Northwest Line Constructors Chapter of the National Electrical Contractors Ass'n v. Snohomish County Public Utility District No. 1

17 P.3d 1251, 104 Wash. App. 842
Court of Appeals of Washington·Decided February 12, 2001·No. No. 45961-9-I·Published·Cited by 5 cases

Opinion

Kennedy, J.

The National Electrical Contractors Association, Northwest Line Constructors Chapter, (NECA) brought this action for declaratory judgment and injunctive relief, alleging in its complaint that Snohomish County Public Utility District No. 1 (PUD) had in the past, and still was, “purchasing more than $50,000 worth of individual items of equipment and installing these items using its own forces without public competitive bidding required by RCW 54.04.070f,]”1 a public utility competitive bidding statute. The complaint also alleged that PUD was “splitting” its contracts in violation of RCW 54.04.070 and other bidding statutes.2 The trial court granted the PUD’s motion for summary judgment dismissing NECA’s complaint, and we affirm.

RCW 54.04.070 allows a public utility district to split electrical substation projects into site preparation work and electrical installation work, and to have its own regularly employed personnel perform the electrical installation work, rather than calling for bids, where such is an accepted industry practice under prudent utility management. That same statute defines “prudent utility management” to mean “performing work with regularly employed personnel utilizing material of a worth not exceeding fifty thousand dollars in value” with the further proviso that “such limit on the value of material being utilized in work being performed by regularly employed personnel shall not [845] include the value of individual items of equipment purchased or acquired and used as one unit of a project.”3

NECA failed to allege in its complaint that PUD’s conduct fell outside accepted industry practice under prudent utility management, but nevertheless argued at summary judgment that (1) splitting a substation project between site work and electrical work is not an accepted industry practice and that (2) the PUD failed to contract out electrical work in which the value of the material used, exclusive of equipment, exceeded $50,000. The trial court gave NECA leave to amend its complaint to allege that the PUD’s practices fell outside accepted industry practice under prudent utility management but NECAfailed to do so. The trial court then dismissed the complaint with prejudice because it failed to state a claim under the bidding statute. But the court also ruled that NECA could file a new action properly raising the claim if the facts warranted it, and the PUD agrees for purposes of this appeal that if NECA does so, it will not contend that the action is barred by preclusion doctrine.4

DISCUSSION

Summary judgment is available only if the pleadings, depositions, answers to interrogatories, admissions on file, and any affidavits show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law. CR 56(c). In reviewing a summary judgment order, this court conducts the same inquiry as the trial court. Mountain Park Homeowners Ass’n v. Tydings, 125 Wn.2d 337, 341, 883 P.2d 1383 (1994). We review questions of law de novo. Id.

NECA argues that the PUD’s practice of splitting [846] projects between site preparation work and electrical installation work violates RCW 54.04.070 because that statute does not permit contract splitting. This issue involves statutory construction, a question of law reviewed de novo. State v. Ammons, 136 Wn.2d 453, 456, 963 P.2d 812 (1998). Where a statute is plain, unambiguous, and clear on its face, there is no room for construction. Nat’l Elec. Contractors Ass’n v. City of Bellevue, 1 Wn. App. 81, 83, 459 P.2d 420 (1969) (citing King County v. City of Seattle, 70 Wn.2d 988, 425 P.2d 887 (1967)).

The portion of RCW 54.04.0705 relevant to this case states:

Any work ordered by a district commission, the estimated cost of which is in excess of ten thousand dollars exclusive of sales tax, shall be by contract, except that a district commission may have its own regularly employed personnel perform work which is an accepted industry practice under prudent utility management without a contract. Prudent utility management means performing work with regularly employed personnel utilizing material of a worth not exceeding fifty thousand dollars in value without a contract: PROVIDED, That such limit on the value of material being utilized in work being performed by regularly employed personnel shall not include the value of individual items of equipment purchased or acquired and used as one unit of a project.

Under the plain terms of this statute, unless an exception applies, work ordered by a public utility district must be by contract if the estimated cost of the work is in excess of $10,000. Under the only relevant exception here, a district may have its own regularly employed personnel perform work without calling for competitive bids where such is an accepted industry practice under prudent utility management. “Prudent utility management means performing work with regularly employed personnel utilizing material of a worth not exceeding fifty thousand dollars in value” but “such limit on the value of material being utilized in work being performed by regularly employed personnel shall not [847] include the value of individual items of equipment purchased or acquired and used as one unit of a project.” RCW 54.04.070.

Free access — add to your briefcase to read the full text and ask questions with AI

Northwest Line Constructors Chapter of the National Electrical Contractors Ass'n v. Snohomish County Public Utility District No. 1, 17 P.3d 1251, 104 Wash. App. 842 (Wash. Ct. App. 2001).

17 P.3d 1251 (Northwest Line Constructors Chapter of the National Electrical Contractors Ass'n v. Snohomish County Public Utility District No. 1) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Camp Finance, LLC v. Brazington
135 P.3d 946 (Court of Appeals of Washington, 2006)
In Re Estate of Bowers
131 P.3d 916 (Court of Appeals of Washington, 2006)
Berghmans v. Museum of Flight
131 P.3d 916 (Court of Appeals of Washington, 2006)
Northwest Line Constructors v. Pud
17 P.3d 1251 (Court of Appeals of Washington, 2001)