Norden Sys. v. General Dynamics Corp., No. Cv89 0101260 S (Nov. 8, 1990)

1990 Conn. Super. Ct. 3600
CourtConnecticut Superior Court
DecidedNovember 8, 1990
DocketNo. CV89 0101260 S
StatusUnpublished

This text of 1990 Conn. Super. Ct. 3600 (Norden Sys. v. General Dynamics Corp., No. Cv89 0101260 S (Nov. 8, 1990)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Norden Sys. v. General Dynamics Corp., No. Cv89 0101260 S (Nov. 8, 1990), 1990 Conn. Super. Ct. 3600 (Colo. Ct. App. 1990).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION RE: MOTION TO STRIKE Plaintiff, Norden Systems, Inc. ("Norden") brings this six count revised second amended complaint, dated February 8, 1990 against the defendant, General Dynamics, Inc., ("General CT Page 3601 Dynamics"). In the first five counts, plaintiff requests damages allegedly sustained as a result of (1) the defendant's breach of contract, (2) the defendant's breaches of a contractual duty of good faith and fair dealings, (3) intentional interference with prospective economic advantage, (4) violations of Conn. Gen. Stat. 42-110a (CUTPA), and (5) fraudulent concealment. In count six, plaintiff, Norden, seeks a determination of the termination provision of the parties contract.

Defendant General Dynamics moves this court to strike counts three and four on the grounds of legal insufficiency.

Plaintiff Norden has alleged the following facts which are relevant to a determination of the defendant's motion to strike.

In 1987 the United States Navy announced that General Dynamics and the McDonnell-Douglas Corporation would be awarded a contract to produce an aircraft which is expected to be in use in the mid-1990's. Prior to this announcement, plaintiff Norden and defendant General Dynamics agreed that if General Dynamics received the aircraft contract, Norden would supply the radar system for the aircraft.

Subsequently, Norden and General Dynamics executed a letter subcontract under which General Dynamics obligated itself to pay Norden over $100 million dollars to design and develop the radar system for the aircraft. The radar subcontract letter stated that it would be superseded by a fixed price definitive contract for work described in the letter no later than May 30, 1988. This definitive contract was never executed.

Norden alleges that, after the execution of the subcontract letter, General Dynamics unilaterally ordered formal and informal changes in the technical requirements for the radar system. The changes allegedly resulted in increased costs and Norden exercised its right to request equitable adjustments in the subcontract price and schedule. The parties did not agree on a revised price and schedule, and plaintiff's performance allegedly continued without a schedule.

Until November of 1988, General Dynamics made progress payments to the plaintiff for its ongoing performance. After November, 1988, General Dynamics allegedly ceased making progress payments without offering any explanation. General Dynamics also discontinued its incremental funding of the radar subcontract from funds received from the Navy and made no funds available after January 6, 1989. Norden allegedly attempted to obtain General Dynamics' compliance and determine its intentions by contacting General Dynamics officials, but without success. CT Page 3602

Plaintiff alleges that General Dynamics' failure to pay progress payments and to make funds available amounted, individually and collectively, to a termination of the contract. This termination, plaintiff alleges, was wrongful and unjustified under the terms of the radar subcontract.

On April 14, 1989, General Dynamics issued a default termination notice to the plaintiff, which notice plaintiff alleges was wrongful and/or had no legal effect in that (1) it was not preceded by a required cure notice, (2) Norden was not in default and (3) in any event, the radar subcontract had already been terminated by General Dynamics' own actions.

Defendant General Dynamics filed a memorandum, a supplemental brief, and a reply in support of its motion to strike counts three and four and plaintiff Norden filed a memorandum in opposition.

The purpose of a motion to strike is to challenge the legal sufficiency of a complaint. Conn. Practice Bk. 152. In reviewing a motion to strike, all pleaded facts and those necessarily implied therefrom are admitted. Amodio v. Cunningham, 182 Conn. 80, 83 (1980). The allegations must be construed in a manner most favorable to the pleader. Mozzochi v. Beck, 204 Conn. 490, 491 (1987).

Defendant General Dynamics challenges plaintiff's third count sounding in tortious interference on the grounds that (1) the count fails to allege interference between plaintiff and a third party and (2) plaintiff's claims for damages are too speculative to amount to the requisite actual loss.

