Memorandum of Decision
JAMES B. HAINES, JR., Bankruptcy Judge.
I. Introduction
Before me is a lien priority dispute between Northeast Bank (“Northeast”) and Caterpillar Financial Services Corp. (“Caterpillar”). Each asserts a senior position in four pieces of logging equipment purchased by T & R Flagg Logging, Inc., (“Flagg”) from Southworth-Milton, Inc., before Flagg filed for bankruptcy relief. As explained below, I find and conclude that Northeast’s blanket security interest in all Flagg’s assets trumps Caterpillar’s lien because, although it claims to do so, Caterpillar does not hold a perfected purchase money security interest (pmsi) in the equipment.
II. Procedural History
Flagg filed a voluntary petition for relief under Chapter 11 of the Bankruptcy Code
in the fall of 2007. In early 2008, Flagg’s case was converted to Chapter 7. Caterpillar has been granted relief from stay with regard to the equipment encumbered by its and Northeast’s competing liens, but the two lienors reserved the right to joust over their respective priorities.
The issues were proffered via cross-motions for summary judgment. However, at oral argument, counsel conceded that the outcome pivots not so much on
what happened when
(about which there is no real dispute) as it does upon the
legal significance of events.
Accordingly, they stipulated that the matter would be submitted for decision on the record. Thus, I proceed to decision under the auspices of Fed. R. Bankr.P. 7052, rather than Fed. R. Bankr.P. 7056.
This memorandum sets forth my findings of fact and conclusions of law pursuant to
Rule 7052’s paradigm.
III. Factual History
Flagg borrowed approximately $740,000 and entered into a $50,000 line of credit arrangement with Northeast late in 2006. Flagg secured its repayment obligations with mortgages of real property and a blanket security interest in all its personal assets, extending to after-acquired personalty, as well. Northeast’s security interest is valid and perfected.
In February 2007, Flagg applied to Caterpillar for financing to enable it to purchase equipment from Southworth-Milton. Caterpillar declined Flagg’s application, indicating it needed additional information, and compliance with certain terms (e.g., cross-default and cross-collateralization covenants) before it would consider the application further.
On March 23, 2007, Flagg’s principal completed a Southworth-Milton purchase order for four pieces of equipment with a total proposed purchase price of $553,000, plus tax and other costs. The purchase order contemplated Flagg’s trade-in of three pieces of its own equipment and a $44,017.17 down payment. The purchase order indicated that the parties anticipated financing through Caterpillar, but final sale was not conditioned on that financing.
Notwithstanding the fact that Flagg’s execution of the purchase order did not, in either party’s view, create a contract, Southworth-Milton delivered the four pieces of to-be-purchased equipment to Flagg over the period March 12, 2007, through April 11, 2007. As to one item, Flagg signed a receipt, indicating the equipment was taken as a “demo.”
About the same time, Southworth-Milton took possession of the three machines Flagg had indicated it would trade in as part of the transaction they anticipated consummating.
On March 27, 2007, Flagg again applied to Caterpillar for financing and, again, was declined. Discussions endured. On May 10, 2007, Flagg forwarded to Caterpillar disbursement instructions (including payoff amounts for liens encumbering the trade-in machines) for such funds as may be advanced should Caterpillar extend the requested credit.
From the time the machines were delivered to Flagg until June 11, 2007, South-worth-Milton was the sole owner of the equipment Flagg intended to purchase; no sale had taken place. But on June 11, 2007, Southworth-Milton issued its Sales/Rental Invoice to Flagg in the amount of $312,900 (representing the purchase price, less trade-in credit, but not including amounts required to pay off liens on the trade-in machines), with a term requiring “net cash on receipt of invoice.” This invoice contained boilerplate by which Southworth-Milton purported to retain title to the sold equipment pending full payment of the purchase price. At the same time, Southworth-Milton removed the purchased equipment from its inventory, added the trade-in equipment to its inventory, and booked a $312,900 receivable owed by Flagg. As of June 11, 2007, Caterpillar had not committed, even conditionally, to the financing Flagg sought.
Southworth-Milton re-sold one of Flagg’s traded-in machines on June 17, 2007. The record does not reflect how Southworth-Milton applied the sale proceeds.
Eventually, negotiations between Caterpillar and Flagg got on track, and they agreed on terms for financing.
Twice, on July 11 and again on July 23, 2007, Caterpillar requested that Northeast subordinate its security interest with respect to the purchased (and, now, to-be-financed) equipment. Northeast demurred.
On July 17, 2007, Caterpillar filed a UCC-1 Financing Statement with the Maine Secretary of State, disclosing its security interests in the purchased machines. On July 30, 2007, Flagg executed a security agreement granting those security interests to Caterpillar, and Flagg provided Caterpillar a promissory note in the amount of $491,596.41. Caterpillar wired Southworth-Milton the purchase price it was owed and paid off the encumbrances on the equipment Flagg had traded-in.
