Northrop Corp. v. McDonnell Douglas Corp.

705 F.2d 1030, 30 Cont. Cas. Fed. 70,860, 36 Fed. R. Serv. 2d 102, 1983 U.S. App. LEXIS 30124
CourtCourt of Appeals for the Ninth Circuit
DecidedFebruary 28, 1983
DocketNos. 81-5165, 81-5172
StatusPublished
Cited by197 cases

This text of 705 F.2d 1030 (Northrop Corp. v. McDonnell Douglas Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northrop Corp. v. McDonnell Douglas Corp., 705 F.2d 1030, 30 Cont. Cas. Fed. 70,860, 36 Fed. R. Serv. 2d 102, 1983 U.S. App. LEXIS 30124 (9th Cir. 1983).

Opinion

BOOCHEVER, Circuit Judge:

This appeal and cross-appeal present complex issues concerning the extent to which private parties may obtain redress for alleged injuries occurring in the heavily regulated military aircraft industry. The principal issues are whether: (1) suit against the Government pursuant to 22 U.S.C. § 2356 (disclosure of proprietary data) is the exclusive remedy; (2) the Government is a necessary party; (3) the claims present non-justiciable political or foreign policy questions; [1036]*1036(4) certain agreements between the parties are per se illegal restraints of trade; and (5) the Government so pervades the relevant market that no trade or commerce exists for Sherman Act purposes.

The case arises out of a series of “teaming” agreements that Northrop and McDonnell Douglas (“McDonnell”) entered into at the Government’s request to develop military aircraft. The. agreements allegedly limited Northrop to marketing those aircraft developed through the teaming effort that were suitable for land-based operation and McDonnell to marketing those suitable for aircraft-carrier operation. Despite its extensive involvement in the military aircraft industry, the Government is not a formal party to either the agreements or this action.

The trouble giving rise to Northrop’s complaint and McDonnell’s counterclaim began when McDonnell was awarded a large Navy contract, Northrop lost the competition for a similar Air Force contract, and McDonnell subsequently began marketing land-based aircraft to foreign countries. Northrop contends that McDonnell’s marketing of land-based aircraft violated the agreements. It filed suit claiming, inter alia, fraud, breach of contract, economic coercion, refusal to deal, unfair competition, and industrial espionage. McDonnell subsequently filed a counterclaim seeking, inter alia, a declaration of rights under the agreements and damages for Northrop’s allegedly illegal conduct and breaches of the agreements.

After some preliminary procedural maneuvering, the district court dismissed Northrop’s first amended complaint in its entirety and, alternatively, granted McDonnell summary judgment as to five of the eight counts in the complaint. Northrop Corp. v. McDonnell Douglas Corp., 498 F.Supp. 1112 (C.D.Cal.1980). The district court also dismissed McDonnell’s counterclaim and, alternatively, granted Northrop summary judgment on the ground that the counterclaim was the “mirror image” of Northrop’s complaint.

We conclude that dismissal and summary judgment were inappropriate as to Northrop’s complaint and McDonnell’s counterclaim. Accordingly, except for the denial of a motion to modify a finding of fact, which we affirm, the decision of the district court is reversed and the matter remanded for further proceedings.

I

Background

A. Facts

Between 1965 and 1972 Northrop devoted substantial resources toward developing a lightweight, moderately priced, multi-mission jet fighter. This development effort produced an aircraft design Northrop termed the P-530.

In 1972, the United States Air Force awarded Northrop a multi-million dollar contract to produce two prototype aircraft (designated the “YF-17”) based generally on the P-530 design. The Air Force concurrently awarded a similar contract to General Dynamics Corporation to produce two prototypes based on an alternative design concept (designated the “YF-16”). Both contracts were awarded as part of the Air Force’s Air Combat Fighter (“ACF”) competition for prototype development of lightweight land-based fighters. In keeping with its usual procurement policy (see generally Armed Services Procurement Regulations [“ASPR”], 32 C.F.R. §§ 7-104.-9, 9-201(d), and 9-202.2(b) (1981)), the Government obtained unlimited rights through the contracts in the technology incorporated in the YF-16 and YF-17 prototypes.

McDonnell did not compete for an ACF contract. Instead, McDonnell concentrated on improving its F-15 design, which was for a more specialized and expensive land-based fighter than the YF-16 and YF-17 designs.