In support of its argument that the plaintiff's failure to allege an economic relationship with a third party renders count three legally insufficient, defendant General Dynamics cites extra judicial cases in which courts held that actual damage to a business relationship expectancy with a third party was a necessary element of the tort. Ellis v. City of Valdez,686 P.2d 700, 708 (Alaska 1984) (court concluded that the tort contemplated wrongful interference with a developing relationship by an outsider to that relationship); Riseman v. Orion Research, Inc., 394 Mass. 311, 475 N.E.2d 398 (1985) (court found that defendant corporation could not tortiously interfere with its own relationship with plaintiff stockholder).

Research discloses that it is considered tortious either to induce a breach of contract or to interfere with financial expectancies. Connecticut courts have tended to confuse the two separate actions and, consequently, there is no clear enumeration of their requisite elements. CT Page 3603

The tort of interference with contractual relations only lies when a third party adversely affects the contractual relations of two other parties. Heirs v. Cohen, 31 Conn. Sup. 305,310 (1973) Citing R and W Hat Shop, Inc. v. Sculley,98 Conn. 1, 14 (1922).

The tort of interference with economic expectancies has been recognized in Connecticut since the case of Bulkley v. Storer, 2 Day (Conn.) 531 (1807). See Also Sportsmen's Boating Corp. v. Hensley, 192 Conn. 747, 754 (1984); Busker v. United illuminating Co., 156 Conn. 456, 461 (1968); Golembeski v. Metichewan, Grange No. 190, 20 Conn. App. 699, 702-03 (1990), cert. den.,214 Conn. 809 (1990); Selby v. Pelletier, 1 Conn. App. 320, 322 (1984). The essential elements of this cause of action are: (1) that the defendant's conduct was tortious conduct, such as fraud; and (2) that as a consequence of such conduct, the plaintiff suffered actual loss as alleged, in being deprived of an opportunity which he would otherwise have had. Selby,1 Conn. App. at 323-24, citing Busker, 156 Conn. at 461. In order to succeed on a claim of tortious interference with business expectancies, however, the plaintiff must do more than show that the defendant's actions proximately caused a loss to the plaintiff's business. He must prove that the defendant was guilty of fraud, misrepresentation, intimidation or molestation, or that the defendant acted maliciously. Sportsmen's,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Busker v. United Illuminating Co.
242 A.2d 708 (Supreme Court of Connecticut, 1968)
Amodio v. Cunningham
438 A.2d 6 (Supreme Court of Connecticut, 1980)
Miller v. Appleby
438 A.2d 811 (Supreme Court of Connecticut, 1981)
Riseman v. Orion Research Inc.
475 N.E.2d 398 (Massachusetts Supreme Judicial Court, 1985)
Ellis v. City of Valdez
686 P.2d 700 (Alaska Supreme Court, 1984)
Selby v. Pelletier
472 A.2d 1285 (Connecticut Appellate Court, 1983)
R an W Hat Shop, Inc. v. Sculley
118 A. 55 (Supreme Court of Connecticut, 1922)
Levine v. Bess & Paul Sigel Hebrew Academy of Greater Hartford, Inc.
471 A.2d 679 (Connecticut Superior Court, 1983)
Hiers v. Cohen
329 A.2d 609 (Connecticut Superior Court, 1973)
Sportsmen's Boating Corp. v. Hensley
474 A.2d 780 (Supreme Court of Connecticut, 1984)
Atlantic Richfield Co. v. Canaan Oil Co.
520 A.2d 1008 (Supreme Court of Connecticut, 1987)
Web Press Services Corp. v. New London Motors, Inc.
525 A.2d 57 (Supreme Court of Connecticut, 1987)
Mozzochi v. Beck
529 A.2d 171 (Supreme Court of Connecticut, 1987)
Daddona v. Liberty Mobile Home Sales, Inc.
550 A.2d 1061 (Supreme Court of Connecticut, 1988)
Sanghavi v. Paul Revere Life Insurance
572 A.2d 307 (Supreme Court of Connecticut, 1990)
Golembeski v. Metichewan Grange No. 190
569 A.2d 1157 (Connecticut Appellate Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
1990 Conn. Super. Ct. 3600, Counsel Stack Legal Research, https://law.counselstack.com/opinion/norden-sys-v-general-dynamics-corp-no-cv89-0101260-s-nov-8-1990-connsuperct-1990.