Northern Virginia Electric Co v. FERC

CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 20, 2019
Docket17-1262
StatusPublished

This text of Northern Virginia Electric Co v. FERC (Northern Virginia Electric Co v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northern Virginia Electric Co v. FERC, (D.C. Cir. 2019).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued November 18, 2019 Decided December 20, 2019

No. 17-1262

NORTHERN VIRGINIA ELECTRIC COOPERATIVE, INC., PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

Consolidated with 17-1265, 18-1230, 18-1234

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Adrienne E. Clair argued the cause for petitioners. With her on the briefs were Rebecca L. Shelton, Alan I. Robbins, and Debra D. Roby.

Elizabeth E. Rylander, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were Robert H. Solomon, Solicitor, and Lona T. Perry, Deputy Solicitor. Anand Viswanathan, Attorney, entered an appearance. 2

Christopher R. Jones argued the cause for intervenor Virginia Electric and Power Company. With him on the brief was Miles H. Kiger.

Sean T. Beeny, Denise C. Goulet, and Phyllis G. Kimmel were on the brief for intervenor North Carolina Electric Membership Corporation in support of respondent.

Before: GARLAND, Chief Judge, WILKINS, Circuit Judge, and WILLIAMS, Senior Circuit Judge.

Opinion for the Court filed by Senior Circuit Judge WILLIAMS.

WILLIAMS, Senior Circuit Judge: In the mid to late 2000s, the Virginia Electric and Power Company (known in this case by its trade name, “Dominion”) sought to construct three projects to upgrade its electricity transmission grid. The state of Virginia required Dominion to place the new transmission wires underground rather than use cheaper overhead wiring, thereby increasing the cost of the three projects from about $84 million to $233 million in total. Dominion serves customers in both Virginia and North Carolina. This case involves a simple question: How should the cost of undergrounding be allocated among Dominion’s customers?

In a series of proceedings, the Federal Energy Regulatory Commission concluded that Dominion’s Virginia customers, but not its North Carolina customers, should bear those costs; the evidence showed that Virginia customers benefited from the undergrounding, while no evidence showed that North Carolina customers benefited. In the Commission’s words, this decision represented “a limited exception” to a general principle that all of a utility’s customers should share the costs of upgrading the grid. Old Dominion Elec. Coop., 146 FERC 61,200 ¶ 52 (2014) (“Allocation Order”), reh’g denied, 161 3

FERC 61,055 (2017) (“First Order on Rehearing”); see also Old Dominion Elec. Coop., 161 FERC 61,054 (2016), reh’g denied, 164 FERC 61,006 (2018) (“Second Order on Rehearing”).

In this petition, Virginia power wholesalers who buy electricity from Dominion challenge the Commission’s decision on procedural and substantive grounds. None of them persuades us. We tackle first the procedural theories, then the substantive ones.

I.

The petitioners argue: (1) that the Commission did not properly invoke its power under § 206 of the Federal Power Act, 16 U.S.C. § 824e; (2) that the Commission failed to provide adequate notice of its intent to modify Dominion’s filed rate; and (3) that the Commission’s administrative law judge misinterpreted a Commission order and thereby improperly cabined the scope of an evidentiary hearing.

1. The claim that a proper § 206 proceeding was missing turns on special rules relating to Commission supervision of formula rates—the sort used by Dominion. The formula rate, filed as a tariff with the Commission, identifies the categories into which Dominion’s costs fall. With the formula in place, Dominion files an annual update informing the Commission and its customers of the projected costs for each category in the formula. Unless modified by the Commission, Dominion recovers the costs under the formula rate, subject to a later true- up procedure. See Virginia Elec. & Power Co., 123 FERC 61,098 ¶ 6 (2008) (“Order Approving Formula”).

At least in Dominion’s case, the tariff creates a procedure, known as a “Formal Challenge,” through which a customer can challenge the legitimacy of inputs. See id. ¶ 16 (describing the 4

Formal Challenge process). (We use initial capitals for the name, to emphasize that it is a word of art and not, so far as we can determine, based on any especially high level of formality.) Although the parties here have spoken and written as if such a Formal Challenge were located under § 206, see, e.g., Oral Argument at 8:23, it seems more accurately akin to a continuation of the § 205 proceeding in which the utility files its formula rate. See 16 U.S.C. § 824d. That’s because the annual update supplements the utility’s initial § 205 filing, which is simply a formula without the necessary inputs. Consequently, in a Formal Challenge, the utility not the complainant bears the burden of proving the justness and reasonableness of its inputs, just as the utility does when it first files the formula rate under § 205. See Order Approving Formula, 123 FERC 61,098 ¶ 47 (noting that those who launch a Formal Challenge to Dominion’s annual update do not bear the burden of proof); cf. Midwest Indep. Transmission Sys. Operator, Inc., 143 FERC 61,149 ¶ 120 n.199 (2013) (citing § 205 on this point regarding a different tariff). In contrast, in a conventional § 206 proceeding, the complainants or the Commission must prove the unjustness and unreasonableness of the utility’s rate. See 16 U.S.C. § 824e(b) (placing the burden of proof “upon the Commission or the complainant”).

For purposes of this case, there is a further key distinction between a Formal Challenge and a § 206 proceeding: In a Formal Challenge proceeding, a party cannot advance “attacks on the formula rate itself” and cannot advocate “that expenses should be treated differently from how the formula prescribes.” Delmarva Power & Light Co., 160 FERC 61,102 ¶ 19 (2017); see also Ameren Ill. Co., 156 FERC 61,209 ¶ 71 (2016).

When Dominion filed its formula rate in 2008, it did not distinguish between its Virginia and North Carolina customers. In its 2010 annual update, Dominion proposed including the undergrounding costs at issue here as inputs into the formula 5

rate for all its customers. On March 17, 2010, Dominion’s customers in both Virginia and North Carolina objected and instituted a Formal Challenge to the undergrounding costs’ inclusion. By its own terms, their complaint did not “seek [] to challenge the formula rate, but rather [to] challenge only the inputs into the formula rate for the 2010 Annual Update.” J.A. 52.

The Virginia customers now argue that because they launched a Formal Challenge to the annual update’s inputs— and not a standard § 206 proceeding—the Commission lacked the statutory authority to modify the formula rate itself so as to saddle the Virginia but not North Carolina customers with costs.

But in fact the Commission broadened the scope of the complaint proceedings. On March 24, 2010, a week after Dominion’s customers filed their Formal Challenge, Dominion responded by filing its own proposal under § 205 to assign those costs directly to its customers in case the Commission determined that Dominion could not include the costs in its existing formula rate. See Virginia Elec. & Power Co., 131 FERC 61,171 ¶¶ 1, 4, 18 (2010) (“May 20, 2010 Order”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Northern Virginia Electric Co v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-virginia-electric-co-v-ferc-cadc-2019.