North Carolina v. Hudson

731 F. Supp. 1261, 20 Envtl. L. Rep. (Envtl. Law Inst.) 21070, 1990 U.S. Dist. LEXIS 1576, 1990 WL 15434
CourtDistrict Court, E.D. North Carolina
DecidedFebruary 2, 1990
Docket84-36-CIV-5
StatusPublished
Cited by15 cases

This text of 731 F. Supp. 1261 (North Carolina v. Hudson) is published on Counsel Stack Legal Research, covering District Court, E.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Carolina v. Hudson, 731 F. Supp. 1261, 20 Envtl. L. Rep. (Envtl. Law Inst.) 21070, 1990 U.S. Dist. LEXIS 1576, 1990 WL 15434 (E.D.N.C. 1990).

Opinion

MEMORANDUM OPINION

BRITT, Chief Judge.

The City of Virginia Beach, Virginia, is seeking permission from the United States Corps of Engineers (the Corps) to construct a sixty-inch pipeline some 84.5 miles across southern Virginia and withdraw up to 60 million gallons of water per day (mgd) from Lake Gaston for the purpose of meeting its municipal water supply needs. After the Corps made a decision to issue the permits needed by Virginia Beach to accomplish the project, this action was begun by the State of North Carolina, the Roanoke River Basin Association (RRBA) and several counties in Virginia and North Carolina for judicial review of the decision of the Corps. Thereafter, this court conducted a review of the Corps’ decision under the Administrative Procedure Act, 5 U.S.C.A. § 706 (West 1977) and rendered a decision on 7 July 1987, State of North Carolina v. Hudson, 665 F.Supp. 428 (E.D.N.C.1987).

I. PROCEDURAL HISTORY

After a thorough review of the Administrative Record and consideration of the arguments and briefs of all parties, the court remanded the matter to the Corps. The court’s decision was very specific on the scope of the further review which was mandated:

On remand, the Corps shall:

1. As a part of its NEPA review make an independent assessment of the effects of the proposed project on striped bass to determine whether the preparation of an EIS [Environmental Impact Statement] is required or whether any mitigative measures are necessary; and,
2. As a part of its public interest review make a determination of the extent of Virginia Beach’s water needs.

Hudson, 665 F.Supp. at 450.

All other objections by plaintiffs to the decision 1 of the Corps were rejected. The *1263 court retained jurisdiction and directed the Corps to file with the court the results of its reconsideration and the record supporting its decision. The Corps has complied and the matter is now before the court for review of the supplemental record. 2

The record includes a Supplement Environmental Assessment (SEA), a Supplement Statement of Findings (SSOF) and a Revised Finding of No Significant Impact (RFONSI). 3 The Corps concluded that Virginia Beach’s withdrawal of water from Lake Gaston will have no significant impact on the human environment, that an environmental impact statement (EIS) is not necessary, and that the amount of the proposed withdrawal, 60 mgd, is needed.

II. BACKGROUND

In order to evaluate the potential for harm to the striped bass population from the withdrawal of water from Lake Gaston, it is necessary to understand the Roanoke River Basin and its interconnected system of lakes as well as the history and habits of striped bass.

A. THE ROANOKE RIVER BASIN

The Roanoke River is formed at the confluence of the North and South Forks in Montgomery County, Virginia, and flows generally in a southeasterly direction until it empties into the Albemarle Sound in northeastern North Carolina. Dams have been constructed on the river for both flood control and hydroelectric purposes, resulting in the formation of many lakes, the lower three of which, Kerr, Gaston and Roanoke Rapids, are important for this discussion. (Philpott and Smith Mountain are upstream from Kerr and are not directly affected by the project, although the amount of water released from them does affect the amount of water in the Kerr Lake reservoir.) Kerr Lake (also known as Bugg’s Island Lake) lies mostly in Virginia and is controlled by the Wilmington District of the Corps. Lake Gaston, just downstream of Kerr, lies mostly in North Carolina and is controlled by Virginia Power Company (VEPCO). Roanoke Rapids Lake is entirely in North Carolina, lies downstream of Gaston, and is also controlled by VEPCO.

By use of the dams, the flow of water can be restricted from the natural flow of the river during times of flood or high water conditions and increased during drought or low water conditions. Thus, more uniformity in stream flow can be accomplished than would occur naturally. Nevertheless, wide fluctuations still occur.

