Northwest Pipeline Corp. v. Federal Energy Regulatory Commission

986 F.2d 1330
CourtCourt of Appeals for the Tenth Circuit
DecidedFebruary 23, 1993
DocketNos. 91-9566, 91-9567
StatusPublished
Cited by2 cases

This text of 986 F.2d 1330 (Northwest Pipeline Corp. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwest Pipeline Corp. v. Federal Energy Regulatory Commission, 986 F.2d 1330 (10th Cir. 1993).

Opinion

TACHA, Circuit Judge.

Petitioner Northwest Pipeline Corporation (“Northwest”) seeks review of two orders of the Federal Energy Regulatory Commission (“FERC”) requiring Northwest to amend downward the take-or-pay surcharge that it charges its customers. Because we conclude that the issues Northwest raises in its petitions are not yet ripe for review, we dismiss the petitions for lack of jurisdiction.

BACKGROUND

On August 7, 1987, FERC issued its Order No. 500 which promulgated new guidelines under which pipelines can recover take-or-pay costs incurred as a result of the deregulation of the natural gas industry in the 1980s. See Regulation of Natural Gas Pipelines After Partial Wellhead Decontrol (Order No. 500), 52 Fed.Reg. 30,334 (1987) (codified in part at 18 C.F.R. § 2.104); see also Associated Gas Distribs. v. FERC, 824 F.2d 981, 995-96 (D.C.Cir.1987) (recounting the development of the take-or-pay problem). These guidelines permit a pipeline that agrees to absorb 25% to 50% of its take-or-pay costs to recover from its customers an equal percentage through a fixed surcharge and the remainder through either a commodity rate surcharge or a volumetric surcharge on total throughput. 18 C.F.R. § 2.104(a).

On March 31, 1989, Northwest filed tariff sheets to implement a mechanism to recover its take-or-pay costs pursuant to Order No. 500. It proposed to absorb 25% of its costs and to recover 25% through a fixed surcharge and 50% through a volumetric surcharge which Northwest denominated a Supplier Settlement Payment ("SSP") surcharge. FERC accepted the SSP surcharge on the condition that Northwest recalculate it to reflect the volumes underlying "its most recent Commission-approved rates" as required by 18 C.F.R. § 2.104(b). Northwest Pipeline Corp., 47 F.E.R.C. ¶ 61,147 (1989). Northwest began collecting its SSP surcharge in the second quarter of 1989 and has made regular quarterly updates, all based on the throughput volume of 450 TBtu (trillion British thermal units) underlying the rates established in the settlement of Northwest’s most recent general rate case ("General Rate Case"). See Northwest Pipeline Corp., 49 F.E.R.C. ¶ 61,072 (1989) (approving contested settlement as modified).

On May 31, 1991, Northwest filed tariff sheets to restate its base tariff rates ("Restatement Filing"), thus initiating a rate restatement proceeding ("Restatement Proceeding"). Northwest sought to restate and continue in effect the base rates approved in the General Rate Case because [1332]*1332its cost and revenue study indicated that its jurisdictional costs exceeded its jurisdictional revenues. The study also demonstrated that Northwest had moved 568.6 TBtu of natural gas through its pipeline during the year ending February 28, 1991. FERC accepted and suspended the Restatement Filing subject to refund and to conditions not at issue here. Northwest Pipeline Corp., 55 F.E.R.C. ¶ 61,514 (1991).

On May 24, 1991, Northwest submitted a quarterly filing to update its SSP surcharge for the third quarter of 1991. On June 28, 1991, FERC accepted and suspended the filing, but ordered Northwest to recalculate the SSP surcharge by basing it on the 568.6 TBtu throughput volume disclosed in the Restatement Filing. Northwest Pipeline Corp., 55 F.E.R.C. ¶ 61,525 (1991). Northwest sought rehearing, arguing that its proposed SSP surcharge was properly based on the 450 TBtu throughput volume underlying the rates established in the General Rate Case. FERC denied Northwest’s motion, see Northwest Pipeline Corp., 56 F.E.R.C. ¶ 61,424 (1991), and this appeal followed in Case No. 91-9566.

On September 6, 1991, Northwest submitted its corrected quarterly filing for the fourth quarter of 1991 and again relied on the 450 TBtu throughput volume underlying the rates established in the General Rate Case. On September 30, 1991, FERC accepted and suspended the filing, but again ordered Northwest to recalculate the SSP surcharge by basing it on the 568.6 TBtu throughput volume disclosed in the Restatement Filing. Northwest Pipeline Corp., Nos. TM92-2-37-000 and TM92-2-37-001, slip op. (Sept. 30, 1991). FERC rejected Northwest’s request for rehearing and stay, Northwest Pipeline Corp., 57 F.E.R.C. ¶ 61,194 (1991), and this appeal followed in Case No. 91-9567.

On October 15, 1991, Northwest filed motions for reconsideration and stay of FERC’s order denying Northwest’s motion for rehearing in the first case. While these motions were pending, Northwest complied with the initial orders in the two cases below by refiling its quarterly tariff sheets with the recalculated SSP surcharges.

On January 23, 1992, FERC issued its Order Denying Reconsideration and Stay and Accepting Compliance Filing, Northwest Pipeline Corp., 58 F.E.R.C. ¶ 61,054 (1992). In that order, FERC summarized its reasons for requiring Northwest to recalculate its SSP surcharges. It conceded that "the 568.6 TBtu volume is not, strictly speaking, a volume which has been used to design Northwest’s rates." It noted, however, that "Northwest’s higher costs have been counterbalanced by increased volumes, thus making it possible for Northwest to forego" initiating a general rate case to increase its base rates. It concluded that if Northwest did not amend downward its SSP surcharge before the next general rate case, the substantially higher volume of gas it was moving would permit it to substantially overrecover its take-or-pay costs. Because this result would be "unjust and unreasonable," FERC ordered Northwest to amend its SSP surcharge. Finally, FERC reemphasized that use of the 568.6 TBtu figure was provisional. At the conclusion of the Restatement Proceeding, FERC would identify the proper throughput figure on which to base the SSP surcharges for the third and fourth quarters of 1991.

FERC subsequently filed a Motion for Leave to Issue Order, which this court granted on February 12, 1992. Consequently, Northwest currently is charging its SSP surcharges based on the 568.6 TBtu throughput volume disclosed in the Restatement Filing rather than on the 450 TBtu throughput volume underlying the rates established in the General Rate Case.

On December 18, 1992, after we heard oral argument in this case, FERC issued a letter order accepting and approving a settlement in the Restatement Proceeding. Northwest Pipeline Corp., 61 F.E.R.C. ¶ 61,345 (1992). That order, which is now final, quotes the settlement which specifically provides:

“1.1 The suspended restated base tariff rates in effect as of July 1, 1991, will continue in effect until superseding rates are placed into effect. The cost of service and throughput volumes underlying [1333]*1333these rates will be the cost of service and throughput volumes approved in [the General Rate Case], except for the throughput volumes used to calculate Northwest’s SSP commodity charge, which remains an issue to be resolved in this proceeding.”

Therefore, the volume underlying Northwest’s current rates remains 450 TBtu. FERC emphasizes, and the settling parties agree, that the final appropriate volume underlying the SSP surcharge is not resolved by the settlement and is reserved for resolution at a later hearing (“SSP Hearing”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
986 F.2d 1330, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwest-pipeline-corp-v-federal-energy-regulatory-commission-ca10-1993.