Northern Pipe Line Company Case

1 A.2d 526, 132 Pa. Super. 406, 1938 Pa. Super. LEXIS 53
CourtSuperior Court of Pennsylvania
DecidedMay 4, 1938
DocketAppeal, 2
StatusPublished
Cited by2 cases

This text of 1 A.2d 526 (Northern Pipe Line Company Case) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northern Pipe Line Company Case, 1 A.2d 526, 132 Pa. Super. 406, 1938 Pa. Super. LEXIS 53 (Pa. Ct. App. 1938).

Opinion

Opinion by

Keller, P. J.,

State Highway Route No. 68 — also known as Legislative Route No. 380 — passes through Farmington Township, Clarion County. Until 1931 that portion of the road lying between stations 97 + 18 and 330 + 75, a distance of 23,975 feet or over 4% miles, had not been improved and was only an earth road. The Secretary of Highways, acting for the Department of Highways, decided to improve this part of the road and with that end in view divided it into two sections: (1) From station 97 + 18 to station 188 + 03, a distance of 9,085 feet, or 1.72 miles; (2) from station 188 + 03 to station 330 + 75, a distance of 14,890 feet, or 2.82 miles.

In this case we are concerned only with the first section, although, it may be added, a relocation of the road in the second section for almost its entire length was also made.

Considering, then, section 1, thé Department’s engineers found that by relocating the highway south of the old road for a distance of about 7,500 feet, three grade crossings of the Baltimore & Ohio Railroad could be avoided, one at station 120, one at station 161 and one at station 177, and that the increased expense of construction would be only $2,000, of which the railroad was willing to pay $1,000, if the crossing at station 177 was abolished. To obtain a better grade for this improvement the highway was also relocated north of the old road for about 1,500 feet.

Accordingly on March 7, 1931 a plan so relocating the state highway was prepared by the Division Engi *409 neer and its approval recommended to the Secretary of Highways, and on March 25, 1931, the plan was approved by the Chief Engineer, the Secretary of Highways and the Governor. This was done pursuant to section 8 of the Act of May 31, 1911, P. L. 468, and on approval by the Governor the road as relocated became the route of the state highway in place of the old road, and the plan so approved became the record of the appropriation of the land taken for the new or relocated highway, to be paid for by the agency of Government legally responsible therefor when actual entry was made on the land: May v. County of Westmoreland, 98 Pa. Superior Ct. 488; In the Matter of Appointment of View ers, 103 Pa. Superior Ct. 212, 158 A. 296; Urbanskis’ Petition, 128 Pa. Superior Ct. 293, 296, 194 A. 210; Penn Builders v. Blair County, 302 Pa. 300, 153 A. 433; Eshleman v. Commonwealth, 325 Pa. 521, 524, 525, 189 A. 340.

Following this, work on the relocated highway began on May 4, 1931 and was completed on August 11, 1931.

In laying out the relocated highway certain land of Northern Pipe Line Company was taken and appropriated, and its pipe line, located on its right of way over other lands so taken gnd appropriated, had to be lowered, causing it additional expense.

After the relocation had been decided on and approved but before the work on the ground was begun, the Secretary of Highways filed a petition with the Public Service Commission, under section 12 of Article Y of the Public Service Company Law of July 26, 1913, P. L. 1374, praying for the abolition of the grade crossing at station 177 of the old road, and for the allocation of the cost of construction of a marginal road incident to the closing of the crossing, having reference thereby to the $1,000 which the railroad company had agreed to pay on the abolition of said crossing. A hear *410 ing was had on April 22, 1931, when the plan of the relocated highway, approved as above, was presented, which showed that the new highway had rendered the grade crossing at station 177 unnecessary, and the agreement with the railroad company was referred to and acknowledged by both parties. At this hearing the examiner for the Commission interrogated the Assistant Engineer representing the Department of Highways, as follows: “Will it be necessary for the Public Service Commission to condemn any private property in connection with this relocation and in order to complete it?” To which the representative of the Department replied: “It will not. The highway is being relocated under and by authority of the Highway Act of May 31,1911.”

On October 5, 1931 the Public Service Commission entered its order approving the abolition of the grade crossing at station 177 and directing the payment of $1,000 by the Baltimore & Ohio Railroad Company to the Department of Highways, to apply on the cost of materials furnished and work done by the Department of Highways; but ordering the continuance of the existing grade crossings at stations 120 and 161 to accommodate local traffic. It will be noted that this order was entered nearly two months after the actual relocation of the state highway had been completed.

On August 1,1932 Northern Pipe Line Company filed its petition in the court below asking for the appointment of viewers to assess the damages caused by the taking and appropriation of certain of its land in Farmington Township and by the injury to its right of way and the necessary lowering of its pipe lines due to the taking and appropriation of other lands, in the relocation of said highway. Viewers were appointed who, on December 5, 1932, after full hearing, filed their report awarding damages to the petitioner. To this the County on December 19, 1932 filed the fol *411 lowing exception: “The appointment of viewers and assessment of damages is based entirely on statutes. The law makes no provision for the appointment of viewers to assess damages, where said damages were caused by the abolition of a grade crossing; therefore the said viewers were appointed without authority of law and they had no legal right to assess damages. County courts have no jurisdiction in such cases.” Certain delays occurred in the disposition of the exceptions for which the present court below was not responsible, but on September 20, 1937 the exception of the County of Clarion was sustained, confirmation of the report of viewers was refused and stricken off, and the report was quashed. Northern Pipe Line Company appealed. The order will be reversed.

Under the law in force at the time of the taking and appropriation 1 of appellant’s land, the County of Clarion was responsible for the payment of damages caused by the taking and appropriation of land in the relocation of a state highway under section 8 of the Act of May 31, 1911, P. L. 468, and its amendments. Appellant’s land was actually taken in the relocation of the highway. State Highway Route 72, 71 Pa. Superior Ct. 85, affirmed, 265 Pa. 369, 108 A. 820. The amount of the award is not in question in this proceeding. The exception filed by the county went to the jurisdiction of the court of quarter sessions to appoint viewers and of the viewers to make any award.

The exceptant and the learned court below have misunderstood and misapplied the statutes involved.

--

*412

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Department of Highways v. Pennsylvania Public Utility Commission
182 A.2d 267 (Superior Court of Pennsylvania, 1962)
Lubrecht v. Commonwealth
38 A.2d 242 (Supreme Court of Pennsylvania, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
1 A.2d 526, 132 Pa. Super. 406, 1938 Pa. Super. LEXIS 53, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-pipe-line-company-case-pasuperct-1938.