On September 20, 2007, SouthworthMilton deposited three checks from Flagg, all dated July 18, 2007, totaling $44,017.17. The checks did not clear. Flagg stopped payment and filed its bankruptcy petition on September 21,2007.
III. Discussion
Article Nine of Maine’s Uniform Commercial Code (UCC) governs here.
The general rule under Article Nine is that earlier-perfected security interests are entitled to priority over later-perfected security interests.
Northeast acknowledges that Caterpillar holds a valid, perfected security interest in the equipment SouthworthMilton sold Flagg. It attached on July 30, 2007, when Caterpillar transferred funds to Southworth-Milton,
and it was perfected the same date, as the appropriate financing statement had previously been filed.
Northeast’s perfection predated Caterpillar’s by months.
Free access — add to your briefcase to read the full text and ask questions with AI
Memorandum of Decision
JAMES B. HAINES, JR., Bankruptcy Judge.
I. Introduction
Before me is a lien priority dispute between Northeast Bank (“Northeast”) and Caterpillar Financial Services Corp. (“Caterpillar”). Each asserts a senior position in four pieces of logging equipment purchased by T & R Flagg Logging, Inc., (“Flagg”) from Southworth-Milton, Inc., before Flagg filed for bankruptcy relief. As explained below, I find and conclude that Northeast’s blanket security interest in all Flagg’s assets trumps Caterpillar’s lien because, although it claims to do so, Caterpillar does not hold a perfected purchase money security interest (pmsi) in the equipment.
II. Procedural History
Flagg filed a voluntary petition for relief under Chapter 11 of the Bankruptcy Code
in the fall of 2007. In early 2008, Flagg’s case was converted to Chapter 7. Caterpillar has been granted relief from stay with regard to the equipment encumbered by its and Northeast’s competing liens, but the two lienors reserved the right to joust over their respective priorities.
The issues were proffered via cross-motions for summary judgment. However, at oral argument, counsel conceded that the outcome pivots not so much on
what happened when
(about which there is no real dispute) as it does upon the
legal significance of events.
Accordingly, they stipulated that the matter would be submitted for decision on the record. Thus, I proceed to decision under the auspices of Fed. R. Bankr.P. 7052, rather than Fed. R. Bankr.P. 7056.
This memorandum sets forth my findings of fact and conclusions of law pursuant to
Rule 7052’s paradigm.
III. Factual History
Flagg borrowed approximately $740,000 and entered into a $50,000 line of credit arrangement with Northeast late in 2006. Flagg secured its repayment obligations with mortgages of real property and a blanket security interest in all its personal assets, extending to after-acquired personalty, as well. Northeast’s security interest is valid and perfected.
In February 2007, Flagg applied to Caterpillar for financing to enable it to purchase equipment from Southworth-Milton. Caterpillar declined Flagg’s application, indicating it needed additional information, and compliance with certain terms (e.g., cross-default and cross-collateralization covenants) before it would consider the application further.
On March 23, 2007, Flagg’s principal completed a Southworth-Milton purchase order for four pieces of equipment with a total proposed purchase price of $553,000, plus tax and other costs. The purchase order contemplated Flagg’s trade-in of three pieces of its own equipment and a $44,017.17 down payment. The purchase order indicated that the parties anticipated financing through Caterpillar, but final sale was not conditioned on that financing.
Notwithstanding the fact that Flagg’s execution of the purchase order did not, in either party’s view, create a contract, Southworth-Milton delivered the four pieces of to-be-purchased equipment to Flagg over the period March 12, 2007, through April 11, 2007. As to one item, Flagg signed a receipt, indicating the equipment was taken as a “demo.”
About the same time, Southworth-Milton took possession of the three machines Flagg had indicated it would trade in as part of the transaction they anticipated consummating.
On March 27, 2007, Flagg again applied to Caterpillar for financing and, again, was declined. Discussions endured. On May 10, 2007, Flagg forwarded to Caterpillar disbursement instructions (including payoff amounts for liens encumbering the trade-in machines) for such funds as may be advanced should Caterpillar extend the requested credit.
From the time the machines were delivered to Flagg until June 11, 2007, South-worth-Milton was the sole owner of the equipment Flagg intended to purchase; no sale had taken place. But on June 11, 2007, Southworth-Milton issued its Sales/Rental Invoice to Flagg in the amount of $312,900 (representing the purchase price, less trade-in credit, but not including amounts required to pay off liens on the trade-in machines), with a term requiring “net cash on receipt of invoice.” This invoice contained boilerplate by which Southworth-Milton purported to retain title to the sold equipment pending full payment of the purchase price. At the same time, Southworth-Milton removed the purchased equipment from its inventory, added the trade-in equipment to its inventory, and booked a $312,900 receivable owed by Flagg. As of June 11, 2007, Caterpillar had not committed, even conditionally, to the financing Flagg sought.
