North Carolina Utilities Commission v. Federal Energy Regulatory Commission

741 F.3d 439, 2014 WL 265489, 2014 U.S. App. LEXIS 1387
CourtCourt of Appeals for the Fourth Circuit
DecidedJanuary 24, 2014
Docket12-1881
StatusPublished

This text of 741 F.3d 439 (North Carolina Utilities Commission v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Carolina Utilities Commission v. Federal Energy Regulatory Commission, 741 F.3d 439, 2014 WL 265489, 2014 U.S. App. LEXIS 1387 (4th Cir. 2014).

Opinion

Affirmed by published opinion. Judge DUNCAN wrote the opinion, in which Judge WYNN and Judge THACKER joined.

DUNCAN, Circuit Judge:

The North Carolina Utilities Commission (“NCUC”) challenges incentives granted by the Federal Energy Regulatory Commission (“FERC”) to Virginia Electric Power Company d/b/a Dominion Virginia Power (“VEPCO”) to encourage investment in transmission infrastructure projects. NCUC argues that FERC violated § 219 of the Federal Power Act *443 (“FPA”) and abused its discretion by granting these incentives in 2008 and by denying its petition for rehearing in 2012. Constrained by the standard of review, we affirm.

I.

We begin with a brief description of FERC’s statutory authority to grant the incentives at issue. Under the Federal Power Act, FERC exercises general jurisdiction over all rates, terms, and conditions of interstate electric transmission service provided by public utilities. See 16 U.S.C. § 824(b). Congress amended the FPA in 2005 by passing the Energy Policy Act (“EPAct”) to create a national energy policy focused on increasing efficiency and innovation. Pub.L. 109-58, 119 Stat. 594 (2005); S. Rep. 109-78 at 1 (2005). In response to concerns about the reliability of the country’s aging transmission system, § 219 of the FPA required FERC to promulgate a rule establishing incentive-based rate treatments for qualifying projects to spur infrastructure investment. 16 U.S.C. § 824s (c). 1

After notice and comment, FERC adopted a final rule establishing a three-prong test for evaluating applications for incentives under § 219. Promoting Transmission Investment Through Pricing Reform, Order No. 679, FERC Stats. & Regs. ¶ 31,222, at P 326 (2006), order on reh’g, Order No. 679-A, FERC Stats. & Regs. ¶ 31,236 (2007), order on reh’g, Order No. 679-B, 119 FERC ¶ 61,062 (2007); codified at 18 C.F.R. § 35.35 (“Orders No. 679, 679-A, & 679-B”). First, the utility must show that its infrastructure project will increase reliability or reduce congestion. Order No. 679 ¶ 42. Second, the utility must demonstrate a nexus between the requested incentive and the project. Id. ¶48. Finally, the utility must prove that its resulting rates with the incentive remain “just and reasonable.” Id. ¶ 59. We briefly explain each prong.

A.

The requirement of prong one — a showing of either increased reliability or reduced congestion — is largely self-explanatory with one proviso relevant here. A utility can qualify for a rebuttable presumption that its infrastructure project will either ensure reliability or reduce transmission congestion if it resulted from a regional planning process that included consideration of reliability and cost reduction. Order No. 679 ¶ 58; Order No. 679-A ¶ 5.

B.

The analysis under prong two — determining whether the nexus requirement is met — is more challenging. A utility must demonstrate that the incentive will materially affect investment decisions by showing that it is “tailored to [the project’s] risks and challenges.” Order No. 679 ¶ 26; see also Order No. 679-A ¶21. Significantly here, a utility need not prove it would not undertake the project without the incentive. Order No. 679 ¶48. FERC determined that a but-for test would erect too high of an “evidentiary hurdle.” Order No. 679-A ¶ 25.

FERC has further clarified the parameters of the nexus test through adjudication. In Baltimore Gas & Electric Company, 120 FERC ¶ 61,084 (2007), FERC held that a project meets the nexus test if it is “not routine.” Id. ¶ 54. To make this determination, FERC considers all *444 relevant factors including: (1) the project’s scope measured in dollar investment or increase in transfer capability; (2) its impact on regional reliability or reduced congestion costs; and (3) project specific challenges including siting risks, political pressure, and difficulties in securing financing. Id. ¶ 52. FERC also held projects resulting from a regional planning process qualify as “not routine” because of their impact on regional reliability. .Id. ¶58. 2

FERC’s approach to applying the nexus test has evolved over time. Initially, when a utility included multiple, unrelated projects in a single application, FERC evaluated the projects in the aggregate to determine whether the nexus test was met. Order No. 679-A ¶ 27. While the utility was still required to “provide sufficient explanation and support to allow the Commission to evaluate each element of the package,” because an incentive for one project might lower the risk of another in the same application, FERC sought to ensure that the package of incentives as a whole would appropriately address the utility’s risk overall. Id.

In 2010, however, in PJM Interconnection, Inc., 133 FERC ¶ 61,273 (2010), and Oklahoma Gas and Electric Company, 133 FERC ¶ 61,274 (2010), FERC announced that it would no longer apply the nexus test in the aggregate to unrelated projects presented in a single application. Instead, a utility would be required to meet the nexus test for each individual project. PJM Interconnection, 133 FERC ¶ 61,273, at ¶ 45. This new policy would be applied “in this and future cases.” Id.

C.

Finally, under the third prong of the Order No. 679 test, a utility must demonstrate that its resulting rates are “just and reasonable” under § 219(d). This requirement clarifies that a utility seeking a § 219 incentive remains constrained by the requirement that its rates be “just and reasonable” under § 205 of the FPA. Order No. 679 ¶8. Under the FPA, a utility must obtain approval through a rate-setting process in order to raise its rates to incorporate an incentive. Id. ¶ 77. A utility meets this requirement if its return on equity (ROE) with the requested incentive falls within a “zone of reasonableness.” 3 Id. ¶ 91. With this explanation in mind, we turn now to FERC’s application of the three prongs of Order No. 679’s test to VEPCO’s application in its 2008 declaratory proceeding.

II.

On July 1, 2008, VEPCO, a member of PJM Interconnection LLC (“PJM”), 4 sought incentives for eleven transmission projects with a total estimated cost of $877 *445 million. VEPCO requested a 125 basis point adder for a bundle of seven projects, a mix of new construction and improvements to existing infrastructure. VEPCO requested an additional 150 basis point adder for a bundle of four larger-scale projects.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Securities & Exchange Commission v. Chenery Corp.
332 U.S. 194 (Supreme Court, 1947)
Burlington Truck Lines, Inc. v. United States
371 U.S. 156 (Supreme Court, 1962)
T-MOBILE NORTHEAST LLC v. City of Newport News
674 F.3d 380 (Fourth Circuit, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
741 F.3d 439, 2014 WL 265489, 2014 U.S. App. LEXIS 1387, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-carolina-utilities-commission-v-federal-energy-regulatory-commission-ca4-2014.