Noland Company, Incorporated, and Third-Party and Cross-Appellant v. Graver Tank & Manufacturing Company, Third-Party and Cross-Appellee

301 F.2d 43, 5 Fed. R. Serv. 2d 140, 1962 U.S. App. LEXIS 5643
CourtCourt of Appeals for the Third Circuit
DecidedMarch 19, 1962
Docket8434_1
StatusPublished
Cited by41 cases

This text of 301 F.2d 43 (Noland Company, Incorporated, and Third-Party and Cross-Appellant v. Graver Tank & Manufacturing Company, Third-Party and Cross-Appellee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Noland Company, Incorporated, and Third-Party and Cross-Appellant v. Graver Tank & Manufacturing Company, Third-Party and Cross-Appellee, 301 F.2d 43, 5 Fed. R. Serv. 2d 140, 1962 U.S. App. LEXIS 5643 (3d Cir. 1962).

Opinion

BOREMAN, Circuit Judge.

Ruscon Construction Company, a South Carolina corporation, brought this action for damages for breach of contract against the Noland Company, Inc., a Virginia corporation, which in turn filed a third-party complaint against Graver Tank & Manufacturing Company, a Delaware corporation. Trial was had before the court without a jury. It was ordered that Ruscon was entitled to recover $13,-065 from Noland, and Noland was awarded the same amount from the third-party defendant, Graver. Both Noland and Graver have appealed from the order of the District Court, each challenging a different portion thereof.

Early in 1958 the United States Government advertised for bids on the construction cost of two Capehart Housing projects — one at Camp Lejeune, Cherry *45 Point, North Carolina, and the other at the Charleston, South Carolina, Air Force Base. Included in both projects were elevated steel tanks for water storage— a 300,000 gallon tank at Cherry Point and a 500,000 gallon painted tank with cathodic protection and obstruction lights for the Charleston Air Force Base. Ruscon prepared a bid for the overall Charleston project and submitted it before the bid closing time, 2 P.M. on March 27, 1958. On the day before Ruscon submitted its bid, one Thomas, manager of the Charleston branch of the No-land Company, operating a plumbing supply business throughout the southeastern United States, learned of the water tank requirement for the Charleston contract and, at the request of one of No-land’s regular customers (who was preparing a subcontract bid to submit to Ruscon), tried to obtain a price on the water tank in question. Noland’s regular supplier of water tanks could not furnish the large 500,000 gallon model but suggested that Thomas contact Graver’s district sales office in Atlanta, Georgia. Following this suggestion, Thomas called Graver’s office on the afternoon of March 26,1958, and talked to Best, Graver’s District Sales Engineer. According to Thomas, he requested a bid price on the 500,000 gallon tank for the Charleston project. Best advised Thomas that he did not know whether his company (Graver) had prepared an estimate on that project, but that he would check with Graver’s Edge Moor, Delaware, office (which prepared estimates from Government-provided specifications) and call Thomas back. About 11 A.M. on March 27, three hours before bids on the general contract were to be opened, Best called Thomas from Atlanta and told him the tank (alleged by Thomas to be the 500,000 gallon one) could be supplied for $58,030. 1 This information was passed on by Thomas to Ruscon 2 and thirty minutes later a Mr. West from Ruscon, considering the quoted price low, called Thomas back, requesting a verification of the $58,030 price and assurance that it was based upon contract specifications. Thomas also thought that perhaps the bid was low but verified it on the information he then had and immediately placed a call for Best in Atlanta. Best was away from his office at that time and consequently there was no confirmation to Noland of the bid price prior to the deadline for submitting the general contract bid. Later in the afternoon of March 27, according to Thomas’ testimony, Best was reached by telephone and confirmed the quoted price. Best testified that he could recall only two telephone conversations with Thomas on March 26-27, 1958, one on the afternoon of March 26 and the other on the morning of March 27; that in both conversations the project for which the water tank was to be used was referred to as the “Capehart Housing job”; that it was his understanding from the first telephone conversation with Thomas that the tank for the Camp Lejeune project was the subject of their discussion.

