National Company, Inc. v. Krider

150 So. 2d 592, 1963 La. App. LEXIS 1377
CourtLouisiana Court of Appeal
DecidedMarch 4, 1963
DocketNo. 894
StatusPublished
Cited by5 cases

This text of 150 So. 2d 592 (National Company, Inc. v. Krider) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Company, Inc. v. Krider, 150 So. 2d 592, 1963 La. App. LEXIS 1377 (La. Ct. App. 1963).

Opinion

SAMUEL, Judge.

This is a suit on a building contract. Plaintiff is a roofing and siding contractor and its action is based upon the alleged fact that the defendant-owners of the property cancelled the contract under a provision giving them the right to cancel upon the payment of the expenses incurred by plaintiff plus liquidated damages in a minimum amount of 20% of the “cash amount of the contract”. The petition prays for such expenses, damages and attorney’s fees. -In a supplemental petition plaintiff prays, in the alternative and in the event liquidated damages are not allowed, that it be awarded in lieu thereof the amount of its anticipated gross profit. Defendants’ answer denied liability on the grounds that the contract was obtained by misrepresentation and reconvened for damages representing the expenditure allegedly necessary to put their building back into its original condition.

There was judgment in the trial court awarding plaintiff the sum of $200.00, the expenses the court found plaintiff had incurred, and awarding plaintiff in reconvention the sum of $200.00, the amount the court said was required to restore the premises. In his reasons for judgment the trial judge stated he found the contract had been invalidated by mutual error of fact. Plaintiff has appealed.

The contract called for installation by plaintiff of aluminum siding on defendants’ residence for a price of $2,500.00, payable $500.00 on completion and the balance, $2,-000.00 plus deferred plan credits, in 36 monthly payments of $63.88 each. That portion of the contract which related to the work to be done is hand written, obviously by plaintiff’s representative, in space provided therefor on plaintiff’s printed form. The writing is not completely clear as to the words “width” and “weather”, but appears to us to read as follows: “Mr. & Mrs. George Krider-2 story residential. Over weather boards install aluminum backing over weather boards then install new 5" aluminum weather board siding. Around all windows and doors install special window trim. Job to be done in strict accord with the factory directions”.

Plaintiff commenced the work and over a two week period was on the job for approximately two days or less when defendants stopped the work and cancelled the contract. Several reasons are given by defendants for the cancellation, such as a bad fit of an outside electric plug box, bad cuts, and other complaints of a minor nature, which were admitted by the plaintiff but, according to it, were of the type which could and would have been corrected upon completion of the job.

The main complaint by defendants was this: Plaintiff’s representative, a Mr. Fischer, explained to the defendants how the work was to be done. He stated to them that the aluminum was to be put directly on the weatherboards and that none of the wooden material in the house would be removed but simply would be covered. Defendants inquired about this because an iron railing around a gallery, a gate and awnings, all of which were attached to the house, would have to be re-attached. They needed the gate and railing because of the presence of children. And they were of the opinion that the attachment would not hold if the wooden material was removed, the aluminum itself being too thin. Accordingly they stopped the work when plaintiff’s employees removed the wooden corners which were holding the iron rail.

Defendants testified, as did. a third witness who was present when the discussion and signing of the contract took place, that Fischer assured them the wooden material would remain. The only other witness who was present, plaintiff’s representative Fischer, did not deny or contradict that testimony. He admitted the discussion and admitted going out on the gallery in order to look at the railing, but he testified that he did not remember making such assurances.

[594]*594Although the factory directions were not introduced and the record contains no evidence that Fischer was unfamiliar therewith, both sides appear to concede, and the trial judge was of the opinion, that those directions called for the use of aluminum corner boards and the removal of the wooden corners, and that neither plaintiff’s representative nor the defendants knew what the factory directions were. Since both conclusions, the factory directions calling for the removal of the wooden corners and the parties’ lack of knowledge regarding the factory directions, are favorable to plaintiff’s demand and in view of the fact that the trial court’s decision, and ours, is against that demand, we accept both conclusions.

There is some testimony in the record to the effect that the work could have been done in such a manner as to permit the desired attachments, as for example the use of two pieces of molding instead of the aluminum corner board, which would have been comparatively unsatisfactory from the standpoint of seal and maintenance. But when defendants complained and cancelled the contract they made many attempts to explain the cause of their concern to a proper representative of plaintiff. They were never able to explain and apparently the suggestion that the work could have .been done in the manner desired by defendants was made for the first time during the trial. In addition, the superintendent in charge of the job was proceeding under a work order and had no knowledge of Fischer’s conversation with the defendants. Regardless of what defendants did, or could reasonably be expected to do, the job was going to be done contrary to their understanding with Fischer. The. work was not done, and was not going to be done, in the manner plaintiff now says it could have been done.

We are satisfied from all of the testimony that prior to and at the time of entering into the contract defendants were concerned about the wooden material remaining on the premises so that they could be sure of preserving a means of attaching the rail, gate and awnings to the building and that this concern was known to plaintiff’s representative. We are also satisfied that defendants entered into the contract only after being assured by plaintiff’s representative that plaintiff would not remove any of the wood and that defendants would not have entered into the contract in the absence of such an assurance.

Plaintiff contends that the error of fact here involved is controlled by LSA-C.C. Arts. 1824—1826 and that under Art. 1825, which provides that in order to invalidate a contract the error in the cause must be on the principal cause (motive) when there are several, defendant cannot invalidate the contract in suit because the defendants’ motive in the instant case was the elimination of the necessity of painting the house after the siding was installed. We do not agree with the contentions. While defendants were interested in eliminating maintenance, the principal cause or motive here was the placing of- aluminum siding on the house, conditioned upon the work being done in a manner which would retain all of the building’s wooden materials. And there was a misunderstanding regarding the manner in which the work was to be done, an error of fact as to what the factory directions stated, between defendants and plaintiff’s representative. We agree with the trial judge that there was an error of fact which had the effect of invalidating the contract.

We are of the opinion that plaintiff has proved it is entitled to recover damages slightly in excess of' the award of $200.00 made by the.trial court. Sufficient proof has been made that .materials used in the job amounted to $130.42, labor to $64.54 and delivery of materials to $30.00, a total of $224.96.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hartsell v. Pipes Auto Shop, Inc.
318 So. 2d 627 (Louisiana Court of Appeal, 1975)
West Esplanade Shell Service, Inc. v. Breithoff
293 So. 2d 595 (Louisiana Court of Appeal, 1974)
North Development Company, Inc. v. McClure
276 So. 2d 395 (Louisiana Court of Appeal, 1973)
Cryer v. M & M Manufacturing Co.
253 So. 2d 69 (Louisiana Court of Appeal, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
150 So. 2d 592, 1963 La. App. LEXIS 1377, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-company-inc-v-krider-lactapp-1963.