In 1974, the United States Navy announced the Navy Air Combat Fighter (“NACF”) competition to develop a lightweight fighter suitable for aircraft carriers. To cut costs, Congress directed the Navy to [1037]*1037make maximum use of the technology already developed and paid for in the Air Force’s ACF program. The Navy was thereby forced to limit its NACF competition to proposals based on General Dynamics’s YF-16 and Northrop’s YF-17 technology. Because of the headstart possessed by General Dynamics and Northrop in this technology and the limited funds the Navy had available to compensate other companies for the expense of catching up, the NACF competition was effectively limited to General Dynamics and Northrop.

Although General Dynamics and Northrop were essentially the only NACF competitors, neither possessed significant experience in producing carrier-suitable aircraft. To overcome this shortcoming, the Defense Department and Navy urged them to “team”1 with companies having greater Navy experience. McDonnell was one of three or four companies that possessed the requisite Navy experience. Although, as noted by the district court, the parties dispute who was the pursuer and who the pursued,2 the outcome of the corporate courtship is clear. On October 2,1974, Northrop and McDonnell executed a “Teaming Agreement” to develop and propose variants of the YF-17 to the Air Force and Navy.

The Teaming Agreement was the first of three major written agreements between the parties. The parties agreed that Northrop would concentrate on the Air Force’s ACF competition while McDonnell concentrated on the Navy’s NACF competition. The proposal submitted to the Air Force listed Northrop as prime contractor and McDonnell as associate contractor; the roles were reversed in the proposal submitted to the Navy. The Agreement was intended “to be the basis for later agreements to be definitized.”

On January 14, 1975, Northrop’s YF-17 lost the ACF competition to General Dynamics’s YF-16. On May 2,1975, the Navy announced that McDonnell’s proposed fighter had won the NACF competition, designating the winning design the “F — 18”. Approximately two months later, the parties entered into a “Basic Agreement” drawn along the same lines as the prior Teaming Agreement.3 The Basic Agreement has five key provisions:

1. In the “Definition” clause, the F-18 is defined as “a carrier-based derivative of [Northrop’s] YF-17 aircraft.... ”
2. In the “Objective” clause, the parties expressed their commitment to:
work together (without in any manner intending to create a joint venture or otherwise incur or imply joint or several liability) for the purpose of obtaining and performing contracts for the development and production of derivatives of [Northrop’s] YF-17 aircraft that are responsive to the requirements of the U.S. Navy and foreign customers.
3. In the “Contract Responsibilities” clause that is at the heart of this dispute, the parties agreed:
3. (a) ... that [McDonnell] will be prime contractor in connection with [1038]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lois Romero v. Wal-Mart, Inc.
C.D. California, 2020
Marvin Roberts v. City of Fairbanks
947 F.3d 1191 (Ninth Circuit, 2020)
Zack Ward v. Apple, Inc.
791 F.3d 1041 (Ninth Circuit, 2015)
United States v. United Technologies Corp.
782 F.3d 718 (Sixth Circuit, 2015)
Marei Von Saher v. Norton Simon Museum of Art At
754 F.3d 712 (Ninth Circuit, 2014)
Ohio Valley Environmental Coalition, Inc. v. Hobet Mining, LLC
723 F. Supp. 2d 886 (S.D. West Virginia, 2010)
United States v. Green
Ninth Circuit, 2010
Wright v. Incline Village General Improvement District
597 F. Supp. 2d 1191 (D. Nevada, 2009)
Chase v. Cohen
519 F. Supp. 2d 267 (D. Connecticut, 2007)
Hubbard v. Rite Aid Corp.
433 F. Supp. 2d 1150 (S.D. California, 2006)
Wilbur v. Locket
423 F.3d 1101 (Ninth Circuit, 2005)
Alperin v. Vatican Bank
410 F.3d 532 (Ninth Circuit, 2005)
Southern Union Co. v. Southwest Gas Corp.
165 F. Supp. 2d 1010 (D. Arizona, 2001)
Third Avenue Trust v. SunTrust Bank
163 F. Supp. 2d 215 (S.D. New York, 2001)
Fanbrella, Inc. v. EDT Products, Inc.
185 F.R.D. 144 (E.D. New York, 1999)
Tower Air, Inc. v. Federal Express Corp.
956 F. Supp. 270 (E.D. New York, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
705 F.2d 1030, 30 Cont. Cas. Fed. 70,860, 36 Fed. R. Serv. 2d 102, 1983 U.S. App. LEXIS 30124, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northrop-corp-v-mcdonnell-douglas-corp-ca9-1983.