Nolan Bros., Partners ex rel. Nolan Bros., Inc. v. United States

98 Ct. Cl. 41, 1942 U.S. Ct. Cl. LEXIS 37, 1942 WL 4449
CourtUnited States Court of Claims
DecidedOctober 5, 1942
DocketNo. 43982
StatusPublished
Cited by5 cases

This text of 98 Ct. Cl. 41 (Nolan Bros., Partners ex rel. Nolan Bros., Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nolan Bros., Partners ex rel. Nolan Bros., Inc. v. United States, 98 Ct. Cl. 41, 1942 U.S. Ct. Cl. LEXIS 37, 1942 WL 4449 (cc 1942).

Opinion

Jones, Judge,

delivered the opinion of the court:

This is one of several suits that were brought by the different contractors for alleged excess costs incurred in carrying out their respective contracts for the construction of locks and dams for the improvement of navigation on the Mississippi River and its tributaries. .

The act conferring general jurisdiction ,on the Court of Claims was broadened for these particular cases by a special jurisdictional act approved July 23, 1937, which is set out in full in finding number 2 of the Special Findings of Fact and will not be repeated here:: ■

The bid of Nolan Bros., in response to public advertisement and invitation for bids to- furnish all plant, labor, and materials and perform all work required for the construction of Lock No. 7 near La Crosse, Wisconsin, was accepted and contract was executed November 16,1933.

The original contract price .was approximately $1,319,989. The work was to be completed within 365 calendar days after receipt of notice to proceed, The contract provided for liquidated damages in the sum of $250 per day for each day’s delay beyond the date fixed for completion until the work should be placed in safe and practical operating condition, and thereafter $25 per day as liquidated damages for each additional day’s delay in final .completion. Certain change orders were issued and the contract price and time of completion adjusted accordingly. The work was completed within the time specified and was accepted as satisfactory.

The contract covered one of-a. series of projects generally known as.P. W. A. projects, authorized by the Federal Emergency Administration of Public Works, the latter being organized under the provisions of' the National Industrial Recovery Act of June 16,1933 (48 Stat. 195).

[79]*79Formal notice to proceed was given on February 5, 1934, but plaintiff had previously been informed that it was the low bidder and would probably be awarded the contract, and with the permission of the officials in charge did some preliminary work prior to that date.

Prior to making its bid plaintiff received from the defendant, together with bidding schedule, form of contract, and specifications, Bulletin No. 51 of the Federal Emergency Administration of Public Works, dated September 7, 1933, which contained the following language:

Sec. 10. Employers may use organized or unorganized labor. Unorganized labor shall be .obtained from local employment agencies designated by the United States Employment Service, * * *. See Form P. W. A. 51, Article 19 (b) * * *

It had also received District Engineer Form No. 1 P. W. A., containing Circular Letter (Finance No. 150) dated September 13,1933, which contained the following provision:

* * * Contractors with existing organizations may take an existing skeleton organization of .keymen, including foremen to new work under National industrial [Recovery Act, but the remainder of the force for the work must meet the requirements of Article 19. (b) of Government Form P. W. A. 51 and of Section 10 of P. W. A. Bulletin 51.

Plaintiff brought to the project from its own organization certain administrative officials and employees, as well as certain keymen to be used as foremen. Labor generally was to be obtained through the National Reemployment Service from La Crosse County, Wisconsin, and Winona County, Minnesota, and if sufficient qualified labor was not thus obtainable, then from these states at large and, if necessary, from other states.

Plaintiff alleges several grounds of complaint as a basis for its first claim. It says that defendant failed to furnish lists of qualified woi'kmen in accordance with the terms of the contract and compelled it to use men who were not experienced or skilled in heavy construction work; that it repeatedly refused to permit plaintiff to bring in available men whom it knew to be qualified and experienced in this type of [80]*80work; that it made restrictive rules and regulations not contemplated by 'and not authorized by the contract and misinterpreted and misapplied other regulations, and by the issuance of such unreasonable regulations and the misinterpretation and misapplication of others greatly increased the cost of construction. Plaintiff’s first claim is for excess costs, damages, and expenses amounting to $280,927.89. Its second claim is for $78,940.29, making a total of $859,868.18, for which plaintiff sues.

Defendant answers that it was not obligated by the contract to furnish qualified labor, but was only required to furnish groups of men from which plaintiff could make its own selection; that the furnishing of lists was not insisted upon by the plaintiff; that the restrictive rules and regulations which were issued were reasonable; that the plaintiff was permitted to bring in such essential keymen, administrative officers, and foremen as the contract contemplated, and that -the plaintiff, therefore, is not entitled to recover on its first claim.

The general method used by the National Reemployment Service was to accept applications, have applicants make a statement as to their experience, make out a card and send the applicants over with the card, thus permitting plaintiff to make its own selection from the group furnished.

The area in which the work was done was largely an agricultural section, with one or two small cities that had some industrial activity.

In response to plaintiff’s call for labor, the La Crosse Reemployment Office sent groups of men to the project. Some of them were experienced and able to perform the work required; many others were neither qualified nor physically able to do the required work. Many of the workers were inexperienced in the handling of tools and wholly without experience in heavy construction work. Many had no tools and did not know how to handle or care for them. Some had only tennis shoes, which were wholly unsuited to heavy construction work. Consequently there were numerous foot injuries. Some of the men sent out as skilled workers were not trained in handling cranes, overturning six of them, within the first six months, seriously damaging them. Many [81]*81of the carpenters were inexperienced in reading the drawings or building forms and recesses and inserts for this type of work, thus causing loss of time and excess costs. At one time plaintiff asked permission to employ an experienced riveting crew which had formerly worked for him and which was then available. This permission was refused by the La Crosse office on the ground that riveters were available through the Eeemployment Service. Plaintiff took the crew sent out by the La Crosse office, but so much of the work was rejected by the Government inspector that the men were dropped at the end of the first day. Plaintiff again asked ■permission to use the experienced crew, but was again refused, and after a two days’ delay the La Crosse office sent down another crew from Milwaukee. Their work was also unsatisfactory and they were let go after .6 hours’ work. A large part of the work done by these men was rejected by the Government inspector and had to be done over. When plaintiff was laying derrick stone the men tipped a northwest crane boom backward twice in one day.

There was considerable unemployment in this section and among the men sent down were some clerks, a cripple with a wooden leg, a professor, a hairdresser, and a conductor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Central Eureka Mining Co.
357 U.S. 155 (Supreme Court, 1958)
Grant v. United States
92 F. Supp. 369 (E.D. North Carolina, 1950)
Addison Miller, Inc. v. United States
70 F. Supp. 893 (Court of Claims, 1947)
Frazier-Davis Construction Co. v. United States
100 Ct. Cl. 120 (Court of Claims, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
98 Ct. Cl. 41, 1942 U.S. Ct. Cl. LEXIS 37, 1942 WL 4449, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nolan-bros-partners-ex-rel-nolan-bros-inc-v-united-states-cc-1942.