Norman S. Wright & Co. v. Slaysman

27 Cont. Cas. Fed. 80,176, 604 P.2d 252, 124 Ariz. 321, 1979 Ariz. LEXIS 371
CourtArizona Supreme Court
DecidedNovember 8, 1979
Docket14494-PR
StatusPublished
Cited by3 cases

This text of 27 Cont. Cas. Fed. 80,176 (Norman S. Wright & Co. v. Slaysman) is published on Counsel Stack Legal Research, covering Arizona Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Norman S. Wright & Co. v. Slaysman, 27 Cont. Cas. Fed. 80,176, 604 P.2d 252, 124 Ariz. 321, 1979 Ariz. LEXIS 371 (Ark. 1979).

Opinion

HAYS, Justice.

Defendant-appellee, Melvin J. Slaysman, contracted with the Board of Education for remodeling of and additions to West High School in Phoenix. Appellee in turn subcontracted a portion of the undertaking to Southwest Air Conditioning (hereinafter referred to as the subcontractor). Plaintiff-appellant, Norman A. Wright & Co., supplied the subcontractor with materials used in the West High School project. Upon failure to receive payment, appellant turned to appellee, the general contractor, for compensation under the latter’s “Little Miller Act” and general contractors licensing bonds. Summary judgment was granted in favor of appellee from which plaintiff appealed. The Court of Appeals affirmed, and we granted appellant’s petition for review pursuant to 17A A.R.S. Rules of Civil Appellate Procedure, rule 23. The opinion *322 of the Court of Appeals (filed July 12, 1979) is vacated.

Two issues are presented for resolution by this court:

(1) whether appellee received sufficient notice of appellant’s “Little Miller Act” claim?

(2) whether A.R.S. § 32-1152 (Supp.1978) requires a contractual relationship?

“LITTLE MILLER ACT” CLAIM'

Appellant last supplied the subcontractor with materials for the West High School project on April 2, 1976. On June 7, 1976, appellant mailed the following letter, with copies of the relevant unpaid invoices attached, to appellee Slaysman:

Mel Slaysman Construction Company

1517 West Saharo Drive

Sunnyside, Arizona

Attn: Butch

Subject: West High School — Fans, Make-up Air Units, Air Curtain, Pennhouses, Hep Vane & Rail, Access Doors

SDN-4-100

Accounts Payable to Norman S. Wright & Co. SW

Balance on above job: $10,809.00

Southwest Air Conditioning,

Sub-contractor PO # 685

In accordance with instructions from you this morning, we are attaching hereto copies of invoices NOT PAID on above job.

We did receive joint check for $1,949.00 covering invoices listed and we did issue a “Partial” Lien Waiver on May 10th for this payment.

We shall appreciate your advice as to when we may receive your joint check in the above amount for the invoices as submitted. Thank you for your cooperation and assistance.

Very truly yours,

NORMAN S. WRIGHT & CO. SW

Martha Stewart, Phoenix Accts.

Rec.

MS:s

Attachments

Inv. #12614 $ 3355.00

#12739 2260.00

#12740 3753.00

#13388 585.00

7157 348.00

8178 120.00

13413 348.00

13318 40.00

$10,809.00

A.R.S. § 34-222(A)(2) requires all contractors involved in public construction to post a payment bond for the protection of suppliers of labor or materials. A.R.S. § 34 — 223(A) grants uncompensated suppliers the right to sue on this bond,

. provided however that any such claimant having a direct contractual relationship with a subcontractor of the contractor famishing such payment bond but no contractual relationship express or implied with such contractor shall have a right of action upon such payment bond upon giving written notice to such contractor within ninety days from the date on which such claimant performed the last of the labor or furnished or supplied the last of the material for which such
claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied .

Appellee claims that the June 7 letter constituted insufficient notice, under the above-quoted statutory language, that appellant was looking to it for payment. We cannot agree.

Initially, the letter’s subject line indicated that the correspondence concerned accounts payable to appellant, and listed both the balance due the supplier and the name of the debtor subcontractor. In addition, the mailing twice noted the inclusion of copies of unpaid invoices. Of particular significance is the request for the issuance of “your joint check” contained in the final paragraph. The record indicates that this makes reference to drafts issued by appellee jointly to appellant and the subcontractor.

Although all of the cases are in agreement in requiring notice as a prerequisite to an action on the contractor’s payment bond, there is no requirement in the *323 statute that the notice adopt a particular form. The writing need refer specifically to neither the Little Miller Act nor the payment bond itself. See, e. g., Coffee v. United States, 157 F.2d 968 (5th Cir. 1946) [interpreting the Federal Miller Act, 40 U.S.C. § 270 et seq.- (1969)]; Western Asbestos Co. v. TGK Construction Co., 121 Ariz. 388, 590 P.2d 927 (1979). In Western Asbestos, supra, we decided that the notice requirement is to be liberally construed in order to effectuate the Little Miller Act’s purpose of protecting those who furnish labor and material for public works. See also Coffee, supra. With this in mind, we hold that the June 7, 1976 letter constituted sufficient notice to appellee that appellant was looking to the general contractor for payment of the subcontractor’s bill.

Appellee additionally urges that, having been sent by ordinary, and not registered or certified mail, the June 7 correspondence violated the substance of § 34-223(A). 1 This argument, however, has been previously raised and rejected by this court. Western Asbestos, supra.

LICENSE BOND CLAIM

In addition to its “Little Miller Act” claim, appellant seeks recovery against the surety bond required by A.R.S. § 32-1152 (Supp.1978) of all contractors licensed in the state of Arizona.

Subsection D of § 32-1152 sets forth those persons entitled to recourse against the requisite licensing bond:

The bonds or deposit required by this chapter shall be for the benefit of any person covered by this subsection.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northland Pioneer College v. Zarco
875 P.2d 1349 (Court of Appeals of Arizona, 1994)
Ray Electric, Inc. v. Merchants Bonding Co.
758 P.2d 149 (Court of Appeals of Arizona, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
27 Cont. Cas. Fed. 80,176, 604 P.2d 252, 124 Ariz. 321, 1979 Ariz. LEXIS 371, Counsel Stack Legal Research, https://law.counselstack.com/opinion/norman-s-wright-co-v-slaysman-ariz-1979.