Southworth-Milton re-sold one of Flagg’s traded-in machines on June 17, 2007. The record does not reflect how Southworth-Milton applied the sale proceeds.
Eventually, negotiations between Caterpillar and Flagg got on track, and they agreed on terms for financing.
Twice, on July 11 and again on July 23, 2007, Caterpillar requested that Northeast subordinate its security interest with respect to the purchased (and, now, to-be-financed) equipment. Northeast demurred.
On July 17, 2007, Caterpillar filed a UCC-1 Financing Statement with the Maine Secretary of State, disclosing its security interests in the purchased machines. On July 30, 2007, Flagg executed a security agreement granting those security interests to Caterpillar, and Flagg provided Caterpillar a promissory note in the amount of $491,596.41. Caterpillar wired Southworth-Milton the purchase price it was owed and paid off the encumbrances on the equipment Flagg had traded-in.
On September 20, 2007, SouthworthMilton deposited three checks from Flagg, all dated July 18, 2007, totaling $44,017.17. The checks did not clear. Flagg stopped payment and filed its bankruptcy petition on September 21,2007.
III. Discussion
Article Nine of Maine’s Uniform Commercial Code (UCC) governs here.
The general rule under Article Nine is that earlier-perfected security interests are entitled to priority over later-perfected security interests.
Northeast acknowledges that Caterpillar holds a valid, perfected security interest in the equipment SouthworthMilton sold Flagg. It attached on July 30, 2007, when Caterpillar transferred funds to Southworth-Milton,
and it was perfected the same date, as the appropriate financing statement had previously been filed.
Northeast’s perfection predated Caterpillar’s by months. While normally this would give Northeast’s security interest priority over Caterpillar’s, the UCC makes an exception to the first-to-file rule for pmsi’s:
a perfected purchase-money security interest in goods other than inventory or livestock has priority over a conflicting security interest in the same goods ... if the purchase-money security interest is perfected when the debtors receives possession of the collateral or:
(a) In the case of goods covered by Title 29-A, chapter 7, within 30 days thereafter; or
(b) In all other cases, within 20 days thereafter.
Maine’s UCC provides for a pmsi in goods “[t]o the extent that the goods are purchase-money collateral with respect to that security-interest.”
The burden rests with the party seeking pmsi status (here Caterpillar) to prove the validity of its pmsi.
Northeast challenges Caterpillar’s ability to demonstrate the purchase money character of its security interest. In its view, although Southworth-Milton’s delivery of the equipment by April 11, 2007, did not transfer title in the equipment to Flagg, its subsequent issuance of the invoice on June 11, 2007, did do so. Although the invoice contained a boilerplate term by which Southworth-Milton purported to retain title until it was fully paid, the UCC is clear that the term merely effected Southworth-Milton’s reservation to itself of a security interest.
South-worth-Milton’s own bookkeeping supports the conclusion that it extended credit to Flagg in order to effect the sale,
and the deposition testimony of Southworth-Milton’s representative bolsters my finding to that effect.
The long and the short of it is this: Southworth-Milton sold the equip
ment to Flagg on June 11, 2007, hoping (perhaps even expecting) that Caterpillar (or, perhaps some other entity) would eventually shoulder Flagg’s financing. In the course, Southworth-Milton, via its “reservation of title” boilerplate retained a lien to secure payment (viz., a pmsi). But Southworth-Milton failed to perfect that security interest within twenty days of Flagg’s acquiring all rights in the equipment, which was required to give it the statutory leg-up over Northeast’s pre-existing blanket lien. After twenty days ran from June 11, the lien Southworth-Milton retained lost its capacity to trump Northeast’s. At that point, Northeast’s pre-existing security interest was no longer vulnerable to upset with respect to Flagg’s equipment purchase financing. The timing and structure of the sale clearly shows that Southworth-Milton initially financed Flagg’s purchase, and that it consummated the sale while Caterpillar financing had not advanced beyond the pupal stage.
Caterpillar has assembled an array of authorities to buttress its position, but they cannot be bulldozed into a shape that provides meaningful support.
The es
sence of Caterpillar’s contention is that it should be considered the purchase money lender, notwithstanding the June 11, 2007, sale, because its funding was something that Flagg and Southworth-Milton had in mind throughout the course of the sale transaction. But providing Caterpillar with pmsi priority based on the parties’ subjective expectations would do violence to Article Nine’s carefully crafted scheme establishing how consensual liens are created, perfected, and prioritized based on objectively cognizable criteria.
IV. Conclusion
I conclude that Northeast’s pre-existing security interest has priority over Caterpillar’s security interest in the four pieces of equipment Flagg purchased from South-worth-Milton. A separate order consistent with this opinion will enter forthwith.