Nolan Contracting, Inc. v. Regional Transit Authority

651 F. Supp. 23, 1986 U.S. Dist. LEXIS 25672
CourtDistrict Court, E.D. Louisiana
DecidedMay 9, 1986
Docket86-478
StatusPublished
Cited by4 cases

This text of 651 F. Supp. 23 (Nolan Contracting, Inc. v. Regional Transit Authority) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nolan Contracting, Inc. v. Regional Transit Authority, 651 F. Supp. 23, 1986 U.S. Dist. LEXIS 25672 (E.D. La. 1986).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

PATRICK E. CARR, District Judge.

Plaintiff, Nolan Contracting, Inc. (“Nolan”), is a dissappointed bidder challenging the validity of the affirmative action program adopted by the defendant, Regional Transit Authority (“RTA”). Nolan alleges that the RTA’s program violated its rights to due process and equal protection under the Fifth and Fourteenth Amendments, and its statutory rights under the Civil Rights Act, 42 U.S.C. §§ 1981, 1983, and the Louisiana Public Bid Law, La.R.S. 38:2212 et seq.

This matter came on for trial before the Court on March 31, 1986. At that time the parties submitted a joint stipulation of fact. The parties also stipulated to the admissability of all documentary evidence. No live or deposition testimony was offered. Based upon the foregoing, the Court took the matter under submission and allowed the parties time to submit post-trial memoranda.

Upon review of the facts as stipulated, the documents and pleadings in evidence, and the applicable law, the Court hereby renders its findings of fact and conclusions of law in accordance with Rule 52 of the Federal Rules of Civil Procedure.

The Court has jurisdiction pursuant to 28 U.S.C. 1331, with pendent jurisdiction over the state claims. Venue is proper.

Nolan is a licensed Louisiana resident general contractor and subcontractor that has participated in a substantial number of municipal and private contracts throughout the State of Louisiana, including the City of New Orleans. The RTA is a political subdivision of the State of Louisiana, created pursuant to the Regional Transit Authority Act of 1979, La.R.S. 48:1651, et seq.

On October 7, 1985, the RTA issued Invitation for Bids No. 84-066 for construction of the Algiers Park & Ride Project. (Exhibits P-13 and D-17). Funding for the project was received from the Urban Mass Transit Administration (“UMTA”), which is an element of the United States Department of Transportation.

In 1979, the UMTA had approved a grant to construct the Algiers facility. The grant was between the City of New Orleans and the UMTA. The City then donated the land and the land value was used to match federal funds. Pursuant to a transit agreement between the City and the RTA, the RTA agreed to assume this property from the City and the grant for the project was transferred to the RTA’s name. The grant and the conditions thereto became a part of the RTA’s contractual obligation. (See Exhibit D-3.)

The Department of Transportation has had a longstanding policy of “supporting the fullest possible participation of firms owned and controlled by minorities and women” in transportation programs. 49 C.F.R. §§ 23.1(a), 23.43(a)(1). To that end, *25 the Department has enacted regulations requiring recipients of federal funds to implement Minority Business Enterprise (“MBE”) programs. 49 C.F.R. 23.41, et seq. Recipients of funds must submit programs for approval. Upon approval, the programs are to be immediately implemented. Failure to carry out the requirements of the program carries penalties, including the loss of the federal funding. 49 C.F.R. §§ 23.43(c), 23.45(h)(3), 23.68(e)(2).

The federal regulations require the contract recipients to establish overall goals for the use of disadvantaged businesses. Such goals are to be based upon the known availability of MBE’s and upon past experience, among other factors. Agencies accepting UMTA funding must set percentage goals for the dollar value of work to be performed by MBE’s on an overall funding basis and for each specific contract. 49 C.F.R. §§ 23.45(g), et seq. Unless the Secretary of Transportation determines otherwise, recipients are required to “set and meet overall disadvantaged business goals of at least ten percent.” 49 C.F.R. 23.61.

The federal regulations also provide selection criteria to ensure that contracts are awarded to competitors meeting the MBE goals. Initially, these regulations established a conclusive presumption rule as follows:

If any competitor offering a reasonable price meets the MBE contract goal, the recipient shall presume conclusively that all competitors that failed to meet the goal have failed to exert sufficient reasonable efforts and consequently are ineligible to be awarded the contract.

49 C.F.R. 23.45(i) (1980).

This conclusive presumption rule was eliminated in 1981. The current regulations provide instead for a showing of good faith efforts on the part of the competitor to meet the MBE goals. The regulations also provide:

The recipient may prescribe other requirements of equal or greater effectiveness in lieu of good faith efforts.

49 C.F.R. 23.45(h)(2)(i) (1985).

The UMTA has specifically authorized recipients of its funds to continue use of the conclusive presumption rule as an alternative “of equal or greater effectiveness in lieu of good faith efforts.” (Exhibit D-7 at page 1-16.)

The RTA formulated and submitted an MBE program to the UMTA. It was approved as submitted in 1982 and has been readopted in the ensuing fiscal years. (Exhibits D-l and D-5.) The RTA’s MBE program provides for the setting of percentage goals for the dollar value of work to be awarded to MBE’s for each contract let by the RTA. The MBE contract goal set by the RTA for the Algier’s Park & Ride Project was 30%.

The RTA’s program, approved by the UMTA, incorporates the conclusive presumption rule. (Exhibits D-l and P-13 and D-17 at attachment II page 7 of 30.) The 30% MBE goal became a substantive part of the bid specifications for the Algiers Park and Ride Project, id. See also, 45 Fed.Reg. 45286 (July 3, 1980).

On October 22, 1985, the RTA received bids for the Algier’s project from four firms, one of which was Nolan. (Exhibits D-18 through D-21.) Nolan’s bid was the lowest, but failed to meet the 30% MBE goal. Two of the bids, although not the lowest, were found to be reasonably priced and did in fact meet the MBE goal of 30%. The two remaining bids, one of which was Nolan’s, were declared nonresponsive by the RTA for failure to meet the MBE goal, in accordance with the program’s conclusive presumption rule.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Worldwide Parking, Inc. v. New Orleans City
123 F. App'x 606 (Fifth Circuit, 2005)
Feary v. Regional Transit Authority
685 F. Supp. 137 (E.D. Louisiana, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
651 F. Supp. 23, 1986 U.S. Dist. LEXIS 25672, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nolan-contracting-inc-v-regional-transit-authority-laed-1986.