turner failed to provide sufficient notice of BOCA’s default on the underlying contract to enable Nova to exercise its performance options under the bond; and (3) awarding attorney’s fees and pre-judgment interest to Turner. We affirm.

BACKGROUND

The City of Houston (the “City”) hired Turner as the general contractor to build a new cargo facility at Bush Intercontinental Airport. The contract between the City and Turner provided for the assessment of liquidated damages against Turner if Turner were late in completing the project. In January 2004, Turner subcontracted with BOCA to fabricate and install a baggage handling system for the new facility. Turner agreed to pay BOCA a subcontract price of $415,000. This subcontract was time sensitive in that it required BOCA to install the baggage handling system during a narrow time window near the end of the entire project. In Article III, the subcontract provided:

Should the progress of the Work of the Project be delayed, disrupted, hindered, obstructed, or interfered with by any fault or neglect or act or failure to act of the subcontractor ... so as to cause any additional cost, expense, liability or damage to Turner ... the Subcontractor and its surety shall and does hereby agree to compensate Turner ... for and indemnify [it] against all such costs, expenses, damages and liability.

The subcontract provided in Article XI that BOCA’s failure to fully perform or satisfy any of its contractual obligations (among other things) constituted a default entitling Turner to:

the right, in addition to any other rights and remedies provided by this Agreement and the other Contract Documents or by law, after three (3) days written notice to [BOCA] mailed or delivered to the last known address of the latter, (a) to perform and furnish through itself or through others any such labor or materials for the Work and to deduct the cost thereof from any monies due or to become due to [BOCA] under this Agreement, and/or (b) to terminate the employment of [BOCA] for all or any portion of the Work, enter upon the premises and take possession, for the purpose of completing the Work, of all materials, equipment, scaffolds, tools appliances and other items thereon, all of which [BOCA] hereby transfers, assigns and sets over to Turner for such purpose, and to employ any person or persons to complete the Work and provide all the labor, services, materials, equipment and other items required therefor....' [I]f the unpaid balance of the amount to be paid under this Agreement shall exceed the cost and expense incurred by Turner in completing the Work, such excess shall be paid by Turner to [BOCA], but if such cost and expense shall exceed such unpaid balance, then [BOCA] and its surety, if any, shall pay the difference to Turner,

(emphasis added). The subcontract additionally required BOCA to obtain and furnish a performance bond in favor of Turner.

BOCA obtained a performance bond from Nova in the amount of the subcontract price. The performance bond Nova issued to BOCA was a standard performance bond known in the surety industry as an A-311 bond. The bond provided the following remedies available to Turner against Nova in the event that BOCA defaulted on the subcontract:

NOW, Therefore, the Condition of this Obligation is such that, if [BOCA] shall promptly and faithfully perform said subcontract, then this obligation shall be null and void; otherwise it shall remain in full force and effect.

*701 Whenever [BOCA] shall be, and be declared by [Turner] to be in default under the subcontract, [Turner] having performed its obligations thereunder:

(1) [Nova] may promptly remedy the default subject to the provisions of paragraph 3 herein, or:
(2) [Turner] after reasonable notice to [Nova] may, or [Nova] upon demand of [Turner] may arrange for the performance of [BOCA] ’s obligation under the subcontract subject to the provisions of paragraph 3 herein:
(3) The balance of the subcontract price, as defined below, shall be credited against the reasonable cost of completing performance of the subcontract. If completed by [Turner], and the reasonable cost exceeds the balance of the subcontract price, [Nova] shall pay to [Turner] such excess, but in no event shall the aggregate liability of [Nova] exceed the amount of this bond....

The bond also incorporated the terms of the subcontract by reference: “[BOCA] has by written agreement dated 1/16/2004 entered into a subcontract with [Turner] ..., which subcontract is by reference made a part hereof....”

Turner made several payments to BOCA without objection under the subcontract. However, when BOCA was to begin installing the system, Turner sent a series of letters to BOCA regarding BOCA’s failure to meet its performance deadlines. None of these letters declared BOCA in default, and Nova was not copied on any of these letters. On November 9, 2004, Turner invoked Article XI of the subcontract by sending BOCA written notice giving it three days to cure its deficient performance. Turner elected to move forward under option (a) of this Article, which, as noted above, entitled Turner “to perform and furnish through itself or through others any such labor or materials for the Work and to deduct the cost thereof from any monies due or to become due to [BOCA] under this Agreement[.]” Turner did not notify Nova that it considered BOCA to be in default at that time.

On December 15, 2004, Turner notified Nova that BOCA had defaulted on the subcontract. Specifically, Turner faxed a letter to Nova which provided as follows:

The Principal, [BOCA], due to insufficient funds has not been able to pay for labor and material necessary to complete this Project. BOCA has requested that we provide labor and material on their behalf to complete the Project. This letter, therefore, constitutes notice of default by BOCA, Inc. per the terms of the bond. We request that you contact us immediately to review and resolve the non-payment issues for labor and material on this Project.

(emphasis added). Nova hired a consultant, Forcon International Corporation (“Forcon”) to investigate BOCA’s default. Forcon corresponded with Turner to determine whether BOCA had defaulted and the amount of Nova’s liability, if any, under the surety bond. Turner communicated with Forcon regarding the actions it took to complete the project, including the need to completely re-do much of BOCA’s work that had failed certain necessary tests.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
335 S.W.3d 698, 2011 Tex. App. LEXIS 996, 2011 WL 480599, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nova-casualty-co-v-turner-construction-co-texapp-2011.