North Attleboro v. Hartford Fire
Opinion
USCA1 Opinion
April 29, 1994 [NOT FOR PUBLICATION]
UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT
____________________
No. 93-1685
NORTH ATTLEBORO ARMS REALTY TRUST,
Plaintiff, Appellant,
v.
HARTFORD FIRE INSURANCE COMPANY,
Defendant, Appellee.
____________________
APPEAL FROM THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF MASSACHUSETTS
[Hon. Joseph L. Tauro, U.S. District Judge]
___________________
____________________
Before
Breyer, Chief Judge,
___________
Coffin, Senior Circuit Judge,
____________________
and Torruella, Circuit Judge.
_____________
____________________
Guy E. Guarino for appellant.
______________
Raymond A. LaFazia with whom Gunning, LaFazia & Gnys, Inc. was on
__________________ ______________________________
brief for appellee.
____________________
____________________
BREYER, Chief Judge. The plaintiff in this case
____________
(the "Developer") is a real estate trust that hired a
Contractor to build condominiums. The Developer says that a
Subcontractor -- a maker of exterior walling systems --
defaulted on its contract to supply the condominiums with
"curtain walls." And, it has sued that Subcontractor's
surety, The Hartford Fire Insurance Company, for damages.
The district court, trying both the facts and the
law, found that the Developer suffered no harm -- at least,
none that legally entitles it to an award of damages. The
Developer now appeals, basically asking us to find that the
court's factfinding was "clearly erroneous." Fed.R.Civ.P.
52(a). The district court's findings, however, have
adequate record support; and, we therefore affirm its
judgment.
We have read the record in a light appropriately
favorable to the winning party, defendant Surety. See
___
Capt'n Mark v. Sea Fever Corp., 692 F.2d 163, 166 (1st Cir.
___________ ______________
1982). So read, the record reveals the following relevant
background facts:
1) In a contract dated December 2, 1987, the
Subcontractor promised the Contractor (which
in turn was controlled by the Developer) to
provide curtain walls for the condominium
building for a total price of $339,655.
2) As of June or July, 1988, the Subcontractor
had substantially completed the job. Several
months later, on November 4, 1988, the
Contractor's architect provided the
Subcontractor with a "punch list" of five
items to be corrected (such as "rust stains"
on certain walls, "misalignment" of certain
panels, "incomplete trim" around some sliding
doors, etc.) About ten days later, the
architect sent an expanded list of eight
items.
3) On November 18, 1988, the Subcontractor wrote
back that the work on the punch list "will
cost approximately $3,000 to $4,000 to
remedy." But, it would not perform that work
until the architect released its final
payment (which it estimated to be about
$31,000). It pointed out that the architect
retained an additional $34,000 (otherwise
belonging to the Subcontractor) as security
for performance; and, it agreed that the
architect need not release this money until
all the work was complete. In early
December, the Developer wrote to the
architect that the punch list work "ha[d] not
been started," that it would require 24 of
the units "to be plumbed out" (removing
existing dry wall), and that this would cost
$2,200 per condominium unit. A month later,
the Developer wrote to the Surety that the
Subcontractor was in "default."
4) Ten months later, in November 1989, the
Developer's counsel wrote to the Surety
stating that the Subcontractor's failure to
cure the punch list defects meant that the
Developer could not
conclude closings of
fifty-four (54)
units which were
under written
purchase and sale
agreements with
third parties.
-3-
3
He added that these "damages are not
speculative," and that he would like to work
with the Surety "in acquiring a settlement."
Counsel wrote further letters, threatened
legal action, and then, in preparing for
litigation in September 1990, had the
architect draw up a final repair cost
estimate totalling roughly $345,000.
After the Surety refused to pay, the Developer brought this
diversity action, arguing, among other things, that the
Surety broke its surety contract requiring it "promptly" to
Free access — add to your briefcase to read the full text and ask questions with AI
North Attleboro v. Hartford Fire, (1st Cir. 1994).
North Attleboro v. Hartford Fire (North Attleboro v. Hartford Fire) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Related
Capt'n Mark, Etc. v. Sea Fever Corporation
692 F.2d 163 (First Circuit, 1982)
Dedham Water Co., Inc. v. Cumberland Farms Dairy, Inc.
972 F.2d 453 (First Circuit, 1992)
Cierri's Case
396 N.E.2d 149 (Massachusetts Supreme Judicial Court, 1979)