Noram Gas Transmission Company, a Delaware Corporation v. Enterprise Resource Corporation, an Arkansas Corporation, and Alan G. Mikell

141 F.3d 1185, 1998 U.S. App. LEXIS 14116, 1998 WL 165166
CourtCourt of Appeals for the Tenth Circuit
DecidedApril 9, 1998
Docket97-5170
StatusPublished

This text of 141 F.3d 1185 (Noram Gas Transmission Company, a Delaware Corporation v. Enterprise Resource Corporation, an Arkansas Corporation, and Alan G. Mikell) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Noram Gas Transmission Company, a Delaware Corporation v. Enterprise Resource Corporation, an Arkansas Corporation, and Alan G. Mikell, 141 F.3d 1185, 1998 U.S. App. LEXIS 14116, 1998 WL 165166 (10th Cir. 1998).

Opinion

141 F.3d 1185

98 CJ C.A.R. 1652

NOTICE: Although citation of unpublished opinions remains unfavored, unpublished opinions may now be cited if the opinion has persuasive value on a material issue, and a copy is attached to the citing document or, if cited in oral argument, copies are furnished to the Court and all parties. See General Order of November 29, 1993, suspending 10th Cir. Rule 36.3 until December 31, 1995, or further order.

NORAM GAS TRANSMISSION COMPANY, a Delaware corporation,
Plaintiff-Appellee,
v.
ENTERPRISE RESOURCE CORPORATION, an Arkansas corporation, Defendant,
and
Alan G. MIKELL, Defendant-Appellant.

No. 97-5170.

United States Court of Appeals, Tenth Circuit.

April 9, 1998.

Before BALDOCK, EBEL, and MURPHY, Circuit Judges.

ORDER AND JUDGMENT*

DAVID M. EBEL, Circuit Judge.

After examining the briefs and appellate record, this panel has determined unanimously that oral argument would not materially assist the determination of this appeal. See Fed. R.App. P. 34(a); 10th Cir. R. 34.1.9. The case is therefore ordered submitted without oral argument.

Defendant-appellant Alan G. Mikell appeals the district court's judgment in favor of plaintiff-appellee Noram Gas Transmission Company. Because the district court's findings are supported by the evidence, we affirm.

I. Background

Plaintiff Noram Gas Transmission Company is the successor in interest of Arkla Energy Resources. In April 1989, Arkla entered into a settlement agreement with defendants Mikell and Enterprise Resource Corporation to resolve a dispute arising out of gas purchase contracts involving thirty-eight wells in which Mikell and Enterprise owned interests.1 The agreement provided for a prepayment by Arkla of two million dollars, to be recouped from future gas production by defendants over a five and a half year period.

The agreement provided that Arkla could recoup its prepayment through cash refunds from defendants under certain circumstances. Section 2(c) of the agreement provided that if in any calendar quarter Arkla, or its designee, requested delivery of a daily average volume of gas equal to those volumes specified in section 2(b)(ii) of the agreement, and defendants failed to deliver such volumes, Arkla would be entitled to a refund. These volumes were known as the "minimum volumes." The agreement provided that requests for minimum volumes could be satisfied out of the thirty-eight wells identified in the agreement or from any other source.

In addition to the requests for minimum volumes, the agreement required Arkla to make a monthly nomination of the percentage it desired of defendants' "daily deliverability," which is an estimate of a well's daily capability of natural gas production. Arkla could nominate gas only from the thirty-eight wells identified by the agreement in which defendants had interests. When the agreement was signed, the total daily deliverability attributable to defendants from the wells was greater than the minimum volumes set out in the agreement. Thereafter, defendants' daily deliverability declined to an amount less than the minimum volumes. It is undisputed that Arkla/Noram always nominated one hundred percent of defendants' daily deliverability.

The agreement also provided that upon termination of the subject contracts or a judicial determination that defendants breached the contracts or the settlement agreement, defendants were required to refund immediately the unrecouped portion of the prepayment.

In August 1994, Noram Gas Transmission, as successor in interest to Arkla, brought this action against Mikell and Enterprise. Noram alleged that throughout the recoupment period there was a standing request for the minimum volumes of gas set forth in the agreement, and that defendants failed to deliver the requested amounts or make any refunds. Defendants responded that Arkla, and later Noram, never requested the minimum volumes so as to initiate the refund provision, relying on plaintiff's monthly nominations for daily deliverability. Defendants counterclaimed against Noram for damages resulting from Arkla/Noram's alleged breach of the recoupment provisions in the settlement agreement.

After a bench trial, the district court found that Arkla/Noram had a standing request for the minimum volumes set out in the agreement, that there was a difference between a "request" for the minimum volumes from defendants and a "nomination" of daily deliverability from the thirty-eight wells identified by the agreement, and that defendants failed to deliver the requested amounts, thus triggering the refund provision. The court found the damages provision of the agreement, requiring reimbursement of the unrecouped balance of the prepayment, reasonable. Pursuant to 12 Okla. Stat. § 936, the court awarded Noram attorneys fees jointly against Mikell and Enterprise.

On appeal, Mikell argues that the district court's factual findings are contrary to the evidence; that the court erred in enforcing the liquidated damages provision of the agreement; that the court erred in finding the settlement agreement to be a contract for the sale of goods entitling Noram to attorneys fees; and that the court abused its discretion in awarding attorneys fees jointly against Mikell and Enterprise.

II. Breach of Contract

Mikell's primary argument on appeal is that the district court's factual finding that Noram had a standing request for the minimum volumes of gas during the recoupment period is contrary to the evidence. We must accept the district court's findings of fact unless they are clearly erroneous. See Exxon Corp. v. Gann, 21 F.3d 1002, 1005 (10th Cir.1994). A finding of fact is clearly erroneous if it is without factual support in the record or if, after reviewing all the evidence, we are left with a definite and firm conviction that a mistake has been made. See Cowles v. Dow Keith Oil & Gas, Inc., 752 F.2d 508, 511 (10th Cir.1985). We review the evidence in the light most favorable to the district court's ruling and must uphold any finding that is permissible in light of the evidence. See Exxon Corp., 21 F.3d at 1005; see also Anderson v. City of Bessemer City, 470 U.S. 564, 573-74, 105 S.Ct. 1504, 84 L.Ed.2d 518 (1985) ("If the district court's account of the evidence is plausible in light of the record viewed in its entirety, the court of appeals may not reverse it even though convinced that had it been sitting as the trier of fact, it would have weighed the evidence differently. Where there are two permissible views of the evidence, the factfinder's choice between them cannot be clearly erroneous.").

Here, the district court's factual finding regarding the standing request for minimum volumes is well supported by the evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
141 F.3d 1185, 1998 U.S. App. LEXIS 14116, 1998 WL 165166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/noram-gas-transmission-company-a-delaware-corporat-ca10-1998.