All three of the dams are operated primarily for peak power production although other goals — flood control, lake levels, and river flow — are also considered. It is the flow of the river below the last dam, Roanoke Rapids, that is of primary concern when considering the impact of the project on striped bass. As the flow of the river below Roanoke Rapids Dam is entirely dependent on natural rainfall and releases from the lake at the dam, the river theoretically, of course, could dry up. This condition is prevented, however, by the license issued to VEPCO by the Federal Energy Regulatory Commission (FERC) which requires minimum releases at the Roanoke Rapids Dam in amounts which vary throughout the year. Releases of at least 1,000 cubic feet per second (cfs) are required from November through March, 2,000 cfs from April through September, and 1,500 cfs in October. VEPCO always has enough water to meet these requirements because the Corps is required by hydropower contracts with VEPCO and Carolina Power & Light Co. (CP & L) to make releases which, when combined with *1264 natural drainage into Lake Gaston and Roanoke Rapids Lake, average at least 545 cfs (352 mgd) more than VEPCO’s minimums during every month of the year. Depending on its own power generation needs, VEPCO may store this surplus in Lake Gaston and Roanoke Rapids Lake for short periods of time and release it during peak electricity demand hours. The average flow of water through Roanoke Rapids Dam is 8,153 cfs.

The flow of water at Roanoke Rapids Dam is augmented during the striped bass spawning season pursuant to the terms of a 1971 Memorandum - of Understanding (MOU) among the Wilmington District of the Corps, VEPCO and the North Carolina Wildlife Resources Commission (NCWRC). Under this agreement the Corps is required to release stored water in Kerr Lake between elevations of 299.5 and 302 feet, mean sea level, during the spawning season so as to maintain, when possible, a minimum stage of 13 feet below the Roanoke Rapids Dam. This release equals an outflow from the Roanoke Rapids Dam of approximately 5700-6000 cfs. The agreement requires the augmented flow for a period of 50 days, which lasts from approximately 26 April until 15 June, although NCWRC determines the exact dates.

Kerr is the largest of the three lakes and is the primary storage facility in the system. In an average year, Kerr’s level fluctuates 12 feet, but in any given year it may fluctuate by as much as 27 feet, between elevations of 293 and 320 feet. 4 The Corps makes every effort to maintain Kerr’s level at the 293 minimum, but it is occasionally unable to do so and still release the amounts required by its contracts with the power companies. At those times, if the power companies agree, the Corps releases only enough water from Kerr to meet VEPCO’s required releases at Roanoke Rapids.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mattaponi Indian Tribe v. Commonwealth
601 S.E.2d 667 (Court of Appeals of Virginia, 2004)
North Carolina v. City of Virginia Beach
882 F. Supp. 77 (E.D. North Carolina, 1995)
City of Virginia Beach, Va. v. Brown
858 F. Supp. 585 (E.D. Virginia, 1994)
DTH Management Group v. Kelso
844 F. Supp. 251 (E.D. North Carolina, 1993)
Roanoke River Basin Association v. Hudson
991 F.2d 132 (Fourth Circuit, 1993)
Roanoke River Basin Association, and State of North Carolina Counties of Bertie, Granville, Halifax, Martin, Northampton, Vance, Warren & Washington, Nc Counties of Charlotte, Halifax & Mecklenburg, Virginia v. Ronald E. Hudson, in His Official Capacity as Norfolk District Engineer Wayne A. Hanson, in His Official Capacity as Wilmington District Engineer Joseph K. Bratton, Lt. Gen., in His Official Capacity as the Chief of Engineers of the U.S. Army Corps of Engineers William R. Gianelli, in His Official Capacity as Asst. Secretary of the U.S. Dept. Of the Army John O. Marsh, in His Official Capacity as Secretary of the U.S. Dept. Of the Army the City of Virginia Beach, National Wildlife Federation North Carolina Wildlife Federation, Amici Curiae. State of North Carolina, and Counties of Bertie, Granville, Halifax, Martin, Northampton, Vance, Warren & Washington, Nc Roanoke River Basin Association Counties of Charlotte, Halifax & Mecklenburg, Virginia v. Ronald E. Hudson, in His Official Capacity as Norfolk District Engineer Wayne A. Hanson in His Official Capacity as Wilmington District Engineer Joseph K. Bratton, Lt. Gen., in His Official Capacity as the Chief of Engineers of the U.S. Army Corps of Engineers William R. Gianelli, in His Official Capacity as Asst. Secretary of the U.S. Dept. Of the Army John O. Marsh, in His Official Capacity as Secretary of the U.S. Dept. Of the Army the City of Virginia Beach, National Wildlife Federation North Carolina Wildlife Federation, Amici Curiae
940 F.2d 58 (Fourth Circuit, 1991)
Roanoke River Basin Ass'n v. Hudson
940 F.2d 58 (Fourth Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
731 F. Supp. 1261, 20 Envtl. L. Rep. (Envtl. Law Inst.) 21070, 1990 U.S. Dist. LEXIS 1576, 1990 WL 15434, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-carolina-v-hudson-nced-1990.