North Haven Planning & Zoning Commission v. Upjohn Co.

753 F. Supp. 423, 1990 U.S. Dist. LEXIS 18472, 1990 WL 237156
CourtDistrict Court, D. Connecticut
DecidedMay 31, 1990
DocketCiv. N-89-526 (TFGD)
StatusPublished
Cited by6 cases

This text of 753 F. Supp. 423 (North Haven Planning & Zoning Commission v. Upjohn Co.) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Haven Planning & Zoning Commission v. Upjohn Co., 753 F. Supp. 423, 1990 U.S. Dist. LEXIS 18472, 1990 WL 237156 (D. Conn. 1990).

Opinion

MEMORANDUM OF DECISION

DALY, District Judge.

The subject of this litigation is a sludge pile containing hazardous materials located on defendant’s property in North Haven, Connecticut. The North Haven Planning and Zoning Commission (“the Commission’’) and Scott Schatzlein, its present Zoning Enforcement Officer (“plaintiffs”) originally filed this action on October 19, 1989 in Superior Court in New Haven, Connecticut, seeking to enjoin the Upjohn Company (“defendant”, “Upjohn”) from implementing a plan capping the sludge pile and also requiring Upjohn to remove it. Defendant subsequently removed this case to federal court. 28 U.S.C. § 1441. On October 25, 1989, the Honorable José A. Cabranes denied plaintiffs’ application for a temporary restraining order. On November 22, 1989, Upjohn answered plaintiffs’ amended complaint, and also filed a counterclaim seeking to enjoin plaintiffs from enforcing any local regulations which prohibit Upjohn from implementing its closure plan and new wastewater treatment system. A consolidated hearing on plaintiffs’ application for a preliminary injunction and trial on the merits of both parties’ claims began on December 4, 1989, and concluded January 10, 1990. Both parties have submitted proposed findings of fact and conclusions of law, and the matter is now ripe for decision.

FINDINGS OF FACT

The Upjohn Company, headquartered in Kalamazoo, Michigan, produces pharmaceuticals, agricultural products, and synthetic organic chemicals. Upjohn’s North Haven, Connecticut facility, a medium-sized manufacturing plant, makes synthetic organic chemicals. The North Haven plant is bounded on its eastern side by the Quinni-piac River. Upjohn started production on this site in 1962.

1) THE PILE

A by-product of Upjohn’s chemical manufacturing is a substantial quantity of wastewater. In 1968, Upjohn began adding lime to its wastewater so as to neutralize its waste, and channeling the water through a series of lagoons to permit any solids to settle before the water was discharged into the Quinnipiac River. Upjohn has modified these lagoons several times to improve its water treatment system. Upjohn also dredged the solids which had collected in the lagoons and, starting in 1973, began placing this waste material, known as sludge, on a portion of its property north of a certain lagoon which by that time contained an aeration device. By 1977 the resulting pile, known as the north sludge pile and the subject of this litigation, covered approximately 4.25 acres of Upjohn’s property.

Upjohn continued to place sludge on this pile until April, 1985. The pile did not expand any further horizontally, but did grow vertically. By 1985, the pile stood approximately 40 feet above grade, and contained approximately 83,000 cubic yards of sludge. The pile is surrounded on all sides by a sloping earthen embankment and dikes. The material in the pile consists of, among other compounds, iron, iron oxides, silica, silica oxides, powdered activated carbon, sodium chloride, microorganisms, lead, dichlorobenzidene, dichloroni-troauiline, other trace chemicals, and water. The materials in the pile are classified as hazardous waste under the Federal Resource Conservation Recovery Act (“RCRA”). 42 U.S.C. § 6901 et seq.

In April, 1985, as a result of adding a substantial amount of material that had not had a sufficient period to dry, the pile partially collapsed, damaging water treatment devices. Upjohn removed approxi *425 mately 27,000 tons of material that had escaped from the pile, placed it in a temporary storage area, and subsequently took it off site. Some time after this accident, Upjohn implemented a treatment system which reduced the quantity of material being produced by approximately 90 percent. Upjohn stopped placing sludge on the north pile in April, 1985.

Upjohn hired Malcolm Pirnie, Inc. to evaluate the remedial alternatives for addressing the environmental problems posed by the north sludge pile. That firm reported in July, 1986, that carting the sludge away would cost $22,600,000, that incineration and carting would cost $19,700,000, and that chemical fixation and carting would cost $40,500,000. The firm also explained that capping the pile and leaving it in place would cost only $900,000. A similar report prepared in 1982 had estimated the cost of carting the sludge away at $12,000,000, with an additional $500,000 per year thereafter for sludge generated at the production rate at that time. There was testimony at trial that chemical manufacturers around the country utilize one or combinations of several options for onsite disposal of sludge: land piling (such as utilized by the defendant), land fill, land spreading or spraying, and land farming. Other manufacturers have inplemented recycle and reuse programs, and still others incinerate, though this was not popular until the 1980’s due to the oil crises of the 1970’s. Finally, some companies take their waste off site.

Upjohn chose to cap their pile, provided it could gain approval from the United States Environmental Protection Agency (“EPA”). The plan developed and modified by Malcolm Pirnie provides for capping the pile in two stages, which includes first adding six inches of gravel, and then replacing this layer with 24 inches of vegetated cover soil and a synthetic membrane. Malcolm Pirnie recommended the phased approach in order to more closely monitor the stability of the pile. The final cap will provide for a “higher degree of long-term integrity.” Def’s exh. 523 at 1-6. Under the plan, the capped pile and subsurface groundwater are to be monitored for hazardous waste leachate for the next thirty years. Id.

2) THE REGULATIONS

Since 1960, North Haven has had zoning regulations in effect which provide for permitted uses in industrial zones delineated within the town. The town’s regulations are permissive in nature, meaning that only those uses which are expressly allowed are permitted. Upjohn’s North Haven facility is located in an industrial zone designated IG-80. Upjohn’s manufacturing processes have always been permitted in this zone. Since 1960, residents of an IG zone were also permitted to engage in “accessory uses customarily incidental to a permitted use on the same premises.” Furthermore, since 1960, North Haven’s regulations have provided that any non-conforming use lawfully existing at the effective date of the regulations or any amendment may be continued.

The Commission became aware of the manner in which Upjohn was disposing of its sludge sometime in the late 1970’s. The Commission and Upjohn had numerous communications concerning the defendant’s wastewater treatment and disposal system from that time through 1986. In 1983, the Commission sent a letter advising Upjohn that it had approved defendant’s applications for permits concerning additions to the wastewater treatment system subject to certain conditions, including that Upjohn submit a plan and a timetable for the removal of all existing sludge. Pltf s exh. 32. The Town also amended its zoning regulations so as to provide “[n]o storage of any type ... shall be permitted outside of an enclosed area without the expressed site plan approval of the Planning and Zoning Commission.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
753 F. Supp. 423, 1990 U.S. Dist. LEXIS 18472, 1990 WL 237156, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-haven-planning-zoning-commission-v-upjohn-co-ctd-1990.