A. E. Shorthill Co. v. Bartlett

108 N.W. 308, 131 Iowa 259
CourtSupreme Court of Iowa
DecidedJuly 11, 1906
StatusPublished
Cited by3 cases

This text of 108 N.W. 308 (A. E. Shorthill Co. v. Bartlett) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. E. Shorthill Co. v. Bartlett, 108 N.W. 308, 131 Iowa 259 (iowa 1906).

Opinion

Weaver, J.—

Plaintiff, a corporation, claims that pursuant to a contract with defendant Bartlett and his eodefendants, William Hitaffer and Carl Prouty, it' manufactured and sold to defendant certain iron columns and plates specially designed and fitted to be used in the construction of a block or building in the city of Estherville, Iowa. It is further alleged that said material constituted only a part of a larger order given by said defendants for iron work to be used in said building, and that while the work of manufacturing and preparing the several items of material so ordered was in progress, and after the columns and plates above mentioned had been completed, ready for delivery, the defendant Bartlett ordered the work stopped and refused to receive or pay for such material. Judgment is asked against defendants for the reasonable value of said items and that a lien therefor be established upon the property. The defendant Bartlett, separately answering, denies having ordered the materials from plaintiff, denies having entered, into any contract or agreement to pay therefor, and denies that any other person had authority to make such order, agreement, or purchase in his behalf. He further pleads that he let the contract to his codefendants to furnish the materials and do the work of constructing said building, and avers that by the [261]*261negligence of his codefendants said building, when partially completed, collapsed, and in view of the situation thus produced he entered into an additional contract with said contractors, Hitaffer and Prouty, agreeing therein to advance the necessary money to pay for the materials and labor required to restore said building. He further says that about this time the appellee wrote a letter to Hitaffer and Prouty, stating that it was about ready to cast certain iron columns such as .were required in said building and-would furnish them at $52 each. This letter, he says, was immediately shown him by Hitaffer and Prouty, and he agreed that they should order the said columns on the terms thus proposed, and he avers that the columns which plaintiff claims to have manufactured for his building were much larger and heavier than was contemplated when the order was made, and upon learning that fact, and learning that plaintiff intended to demand a proportionately higher. price for said work, he promptly notified plaintiff not to ship it.

Appellant further pleads that, Hitaffer and Prouty having failed to complete the building as provided by their agreement, he has been compelled at great loss to employ other help and complete it himself, and that after paying the expense thus incurred there is nothing whatever in his hands due to said contractors, but, on the contrary, there is a large balance due and owing from them to him. In reply plaintiff pleads that by reason of matters hereinafter more fully stated the appellant is estopped to deny his liability for the payment of the claim in suit.

The testimony, most of which is undisputed, tends to show that Bartlett let to Hitaffer and Prouty the contract for furnishing the material and erecting the building in question in accordance with plans prepared by James S-. Cox, architect. The building was to be erected under the supervision of the architect, and the appellant reserved the privilege of taking possession of the work and completing it at any time upon notice or certificate by the architect of any [262]*262neglect or failure of the contractors to conform to the terms of their agreement. When in a state of partial completion, and while the work of the contractors was still in progress, a portion of the building collapsed. Some controversy ensued as to which party should bear the burden of this loss, but finally appellant and Hitaffer and Prouty entered into a written agreement for the restoration and completion of the building, leaving the disputed question as’ to which party should finally bear the loss to future settlement.

The contract is too long to be here set out in extenso. The stipulations material to this controversy provide that Hitaffer and Prouty shall proceed at once to remove the fallen portion of the building and rebuild and construct the same with such changes in kinds of material and’ manner of building as Bartlett shall desire and for which he shall furnish proper plans and specifications, all of said work to be done under the supervision of Bartlett or his agent. The contractors on their part agreed to keep and furnish to Bartlett an accurate account of the expense incurred in restoring the building to its former condition, as well as for each item of new material and of all substituted materials differing from those provided in the' original plan. It was further agreed that, as Hitaffer and Prouty claimed to be financially unable to go on with the work, Bartlett would advance the money required. The language of this clause of the agreement is as follows:

It is therefore agreed that the said Wm. Bartlett, shall advance the necessary money to pay for the said extra materials and the labor performed in restoring the said destroyed portion of said building, excepting the labor of said contractors, and the money as designated herein, as money deposited in the Pirst National Bank. All payments made shall be to the parties entitled thereto, both for materials and for labor upon itemized statements of the materials used in said fallen portion of said building and the labor performed thereon and upon payment thereof, said itemized statement shall be receipted by the parties furnishing said materials and [263]*263doing said work. All materials shall be furnished at cost and all labor shall be done at current rates, in Estlierville. of the wages for the respective kinds of work performed. However, the said Wm. Hitaffer and Carl Prouty shall receive no pay or compensation for their personal services under the terms of the original contract and until all other labor and materials have been paid for, nor until the question of the liability for damage occasioned by the collapse of said building has been determined. It is also agreed by the respective parties hereto that the said Wm. Bartlett may at his option use the certain $500 deposited by the said Wm. Hitaffer and Carl Prouty in the Eirst National Bank of Estherville, Iowa, as collateral bonds, in paying on said materials and labor herein referred to and stated, and the said Hitaffer and Prouty hereby authorize the said Eirst National Bank to turn over and pay to said Bartlett upon his request and showing said contract and receipting for the same the said $500. Said Bartlett shall keep a full account of the disposition of the said $500 and all parts thereof and report the same to said Hitaffer and Prouty.

This contract bears date August 28, 1902. On August 22, 1902, the plaintiff, who it would seem had already furnished the contractors other material not now in controversy, wrote to Bar-tlett asking him what position he had taken with reference to rebuilding and in what position it was likely to place Hitaffer and Prouty with reference to material furnished.” On August 27, 1902, Bartlett replied to this inquiry, saying:

I expect the building to go forward to completion, and do not see that it .will make any difference with regard to material furnished by you and placed in my building provided said material is furnished promptly as needed. I think they have written you with regard to cast iron columns. If you have not already advised them please do so at once, and state how soon we can depend upon getting them. I think they named 12xl6-inch column. This will be larger than needed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hay v. Hassett
174 Iowa 601 (Supreme Court of Iowa, 1916)
Noonan v. Stein
56 Colo. 64 (Supreme Court of Colorado, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
108 N.W. 308, 131 Iowa 259, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-e-shorthill-co-v-bartlett-iowa-1906.