Nottingham Construction Co. v. City of Waveland

291 F. App'x 665
CourtCourt of Appeals for the Fifth Circuit
DecidedSeptember 10, 2008
Docket08-60255
StatusUnpublished

This text of 291 F. App'x 665 (Nottingham Construction Co. v. City of Waveland) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nottingham Construction Co. v. City of Waveland, 291 F. App'x 665 (5th Cir. 2008).

Opinion

PER CURIAM: *

This case arises from a complaint filed by Nottingham Construction Company, L.L.C. (“Nottingham”) against the City of Waveland (“Waveland”) as a result of Waveland’s award of a construction project to Hemphill Construction Company (“Hemphill”) pursuant to a public bidding process. Nottingham alleges that the contract resulted from collusion, bid rigging and/or favoritism. The district court granted Waveland’s motion to dismiss on the basis of a statutory requirement that any appeal of a decision by a municipality be filed within ten days from the date of the decision. For the reasons stated herein, we affirm.

I.

In December 2006, Waveland received bids from numerous contractors for a sewer and water system reconstruction project (the “Project”). During the bidding process, Waveland’s engineer, Digital Engineering and Imaging, Inc., told Nottingham that it could not use excavated materials as select backfill on the project. This information was significant because Nottingham alleges that the use of excavated materials as select backfill, as opposed to hauling in new material to use as backfill, can dramatically reduce the expense of the project. The written communications concerning use of excavated materials as backfill were attached to Contract Addendum No. 2 for the Project at the request of Nottingham.

Nottingham’s bid of $27,472,620.00 was the second lowest among the contractors. Nottingham asserts that the use of excavated materials as select backfill would have reduced its bid for the project by $4,000,000.00. The lowest bid for the project was submitted by Hemphill in the amount of $23,639,425.00. Waveland awarded the contract to Hemphill, which was executed on April 4, 2007. Nottingham does not dispute that it knew the contract was awarded to Hemphill.

*667 After the project had been underway for several months, a Nottingham representative witnessed Hemphill using excavated materials as backfill. Nottingham contacted the engineering firm regarding the use of excavated materials as backfill and alleges that a representative of the engineering firm admitted that the materials were being used and also admitted that Hemphill was not required to use a deductive change order to reflect the lower costs. Nottingham alleges that since Hemphill was allowed to use excavated materials as backfill, the contract resulted from collusion, bid rigging, and/or favoritism. On August 29, 2007, Nottingham notified Waveland of its claim for damages and its protest of the award of the Project. Waveland sent a letter through its attorney denying Nottingham’s request for a hearing on its claim for damages. On October 19, 2007, Nottingham filed a Complaint against Waveland seeking damages it allegedly suffered when it was not awarded the contract for the Project.

In response to the complaint, Waveland filed a motion to dismiss challenging the timeliness of Nottingham’s complaint under Miss.Code Ann. § 11-51-75. The district court agreed that Nottingham’s complaint was not timely filed and dismissed it pursuant to Fed. R. Civ. Proc. 12(b)(6).

II.

We review de novo the district court’s order on a motion to dismiss under Rule 12(b)(6). In re Katrina Canal Breaches Litig., 495 F.3d 191, 205 (5th Cir.2007), cert, denied, Chehardy v. Allstate Indem. Co., — U.S. -, 128 S.Ct. 1231, 170 L.Ed.2d 63 (2008) and Xavier Univ. of La. v. Travelers Cas. Prop. Co. of Am,., — U.S.-, 128 S.Ct. 1230, 170 L.Ed.2d 63 (2008). “The court accepts all well-pleaded facts as true, viewing them in the light most favorable to the plaintiff.” Id. (internal quotations omitted). Because this case is in federal court based on diversity jurisdiction, we must follow Mississippi’s substantive law as interpreted by Mississippi’s highest court. See Erie R.R. Co. v. Tompkins, 304 U.S. 64, 78, 58 S.Ct. 817, 82 L.Ed. 1188 (1938); Am. Nat’l Gen. Ins. Co. v. Ryan, 274 F.3d 319, 328 (5th Cir.2001).

Miss.Code Ann. § 11-51-75 provides:
Any person aggrieved by a judgment or decision of the board of supervisors, or municipal authorities of a city, town, or village, may appeal within ten (10) days from the date of adjournment at which session the board of supervisors or municipal authorities rendered such judgment or decision, and may embody the facts, judgment and decision in a bill of exceptions which shall be signed by the person acting as president of the board of supervisors or of the municipal authorities.

The Mississippi Supreme Court has held that the ten-day time limit is mandatory. Newell v. Jones County, 731 So.2d 580, 582 (Miss.1999). Accordingly, an action challenging a municipality’s decision to enter into a contract must be filed within ten-days of date of adjournment of session where the decision was made or the claims will be dismissed. Id. It is undisputed that Nottingham’s claims challenging Waveland’s contract with Hemphill were not filed within ten days from the date of the contract.

Nottingham asserts that § 11-51-75 does not apply to the present case because Waveland has not made any final decision with respect to Nottingham’s protest. We disagree. The decision to award the contract to Hemphill, not the resolution of Nottingham’s protest, is the basis of Nottingham’s claims. Nottingham cannot restart the clock on its deadline to challenge the award of the contract to Hemphill by filing an untimely protest. Otherwise, the ten-day requirement of § 11-51-75 would be meaningless.

*668 In support of its argument, Nottingham relies almost entirely on Shepard v. City of Batesville, No. 2:04-CV-330, 2007 WL 108288 (N.D.Miss. Jan. 8, 2007). In Shepard, the plaintiff demonstrated that he was the lowest and best bidder on several contracts to perform earthmoving work for the City of Batesville. 2007 WL 108288, at *6. Although the city found him to be the lowest and best bidder, the city only gave him one of the jobs. Id. The city claimed that it hired other contractors to perform the rest of the work because it could not reach the plaintiff by telephone. Id. The court held there was no evidence that the city ever made a final decision awarding the other jobs to different bidders or gave notice of any such decision. Id. As a result, the court held that the ten-day time limit provided for under § 11-51-75 was never triggered. Id.

Shepard is not binding on this court. To the extent that it is persuasive authority, it is clearly distinguishable. The pivotal fact in Shepard

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American National General Insurance v. Ryan
274 F.3d 319 (Fifth Circuit, 2001)
Audler v. CBC Innovis Inc.
519 F.3d 239 (Fifth Circuit, 2008)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
In Re Katrina Canal Breaches Litigation
495 F.3d 191 (Fifth Circuit, 2007)
Newell v. Jones County
731 So. 2d 580 (Mississippi Supreme Court, 1999)
Nelson v. City of Horn Lake
968 So. 2d 938 (Mississippi Supreme Court, 2007)
Thornton v. Town of Charleston
68 So. 169 (Mississippi Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
291 F. App'x 665, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nottingham-construction-co-v-city-of-waveland-ca5-2008.