Ruscon used the $58,030 price in calculating and submitting its total bid of $527,479, the lowest one received by the Government for the Charleston project; the next lowest bid was $560,707. Other prices obtained by Ruscon for the specified 500,000 gallon water tank prior to the bid opening were $76,500 and $84,-300.

As soon as Ruscon was notified that it was the low bidder and that the contract would be awarded to it, Noland was advised that its bid of $58,030 on the tank *46 would be accepted. On March 29, Noland received from Graver a written confirmation of its bid price but then noted that the specifications thereon were for a 300,000 gallon tank to be supplied for Camp Lejeune and did not include certain accessories required for the Charleston project. When Graver discovered the confusion, it promptly advised Noland that it could not furnish the 500,000 gallon tank for $58,030, that being the price quoted for the smaller tank. Noland, in turn, then notified Ruscon that the tank could not be furnished at the price originally quoted. Formal letters of intent to comply with the bid price were submitted by Ruscon to Noland and by No-land to Graver, but both letters were rejected and each was returned to its sender.

Ruscon performed its over-all contract with the Government, furnishing a 500,-000 gallon water tank at a cost of $71,-095. Thereafter the present action was brought against Noland for $13,065, the difference between the original bid price and Ruscon’s actual cost of supplying the tank. Noland, in making Graver a third-party defendant, sought to recover from Graver any amount it (Noland) might have to pay Ruscon plus $4000, the amount of profit Noland allegedly would have made on the completed transaction as originally contemplated. The District Court made no determination with respect to the added claim of profit by No-land, and it is on this point that Noland has appealed. Graver, on the other hand, contends (1) there was no contract between Graver and Noland because of lack of mutuality but (2) if there was a contract the South Carolina Statute of Frauds 3 prevents the enforcement thereof because the contract was not in writing. Thus, there are three issues presented on this appeal: (1) Whether there is sufficient evidence in the record to sustain the District Court’s determination that there was mutuality between Graver and Noland; (2) whether the District Judge properly construed and applied the South Carolina Statute of Frauds; and (3) whether, under Rule 14, Federal Rules of Civil Procedure, 28 U.S.C.A., a third-party plaintiff may recover from the third-party defendant an amount greater than that recovered by the original plaintiff from the third-party plaintiff (the original defendant).

—I—

It is axiomatic that an essential element of a valid contract is mutuality between the contracting parties. Whether there was an agreement between Noland and Graver that the latter was to supply a 500,000 gallon painted water tank complete with cathodic protection and obstruction lights for $58,030 is simply a question of fact which was determined affirmatively by the District Judge as the trier of fact. Though the evidence on this point is conflicting, there is testimony which, if believed, sustains the finding of the District Court. We cannot say that such finding is clearly erroneous.

Graver argues that the undisputed facts do not support a finding of mutual understanding and a meeting of minds between Noland and Graver.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Turner v. Harmon
D. Maryland, 2021
Deutsche Bank National Trust Co. v. Tyner
233 F.R.D. 460 (D. South Carolina, 2006)
Dishong v. Peabody Corp.
219 F.R.D. 382 (E.D. Virginia, 2003)
Taylor v. Cummins Atlantic, Inc.
852 F. Supp. 1279 (D. South Carolina, 1994)
Kline Iron & Steel Co. v. Gray Communications Consultants, Inc.
715 F. Supp. 135 (D. South Carolina, 1989)
United States v. City of Twin Falls
806 F.2d 862 (Ninth Circuit, 1986)
Atlas, Ltd. v. Kingman Warehouse Co.
357 N.W.2d 584 (Supreme Court of Iowa, 1984)
Nationwide Resources Corp. v. Massabni
658 P.2d 210 (Court of Appeals of Arizona, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
301 F.2d 43, 5 Fed. R. Serv. 2d 140, 1962 U.S. App. LEXIS 5643, Counsel Stack Legal Research, https://law.counselstack.com/opinion/noland-company-incorporated-and-third-party-and-cross-appellant-v-graver-ca3-1962.