Nomellini Construction Co. v. Harris

272 Cal. App. 2d 352, 77 Cal. Rptr. 361, 1969 Cal. App. LEXIS 2283
CourtCalifornia Court of Appeal
DecidedApril 28, 1969
DocketCiv. 1034
StatusPublished
Cited by9 cases

This text of 272 Cal. App. 2d 352 (Nomellini Construction Co. v. Harris) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nomellini Construction Co. v. Harris, 272 Cal. App. 2d 352, 77 Cal. Rptr. 361, 1969 Cal. App. LEXIS 2283 (Cal. Ct. App. 1969).

Opinion

CONLEY, P. J.

Nomellini Construction Co., hereafter called Nomellini, plaintiff and respondent herein, was the successful bidder for the construction of a public housing project in San Joaquin County designated CAL 24-6. It entered into a subcontract with the defendant, cross-complainant and cross-defendant Paul C. Harris, doing business as Harris Pence Co., shortened to Harris in this opinion, to supply and install the fence work and the clothes line supports for Conway Homes Annex, the public housing project. Harris did not comply with the terms of the subcontract; he failed to furnish and install a part of the initial fence work and the clothes line supports contracted for within the time required.

This action was later begun by Nomellini to recover damages caused by the default of the subcontractor, and it was claimed by the plaintiff and proven, in conformity with the findings of fact and conclusions of law, that Nomellini was damaged by the necessity of getting additional material and labor to install and complete the work involved in the total sum of $11,712.16, that being the amount necessary to expend in excess of the subcontract price agreed upon by Nomellini *356 and Harris. In Ms answer, Harris admitted the execution of the subcontract and further alleged in a cross-complaint that the cross-defendant, Hurricane Steel Industries, Inc., named Hurricane herein, whose manufacturing plant is near Houston, Texas, was given an order by him in the form of a list of materials which specifically recited: “Material to Meet Federal Specifications, ’ ’ that the cross-defendant undertook to supply such ordered materials, but that the steel parts so shipped were rejected on several successive occasions by the government inspector, resulting in a temporary stop order, and that, solely as a result of the breach by Hurricane of its contract, Harris was rendered unable to comply with the terms of his contract with Nomellini; Harris prayed that if a judgment were granted to Nomellini as against him he should in turn recover the same amount of damages from Hurricane, because the damages which he had caused Nomellini were due entirely to the breach by Hurricane of its contract with Harris. Hurricane in turn filed a cross-complaint against Harris on the theory of an account stated for $12,475, together with interest and costs, and a counterclaim against Harris in the sum of $1,500 as the result of expenses allegedly incurred by it in helping Harris to comply with its contract.

Section 442 of the Code of Civil Procedure reads as follows : “Whenever the defendant seeks affirmative relief against any person, whether or not a party to the original action, relating to or depending upon the contract, transaction, matter, happening or accident upon which the action is brought or affecting the property to which the action relates, he may, in addition to his answer, file at the same time, or by permission of the court subsequently, a cross-complaint. The cross-complaint must be served upon the parties affected thereby, and such parties may demur or answer thereto, or file a notice of motion to strike the whole or any part thereof, as to the original complaint. If any of the parties affected by the cross-complaint have not appeared in the action, a summons upon the cross-complaint must be issued and served upon them in the same manner as upon the commencement of an original action.” Harris thus took advantage of the right granted him by the quoted section of the Code of Civil Procedure and alleged in effect that if a judgment should be granted against him it should also go against Hurricane, because the latter party was, in the final analysis, the sole cause of his own default on the subcontract with Nomellini. The code provision should be interpreted liberally. (Nelson v. Superior *357 Court, 97 Cal.App.2d 78 [217 P.2d 119]; County of Humboldt v. Kay, 57 Cal.App.2d 115 [134 P.2d 501].)

As pointed out in Bracey v. Gray, 65 Cal.App.2d 282 [150 P.2d 564], the purpose of this code section is to enable a final and binding judgment upon all the matters in dispute between the parties; and in Millar v. Millar, 51 Cal.App. 718, 722 [197 P. 811], it is stated that the purpose of allowing a cross-complaint under the circumstances outlined in the code section is to avoid a multiplicity of suits; the situation set up by the section “involves a consolidation of two independent actions, arising out of or related, to the same transaction.” In a suit such as the present one in which a cross-complaint is filed by a defendant bringing into the litigation a third party, it must be apparent that the findings and judgment, in the absence of some counter-consideration cover the entire field of the pleadings, that is to say in the instant ease not only the elements contained in the answer to the complaint by Harris but the elements apposite to the contractual and financial relationship of Harris and Hurricane.

After a lengthy trial, the court filed its memorandum of decision which decided the issues tendered by the complaint and the cross-complaints, including the statement that “Nomellini Construction Company is entitled to a judgment against Paul 0. Harris as prayed for in the sum of $11,712.16, ’ ’ and further:

“(1) That defendant, Hurricane Steel Industries, agreed to furnish Harris supplies in accordance with and under the terms as set forth in paragraph 3 of Harris ’ cross-complaint.
“ (2) The Court furthermore finds that the allegations contained in paragraphs 4, 5, 6 and 7 are sustained by the preponderance of the evidence.
“(3) The Court furthermore finds that by virtue of the breach of express warranty by Hurricane to Harris, that Harris sustained the loss equal to the damages claimed by Nomellini Construction Company, to-wit: $11,712.16.
“With reference to the counter-claim filed by Hurricane, the Court finds in favor of Harris Pence Company and against Hurricane.
“With reference to the cross-complaint filed for a money judgment by Hurricane against Harris based upon an account stated, the Court finds in favor of defendant Harris and against Hurricane Steel Industries. The reason for this latter finding is occasioned by the fact that there was no evidence of *358 an account stated as between Harris and Hurricane but, to the contrary, Harris denied owing Hurricane any sum whatsoever based on an account stated. There was evidence as to an open book account but I am sure counsel will recall that the representative of Hurricane could not testify as to the authenticity of any of the entries on the open book account.
“It is, therefore, the judgment of this Court that Nomellini Construction Company recover a judgment against Harris and Hurricane Steel Industries in the sum of $11,712.16. ”

No appeal was taken by Harris.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson Private Investors v. Colak CA2/2
California Court of Appeal, 2013
Maxfour Engineers & Architects, LLC v. ARB, Inc.
233 F.R.D. 602 (D. Colorado, 2006)
In Re Marriage of Plescia
59 Cal. App. 4th 252 (California Court of Appeal, 1997)
Richardson Associates v. Lincoln-Devore, Inc.
806 P.2d 790 (Wyoming Supreme Court, 1991)
Considine Co. v. Shadle, Hunt & Hagar
187 Cal. App. 3d 760 (California Court of Appeal, 1986)
Valley Circle Estates v. VTN Consolidated, Inc.
659 P.2d 1160 (California Supreme Court, 1983)
El Ranco, Inc. v. NEW YORK MEAT AND PROVISION CO.
493 P.2d 1318 (Nevada Supreme Court, 1972)
Shepherd v. Miles & Sons, Inc.
10 Cal. App. 3d 7 (California Court of Appeal, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
272 Cal. App. 2d 352, 77 Cal. Rptr. 361, 1969 Cal. App. LEXIS 2283, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nomellini-construction-co-v-harris-calctapp-1969.