Norfolk Southern Railway v. Sprint Communications

883 F.3d 417
CourtCourt of Appeals for the Fourth Circuit
DecidedFebruary 22, 2018
Docket16-2107
StatusPublished
Cited by6 cases

This text of 883 F.3d 417 (Norfolk Southern Railway v. Sprint Communications) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Norfolk Southern Railway v. Sprint Communications, 883 F.3d 417 (4th Cir. 2018).

Opinion

DIANA GRIBBON MOTZ, Circuit Judge:

Sprint Communications Company L.P. appeals the district court's order granting Norfolk Southern Railway Company's motion to confirm an arbitration award. Because the award is not "mutual, final, and definite" as required by the Federal Arbitration Act ("FAA"), we reverse and remand the case to the district court for further proceedings consistent with this opinion.

I.

On July 1, 1987, the predecessors of Sprint and Norfolk Southern entered into a License Agreement. Under the Agreement, Norfolk Southern granted Sprint the right to use certain of Norfolk Southern's railroad rights of way for Sprint's fiber optic telecommunications system for an initial term of 25 years. The License Agreement expired on June 30, 2012, but Sprint exercised its right to renew it for an additional 25-year period. This appeal stems from the parties' disagreement over the amount Sprint must pay Norfolk Southern to continue to use the railroad rights of way during the new 25-year term.

Section 2.2.2 of the Agreement outlines the agreed procedure for establishing this payment amount. It provides that, if the parties disagree on the amount, Sprint will select an appraiser to submit an estimate of the amount due. If Norfolk Southern rejects that estimate, it will hire its own appraiser, who will in turn submit his or her estimate. Section 2.2.2 further provides that if the two appraisers cannot agree on the amount due, they will select a third appraiser to broker a compromise.

When the parties' respective appraisers disagreed as to the amount due, they followed these procedures and appointed Charles Argianas as the third appraiser. Argianas, unclear as to how he should proceed in his role as the third appraiser, asked the parties for guidance. The joint response from Sprint and Norfolk Southern instructed Argianas to seek a compromise with one (or both) of the other appraisers. Only if he was unable to do so should he perform his own appraisal. 1

On December 11, 2014, after consulting with the parties' appraisers, Argianas emailed the parties a document titled "Majority Decision for Settlement Purposes Subject to Extraordinary Appraisal Assumptions." This Majority Decision sets forth the compromise Argianas had reached with Norfolk Southern's appraiser. The Majority Decision lists a dollar amount ($6,100,000) and refers to Article 2.2.2 of the Agreement. It explains that Argianas and Norfolk Southern's appraiser had assented to this Majority Decision but that Argianas "reserve[d] his assent without prejudice or time limitation subject to the following extraordinary appraisal assumptions: 1) Norfolk Southern in fact has marketable title of the occupancy corridor; and 2) [Norfolk Southern's appraiser's] ATF value is reasonable, which it appears to be." 2 The Majority Decision further states that "[i]f either of these extraordinary assumptions are found to not be true, Argianas ... reserves the right to withdraw his assent." Norfolk Southern accepted the payment amount contained in the Majority Decision and promptly billed Sprint for that amount. Sprint found the amount unacceptable and refused to pay.

Rather than resolving the matter, the Majority Decision led to further disputes that played out in parallel tracks.

Sprint filed a Demand for Arbitration with the American Arbitration Association ("AAA") pursuant to Section 20.5 of the Agreement, which provides that certain disputes related to the Agreement will be settled through AAA arbitration. In its demand for AAA arbitration, Sprint claimed Norfolk Southern had "unilaterally terminated" the Section 2.2.2 process before that process had run its course such that no final determination had been issued as to the amount Sprint owed. Sprint asked the AAA panel to determine the amount Sprint owed-even though the parties had already spent significant time and effort attempting to resolve that same question pursuant to the procedures outlined in Section 2.2.2.

Meanwhile, Norfolk Southern brought this action against Sprint in the federal district court, seeking enforcement of the Majority Decision as a final and binding arbitration award. Because Section 2.2.2 of the Agreement provided the procedures for establishing the payment amount, Norfolk Southern maintained that the arbitration provision contained in Section 20.5 did not apply. Accordingly, Norfolk Southern asked the district court to enter a judgment against Sprint for breach of contract, declare the Majority Decision final and binding, and stay the AAA arbitration. 3

Thus, at this stage, the dispute between the parties had three essential components. First, the parties disputed whether the Majority Decision constituted a final and binding arbitration award and whether Sprint had breached its contractual obligations by refusing to pay the amount established by the Majority Decision. Second, they disagreed as to the appropriate forum for resolving this dispute. Sprint argued that, pursuant to Section 20.5 of the License Agreement, disputes related to the Majority Decision must be settled through AAA arbitration; Norfolk Southern maintained that Section 20.5 did not apply to claims raised by Sprint and that the parties should proceed in district court. Finally, the parties disagreed as to who should decide whether the parties should proceed in district court or in AAA arbitration proceedings. Sprint asserted that the AAA arbitrators convened under Section 20.5 must decide that question while Norfolk Southern contended the district court must provide the answer.

As to the procedural question-who should decide whether Section 20.5 applies to the dispute-Sprint appeared to have won the day in the district court. On August 21, 2015, without explanation, the district court stayed the litigation initiated by Norfolk Southern so that the AAA arbitration demanded by Sprint could proceed. However, the panel of AAA arbitrators then issued a decision favorable to Norfolk Southern. In particular, the AAA panel found that the Majority Decision constituted a final and binding arbitration award, which Sprint could challenge in court under narrow grounds provided in the FAA-and not in subsequent AAA arbitration. 4

After the AAA panel issued its decision, Norfolk Southern moved to confirm the Majority Decision in district court pursuant to the FAA, and Sprint moved to vacate it. Given the AAA panel's conclusion that the Majority Decision was an arbitration award, Norfolk Southern claimed the only question for the district court was whether the award passed muster under the deferential standard of review outlined in the FAA. It appears that Sprint agreed, because, although it attacked the award on other FAA grounds, it never urged the court to hold that the Majority Decision was not an arbitration award. The district court granted Norfolk Southern's motion to confirm the Majority Decision and denied Sprint's motion to vacate it. Sprint then noted this timely appeal.

II.

On appeal, the parties focus their dispute on whether the district court erred in concluding the Majority Decision was a "final" arbitration award under the FAA. Neither party claims that the Majority Decision is not an FAA arbitration award.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
883 F.3d 417, Counsel Stack Legal Research, https://law.counselstack.com/opinion/norfolk-southern-railway-v-sprint-communications-ca4-2018.