Nofelco Realty Corp. v. United States

521 F. Supp. 458, 11 Envtl. L. Rep. (Envtl. Law Inst.) 21090, 1981 U.S. Dist. LEXIS 18537
CourtDistrict Court, S.D. New York
DecidedSeptember 11, 1981
Docket81 Civ. 0052 (GLG)
StatusPublished
Cited by10 cases

This text of 521 F. Supp. 458 (Nofelco Realty Corp. v. United States) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nofelco Realty Corp. v. United States, 521 F. Supp. 458, 11 Envtl. L. Rep. (Envtl. Law Inst.) 21090, 1981 U.S. Dist. LEXIS 18537 (S.D.N.Y. 1981).

Opinion

MEMORANDUM DECISION

GOETTEL, District Judge.

This action was brought by the plaintiff, Nofelco Realty Corp. (“Nofelco”), seeking judicial review of the action of the Secretary of the Army, through the Army Corps of Engineers (“Corps”), in denying the plaintiff’s application for a permit to construct a bulkhead along the shoreline of its property. The action initially came before this Court on a motion for a preliminary injunction — a rather unusual posture for such a case.

*459 Nofelco owns a piece of tidal property, 100 feet wide and 84 feet deep, in Queens, adjacent to Shellbank Basin, which is a waterway flowing into Jamaica Bay. When Nofelco originally bought the property in 1959, only a strip 10 feet deep was dry land. Nofelco gradually filled in the submerged area, and now the property is dry land to a depth of approximately 72 feet, with another 12 feet of embankment area. The northern 30 feet of the shoreline are occupied by a building owned by Nofelco extending out over the water on stilts. 1

In August 1977, Nofelco applied to the Corps for a permit to build a sloping riprap bulkhead at the shore edge and to fill in the property landward of the bulkhead and also to erect vertical steel sheet pile bulkheading to secure the side boundary of the property at one corner of the shore edge. The Corps granted the permit in April 1978.

In October 1978, Nofelco applied for permission to run the steel sheet bulkhead, which would rise approximately 6 feet above the mean high water level, along the remaining shore edge of the property. The initial review of Nofelco’s application was by the District Engineer of the Corps, who recommended in July 1979 that a permit be issued, despite the objections of the National Marine Fisheries Service and the Fish and Wildlife Service. The Division Engineer, superior to the District Engineer, rejected the recommendation and directed the District Engineer to deny the permit, which he did in May 1980, on the ground that the proposed bulkhead “would increase encroachment upon this heavily stressed waterway for an apparently non-water dependent activity” and was “not in the public interest.” While rejecting Nofelco’s proposal, the notification letter indicated that the Corps would be willing to issue a permit for a similar bulkhead 8.5 feet landward of the location proposed by Nofelco. 2

Nofelco then retained an environmental consultant, who wrote to the Corps on behalf/of the plaintiff. Nofelco subsequently requested an adjudicatory hearing, which was denied on the ground that the denial of the permit was the final administrative action, from which no administrative appeal was permitted. Consequently, Nofelco filed the instant action, seeking review of the administrative action and seeking a preliminary injunction against any action by the Corps to remove the parts of the steel bulkhead that were already constructed.

Nofelco asked for injunctive relief because the letter it received from the Corps had referred to allegedly unauthorized construction at the shore edge of its property, leading Nofelco to fear the institution of Corps action to require the removal of that construction. This Court denied the motion for a preliminary injunction in January 1981 on the ground that there was no immediate threat of irreparable harm, since no steps had yet been taken to require removal of the allegedly unauthorized construction. There has still been no enforcement action brought against Nofelco; consequently, there is still no need for a preliminary injunction, and the plaintiff’s renewed application for it is denied.

Nofelco has also asked for a trial de novo on the merits, on the ground that the procedures by which the Corps denied Nofelco’s October 1978 application violated due process and the Administrative Procedure Act (“APA”), 5 U.S.C. §§ 551 et seq. For the reasons set forth below, this Court has determined that the plaintiff is not entitled to a trial de novo, but rather that the final administrative action taken by the Corps should be reviewed on the basis of the administrative record.

Two statutes govern the permit program under which the plaintiff made its application — section 10 of the Rivers and Harbors Act of 1899,33 U.S.C. § 403, and section 404 of the Federal Water Pollution Control Act, *460 33 U.S.C. § 1344 (as added in 1972 and amended in 1977). Issuing permits to build such structures as bulkheads in navigable waters of the United States has long been the responsibility of the Secretary of the Army and the Chief of Engineers. See 33 U.S.C. § 403; 33 C.F.R. § 320.2(b) (1980). The regulations governing the issuance of such permits are found in 33 C.F.R. §§ 325.1 et seq. (1980) and provide for, inter alia, public notice of the permit application, receipt of written comments from interested parties, an opportunity for the applicant to rebut all substantive adverse comments, a public hearing if the district engineer determines that one is needed or if one is requested, 3 preparation of findings of fact by the district engineer, and written notification to the applicant of a denial and the reasons for it. The responsibility of issuing permits for dredged or fill material under section 1344 was also given to the Secretary of the Army and the Chief of Engineers. See 33 U.S.C. § 1344(a), (d); 33 C.F.R. § 320.2(g) (1980). The regulations governing the issuance of those permits are found in 33 C.F.R. §§ 325.1 et seq. (1980) and are essentially the same as those for section 403 permits. See 40 C.F.R. § 124.1(a) (1980).

The plaintiff has not alleged that the defendants failed to follow the Corps procedures outlined above. Instead, the plaintiff argues that those procedures are inadequate under the standards of the APA and under the due process standard. The plaintiff complains particularly about the failure of the Corps to conduct a formal adjudicatory hearing, as provided for in the APA for adjudications “required by statute to be determined on the record after opportunity for an agency hearing.” 5 U.S.C. § 554(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
521 F. Supp. 458, 11 Envtl. L. Rep. (Envtl. Law Inst.) 21090, 1981 U.S. Dist. LEXIS 18537, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nofelco-realty-corp-v-united-states-nysd-1981.