Norfolk & Western Railway Co. v. Hodges

448 S.E.2d 592, 248 Va. 254, 1994 Va. LEXIS 128
CourtSupreme Court of Virginia
DecidedSeptember 16, 1994
DocketRecord 931056
StatusPublished
Cited by11 cases

This text of 448 S.E.2d 592 (Norfolk & Western Railway Co. v. Hodges) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Norfolk & Western Railway Co. v. Hodges, 448 S.E.2d 592, 248 Va. 254, 1994 Va. LEXIS 128 (Va. 1994).

Opinion

JUSTICE COMPTON

delivered the opinion of the Court.

On September 9, 1987, appellee Ralph R. Hodges, the plaintiff below, was injured while working for appellant Norfolk and Western Railway Company, the defendant below, in the Huddleston area of Bedford County. The plaintiff brought this action against defendant under the Federal Employers’ Liability Act (FELA), 45 U.S.C. § 51 et seq., to recover damages for his injuries.

The plaintiff alleged that he was employed as a “gang signalman” on the day of the accident and was engaged in the removal of relay leads from a damaged relay system case. He further asserted that the defendant failed to provide a reasonably safe work environment for him and did not provide adequate safety devices that were properly operational to protect employees at the time. As a result of such carelessness and negligence, the plaintiff alleged, he was injured in the back, head, and neck when the doors of the damaged relay system case fell upon him. The plaintiff sought recovery in the sum of $4,759,312.00.

Responding, defendant denied the allegations of negligence. In addition, defendant affirmatively alleged that “plaintiff was guilty of contributory negligence with regard to any injuries and damages that he may actually have sustained.”

During a five-day trial by jury in April 1993, the court, over defendant’s objections, ruled that defendant was guilty of primary negligence proximately causing the accident and that plaintiff was free of contributory negligence. During consideration of the contributory negligence issue, the trial court described the question as “very close” and “awfully close.” The case was submitted to the jury on the issue of damages only, and the jury returned a verdict for the plaintiff in the sum of $5 million.

*257 Overruling defendant’s motion to set the verdict aside, the trial court reduced the jury award to the amount sued for and entered judgment in that sum in favor of the plaintiff. We awarded the defendant this appeal from the April 1993 judgment order; we also awarded the appeal upon plaintiff’s assignment of cross-error.

The defendant contends the trial court erred in entering summary judgment on the issues of primary and contributory negligence because the evidence was sufficient to submit those questions to the jury. The defendant also contends the court below erred in certain procedural and evidentiary rulings, and in refusing to set the verdict aside because it was excessive in amount. The cross-error deals with an alleged procedural error.

Initially, we shall address the negligence issues. The “established rule” under FELA jurisprudence is “that in passing upon whether there is sufficient evidence to submit an issue to the jury we need look only to the evidence and reasonable inferences which tend to support the case of a litigant against whom a peremptory instruction has been given.” Wilkerson v. McCarthy, 336 U.S. 53, 57 (1949). Thus, in summarizing the evidence, we shall recite only the evidence and reasonable inferences to support the defendant’s case upon both primary and contributory negligence. The only evidence on both issues was presented through witnesses called by the plaintiff; the defendant called no witness on those questions.

On September 5 and 6, 1987, a severe flood caused a stream next to one of defendant’s sidings near Huddleston to overflow resulting in extensive damage to the railroad’s facilities. The railroad’s signal system controlling movement of trains was “blacked out” from loss of power. Defendant’s supervisory personnel examined the flood damage to determine the necessary steps to place the signal system back into operation. The flood waters had damaged telephone poles and high tension electric lines supplying power to switches, signals, and the communication system. Many of the switches and signal cases were full of mud and water, and there were tree limbs and other debris on the tracks.

On September 7, damage in the area was reported to defendant’s signal maintainer for the section of track near Huddleston. On September 8, the maintainer went to the area and found signal cases at the siding “laid completely down on their backs” from the force of the flood waters.

*258 These signal cases were large, four-door, rectangular, metal cabinets measuring nine by six feet. Each case contained two compartments with metal shelves holding a number of removable signal relay units. There were two end doors and two interior doors. The interior doors were hinged at the center of the case. The end doors were hinged at each end of the case. The four doors opened outward to allow access to the compartments.

Normally, signal cases stand in an upright position. In that position, the vertical doors, weighing 66 pounds each, may be held open by a mechanism within the case at the top using a sliding arm and a tapered pin that drops, by gravity, into predrilled holes in the sliding arm’s frame. This mechanism permitted a door to open 90 degrees, or 180 degrees so that an interior door would be flat against the adjacent door and an end door would rest parallel to the front of the case.

On September 9, the day of the accident and after the flood waters had receded, the signal crew of which plaintiff was a member was ordered to the Huddleston area to repair flood damage. Testimony showed that because tracks of railroads operating in Virginia tend to “follow along by riverbeds, rivers, and streams,” a railroad ought to be aware that flooding “poses a hazard” to its operation. The evidence established that flooding of railroad facilities requires “an immediate response” and that nothing in defendant’s job description of plaintiffs duties included “emergency response” as a task “expected of the signalman.” The evidence further showed that while defendant required members of its signal crews to work “in flood conditions or emergency conditions,” no specific training was furnished those employees “as to how to deal with a flood situation.”

After plaintiff had worked during the morning at the west end of the damaged area digging up underground cables “to check” for cuts in the cable, volunteers were sought to go to the east end of the area, about two and one-half miles away, with a signal crew supervised by Tommy Topham. The plaintiff, who had no prior experience working in flood conditions, volunteered because the area where he had been digging was crowded with workers who “were practically beating each other with shovels in trying to dig in the same spot.”

The plaintiff arrived at the east end with Topham’s crew about mid-morning and began digging with several other workers “checking” cables for cuts. Topham and others were working on *259 overturned signal cases removing relays to be transported to Roanoke for repair. During the early afternoon, Topham asked the plaintiff to help “finish getting these relays out,” so plaintiff began to perform that task.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norfolk Southern Railway Co. v. Sumner
822 S.E.2d 809 (Supreme Court of Virginia, 2019)
Commonwealth v. Turner
87 Va. Cir. 132 (Charlottesville County Circuit Court, 2013)
NORFOLK BELT LINE R. CO. v. Wilson
667 S.E.2d 735 (Supreme Court of Virginia, 2008)
Phillips v. BJ's Wholesale Club, Inc.
77 Va. Cir. 129 (Norfolk County Circuit Court, 2008)
Norfolk Southern Ry. Co. v. Rogers
621 S.E.2d 59 (Supreme Court of Virginia, 2005)
Keranen v. National Railroad Passenger Corp.
743 A.2d 703 (District of Columbia Court of Appeals, 2000)
Norfolk Southern Railway Company v. Thomas
522 S.E.2d 620 (Supreme Court of Virginia, 1999)
Virginia Electric & Power Co. v. Dungee
520 S.E.2d 164 (Supreme Court of Virginia, 1999)
Norfolk Southern Railway Co. v. Trimiew
480 S.E.2d 104 (Supreme Court of Virginia, 1997)
Norfolk & Western Railway Co. v. Johnson
465 S.E.2d 800 (Supreme Court of Virginia, 1996)
Stover v. Norfolk & Western Railway Co.
455 S.E.2d 238 (Supreme Court of Virginia, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
448 S.E.2d 592, 248 Va. 254, 1994 Va. LEXIS 128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/norfolk-western-railway-co-v-hodges-va-1994.