North Development Company, Inc. v. McClure
This text of 276 So. 2d 395 (North Development Company, Inc. v. McClure) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
NORTH DEVELOPMENT COMPANY, INC, Plaintiff-Appellant,
v.
Glendon McCLURE, dba Empire Construction Company, et al., Defendants-Appellees.
Glendon McCLURE, dba Empire Construction Company, Plaintiff-Appellee,
v.
SOUTHERN ERECTION COMPANY, INC, et al., Defendants-Appellants.
Court of Appeal of Louisiana, Second Circuit.
*396 Thomas & Prestridge, by Dewey E. Burchett, Jr., Bossier City, for appellant in Suits No. 12056 and 12057.
*397 Hal V. Lyons, Shreveport, for appellee in Suits No. 12056 and 12057.
Before AYRES, PRICE and HALL, JJ.
PRICE, Judge.
These consolidated cases arise out of a contract entered into on March 18, 1971, between Glendon McClure, dba Empire Construction Company, and Southern Erection Company, Inc., wherein McClure agreed to install the paved streets and drainage and to grade and dress the lots in the development of the Parkland Village Subdivision, Unit 1, Bossier Parish, Louisiana, in accordance with the plans and specifications prepared by the project engineer. The owner of this development is North Development Company, Inc. Both corporations are controlled and managed by T. W. Alley, Sr. and T. W. Alley, Jr.
Prior to execution of the written contract, McClure was furnished a copy of the original plans and specifications and an estimate of the quantities of work to be performed and the materials required by the project engineer. A bid proposal was prepared by him, dated January 5, 1971, quoting the unit cost of each phase of the work he offered to undertake. This proposal, addressed to the project engineer, reflected a total estimated cost of $57,814.30. Subsequent to the preparation of this written proposal the plans and specifications were changed by the project engineer (with approval of the FHA) to lower the required elevation of the entire subdivision one foot. Thus the amount of excavating in preparation for the paving of streets was substantially changed from that reflected by the original plans on which McClure based his proposal.
On November 3, 1971, the project engineer advised North Development Company, Inc., in writing of the completion by McClure of the various items of the construction undertaken by him, giving a composite total of the quantities of work performed and material used in connection therewith. The total cost of each item of work was computed by the engineer on the basis of the unit cost as reflected in the bid proposal submitted by McClure. The aggregate total of all work was shown to be $73,634.90.
At this point a dispute arose between McClure and the management of Southern Erection and North Development as to the amount due McClure for performance of the work.
Southern Erection and North Development contended by the provisions of the written contract McClure agreed to perform all work necessary for a lump price of $57,814.30 and that the changes in plans and specifications had no effect on this agreement. McClure contended he bid the work on a unit price basis and that he should be paid for the quantities of work actually performed on this basis and as shown on the certification of the project engineer.
On February 25, 1972, North Development Company, Inc., as owner of the subdivision and as assignee of all rights of Southern Erection under its contract with McClure by virtue of a written assignment, brought suit against McClure seeking damages and expenses incurred because of an alleged breach of the written contract by McClure in allowing liens to be filed against the property. North Development further asked for judgment ordering cancellation of the lien created by McClure's recordation of an affidavit setting forth his performance of work for which payment had not been received. North Development alleges that in the written contract McClure agreed to waive his rights to file liens against the property on which the work was to be performed and to accept the financial responsibility of Southern Erection, the prime contractor, as sufficient to secure any claim under the contract, and further agreed to protect the property from any lien of his subcontractors or materialmen. A breach of this obligation is alleged to have occurred by the *398 filing of the lien by McClure and two other liens perfected by Braswell Industries, Inc., and Braswell Concrete Products, Inc., resulting from non-payment by McClure for materials furnished him on this project.
In answer to this action McClure denied any breach of his contractual obligations and alleges completion of the work undertaken entitling him to payment of the sum of $73,634.90, less a payment of $6,837.75. He further alleges that although the written contract provides for payment within forty-five days after completion of the work, this amount has never been paid to him. McClure further contends the provision of the contract relating to waiver of lien rights is not supported by any consideration and is thus unenforceable.
On March 21, 1972, McClure filed suit against Southern Erection Co., Inc., North Development Co., Inc., and T. W. Alley, Jr., for the balance owed him for the work performed and for recognition of his lien on the property. In this action the defendants denied his entitlement to the amount claimed and again asserted by reconventional demand claims for damages in the amount of $12,500 against McClure for the same reasons advanced in the suit previously filed by North Development Co., Inc., against McClure.
After trial on the merits of the two suits, which were consolidated for the purpose of trial, judgment was rendered in the suit brought by North Development against McClure rejecting the plaintiff's demands. Judgment was rendered in favor of McClure in his action against Southern Erection and North Development casting those defendants for judgment in solido for the sum of $61,772.06, and maintaining the lien and privilege of McClure against the subject property.
In his reasons for judgment in Suit No. 12,056, North Development Co., Inc. vs. McClure, the trial judge concisely summarized the issues and his conclusions as follows:
"The contract document sued on was prepared by plaintiff's assignor and consequently its every ambiguity must be construed against the plaintiff. Although the contract document refers to plans and specifications prepared by Sammie Craft, Engineer, they were not annexed to and made part of the contract. Upon the trial of this cause the plaintiff did not introduce the plans and specifications and it remained for the defendant to produce the list of quantities upon which the recited contract price was obviously based, the recited consideration of $57,814.30 being the exact figure quoted by the defendant for the work described in his proposal.
"The plaintiff contends that the contract price of $57,814.30 was arrived at independently and that the list of estimated quantities was used only as a guide in negotiating with the defendant. The defendant insists that his bid proposal was based upon the list of estimated quantities required, on a unit price basis. He further contends that his proposal was prepared in the office of the plaintiff, signed by him at the same time he executed the contract and made a part thereof.
"While the plaintiff maintains that this was a lump sum contract requiring the defendant to do an unspecified amount of work, it is quite evident that both the defendant and the plaintiff's engineer understood that the defendant was to be paid on the basis of unit prices for the work required of him.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
276 So. 2d 395, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-development-company-inc-v-mcclure-lactapp-1973.