Noonan v. Stein

56 Colo. 64
CourtSupreme Court of Colorado
DecidedSeptember 15, 1913
DocketNo. 7098
StatusPublished
Cited by3 cases

This text of 56 Colo. 64 (Noonan v. Stein) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Noonan v. Stein, 56 Colo. 64 (Colo. 1913).

Opinion

Mr. Justice Hill

delivered the opinion of the court:

This action involves the interpretation of certain portions of a contract between The Otero Irrigation District and Noonan and O’Neill. The court found that the district has in its possession $12,908.64 due Noonan and O’Neill, which the decree holds was a fund created by express agreement for the express purpose of satisfying claims for labor and material furnished to, and used by, Noonan and O’Neill in the construction of a reservoir for the district. By reason of these findings it was held that the appellees (who were subcontractors, material-men and laborers under the contractors Noonan and O’Neill) were entitled to have most of this fund applied in payment of their claims against the contractors. Judgments were entered accordingly.

The case was disposed of upon the admissions contained in the pleadings and an agreed statement of facts. They disclose that the district was organized under our irrigation district statutes; that it entered into a written contract with Noonan and O’Neill for the construction of a reservoir for which it agreed to pay a certain sum; that the contractors entered upon the construction of this work, during which period they were paid eighty-five per cent of their estimates, fifteen per cent being reserved under the provisions of the contract; that the contractors failed to comply with the terms of the contract, on account of which the district gave them notice to discontinue the work, which they did, all as provided [67]*67by the terms of the contract; that the district then advertised for bids for finishing the uncompleted portion, let a contract therefor under which it was completed. This cost the district $17,047 more than it would have cost had it been completed under the terms of the original contract with Noonan and O’Neill. The district claims the right to charge the contractors with this difference, as an offset, or to recoup as much of this amount as will offset the fifteen per cent unpaid under the estimates. The appellees performed labor and furnished material under Noonan and O’Neill who still owe them about $12,000 therefor. After the termination of the contract as aforesaid, the appellees filed mechanics ’ liens upon the reservoir, and thereafter instituted suits against the contractors, and the district, to recover judgments against the contractors, and to have their liens foreclosed against the property in order to enforce payment. Personal judgments were awarded against the contractors, but the right to maintain their mechanics ’ liens against the property of the district was denied and the actions dismissed as against the district. No appeals were taken from these judgments. The appellees thereafter instituted the present action against the contractors and the district, in which they make the claim, that the fifteen per cent of the estimates withheld from the contractors by the district was a fund created by express agreement for the express purpose of satisfying their claims for labor and material; that the terms of the contract created an equitable assignment of this fund for the benefit of this class of creditors of the contractors; that in this respect the district constituted itself a trustee of this fund for the benefit of the appellees and others similarly situate. To sustain this position the appellees rely upon certain portions of the contract which read as follows:

Sec. 2. “The work embraced in the contract shall be commenced within fifteen days after the execution of the [68]*68contract, - * * * and carried on regularly and uninterruptedly thereafter with sufficient force to insure its completion on or before the first day of January, 1908. Failure to shall render the contractor liable to the Otero Irrigation District in the sum of twenty-five dollars ($25) as.liquidated damages for each and every day’s delay in commencing the work: For reasons satisfactory to the board, said board may waive any claims upon the contractor for damages here referred to.”
Sec. 12. “Should the contractor fail to begin the work within the time stipulated, or fail to prosecute the work in such manner as to insure a full compliance with the contract within the time limit, or fail to perform the said work in compliance with the terms of the contract and the specifications hereto annexed, and the directions of the engineer, or neglect or refuse to remove or rebuild such work as shall have been rejected by the engineer as being defective or unsuitable, the board shall notify the contractor to that effect in writing; and if the contractor shall not within ten days thereafter take such measures as will insure the satisfactory performance or construction of the work within the time limit, the board may notify the contractor to discontinue all work under his contract, and the contractor shall immediately respect said notice and stop work, and cease to have any rights to the possession of the ground and shall forfeit his contract. The board may, thereupon, advertise and let a contract for the uncompleted work in the same manner as was followed in the letting of this contract and charge the cost thereof to said original contractor upon this contract. It is distinctly understood that £time,’ whenever mentioned in this contract, is of the essence of this agreement. ’ ’
Sec. 16. ‘ ‘ The contractor shall be subject to the laws of the state of Colorado regarding liens for labor and [69]*69materials furnished for said work, and shall protect and indemnify the boárd against all legal claims or liens against the work for labor and materials furnished to the contractor, or to parties who may have furnished labor or materials for said work, out of any moneys due or to become due him, and the board shall charge the same to the contractor as so much paid on this contract and the board may from time to time retain such reasonable sums as it may deem necessary for its protection in this behalf, and the contractor shall pay the deficiency arising therefrom upon demand.”
Sec. 20. “Payments shall be made, monthly, to the contractor, on or about the fifteenth day of each month, in installments of eighty-five per cent of all moneys due for the work done or materials delivered under this contract, up to and including the last day of the preceding month, under and in accordance with the provisions and stipulations of this contract based on estimates of work completed, made and certified to by the engineer and approved by the board.”

The appellees claim it is also necessary to take into consideration a part of section 23 of the irrigation district act of 1905, which reads:

“The person or persons to whom a contract may be awarded shall enter into a bond, with good and sufficient sureties, to be approved by the board, payable to said district for its use, for not less than ten per cent of the amount of the contract price, conditioned for the faithful performance of said contract.”

The district contends that section 21 of the contract should also be considered in arriving at the intention of the parties; it reads:

Sec. 21. “When all the work embraced in this contract is fully completed agreeably to the stipulations and [70]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bishop and Diocese of Colorado v. Mote
716 P.2d 85 (Supreme Court of Colorado, 1986)
Depner v. Joseph Zukin Blouses
56 P.2d 574 (California Court of Appeal, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
56 Colo. 64, Counsel Stack Legal Research, https://law.counselstack.com/opinion/noonan-v-stein-colo-1913.