Noe Garza and Noe Garza Engineers, Inc. v. Joe Carmona and Celina Carmona

390 S.W.3d 391, 2012 WL 1134014, 2012 Tex. App. LEXIS 2714
CourtCourt of Appeals of Texas
DecidedApril 5, 2012
Docket13-11-00077-CV
StatusPublished
Cited by16 cases

This text of 390 S.W.3d 391 (Noe Garza and Noe Garza Engineers, Inc. v. Joe Carmona and Celina Carmona) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Noe Garza and Noe Garza Engineers, Inc. v. Joe Carmona and Celina Carmona, 390 S.W.3d 391, 2012 WL 1134014, 2012 Tex. App. LEXIS 2714 (Tex. Ct. App. 2012).

Opinion

OPINION

Opinion by Justice PERKES.

Appellants, Noe Garza and Noe Garza Engineering, Inc. (collectively “Garza Engineering”), appeal from the denial of their motion to dismiss the lawsuit that appel-lees, Joe and Celina Carmona (collectively “Carmonas”), filed against them. See Tex. Civ. Prac. & Rem.Code Ann. § 150.002(f) (West 2011) (authorizing immediate interlocutory appeal from an order denying a motion to dismiss under section 150.002). By three issues on appeal, Garza Engineering argues the certificate of merit the Carmonas filed with their lawsuit did not satisfy the requirements of Texas Civil Practice and Remedies Code section 150.002 because the affidavit did not: (1) address each theory of recovery for which damages were sought; (2) provide the factual basis for each theory of recovery; or (3) identify any applicable standard of care which Garza Engineering allegedly breached. See id. § 150.002(b). We reverse and remand.

I. FACTUAL AND PROCEDURAL BACKGROUND

The pleadings show the following background facts. The Carmonas owned real property in San Benito, Texas, which they sought to develop into a residential subdivision. The Carmonas hired Garza Engineering to design and supervise the development. They hired Modesto Hernandez as the construction contractor to perform construction work under Garza Engineering’s supervision. 1 The Carmonas filed this lawsuit, alleging deficiencies in Garza Engineering and Hernandez’s performance on the project.

In their original petition, the Carmonas alleged five theories of recovery against Garza Engineering: (1) negligence; (2) violations of the Texas Deceptive Trade Practices Act 2 (“DTPA”); (3) common-law fraud; (4) negligent misrepresentation; and (5) breach of contract. Regarding their negligence theory of recovery, the Carmonas pleaded Garza Engineering did not properly design the subdivision, failed to make proper design plans, and failed to adequately supervise construction and correct construction defects as they arose. The Carmonas stressed in their petition that “the most serious failure of Noe Garza Engineering, Inc. was in its neglect and failure to oversee and supervise construction.” The Carmonas pleaded that Garza Engineering negligently failed in their “watchdog role,” and as a result, Hernandez installed a water line to the subdivision that failed the city water district’s pressure test and failed to elevate the lots so that they would drain into the street as per the design plans and city requirements. The Carmonas pleaded that the latter presented a “major flooding hazard.”

Under the DTPA, the Carmonas generally pleaded, without application of facts, that Garza Engineering engaged in “an unconscionable action or course of action,” “caused confusion or misunderstanding as to the source, sponsorship, approval or certification of goods or services,” and breached implied warranties of merchantability, fitness for a particular purpose, and good and workmanlike performance. In a similarly broad fashion, the Carmonas generally pleaded their common-law fraud, *393 negligent misrepresentation, and breach-of-contract claims against Garza Engineering.

With their original petition, the Carmo-nas filed the affidavit of Michael Myers, a licensed professional engineer. The Car-monas state in their petition that “Myers identifies the areas where [Garza Engineering] were negligent in their duty to oversee the development of Carmona Subdivision.” They make no other reference to any other claim with respect to Myers’s affidavit. After setting forth his qualifications, Myers stated:

On February 4, 2010 I examined the subdivision plat construction documents conducted by Noe Garza Engineering, Inc. for Joe and Celina Carmona, for the property described as:
Carmona Subdivision, located off Shafer Road, between Oscar Williams and FM 509 in San Benito, Texas.
After reviewing the construction drawings and the other documents concerning the project provided by the Subdivision owner Joe Carmona, I discovered the following deficiencies from the reviewed documents.
1. The engineer provided no Contractual documents for the contractor and owner to sign to clarify the requirements for the contractor for the project. Specifically:
a. No agreement for Contractor and owner to sign
b. No formal proposal of scope of work
c. No specified duration for time of completion
d. No liquidated damages from failure to perform
e. No payment bond
f. No performance bond
g. No insurance requirements
h. No General or Special conditions to specify terms and conditions for executing the project
i. No Technical specifications to specify the specific details for the execution of the work by the contractor

2. The construction drawings for the subdivision omitted the following items:

a. No standard details for water line construction
b. No standard details for storm drainage construction
c. No detailed drainage plan for total subdivision drainage
d. No standard details for street construction
e. No details for the proposed street profile and compaction requirements
f. No Elevation Bench Mark information for contractor reference.

As engineers it is our professional responsibility and duty to protect the interests of our clients and the public in the development of civil works such as the above mentioned Subdivision Works. In failing to provide these crucial elements to the documentation of this project, Mr. Garza did not provide an acceptable design project plan for the owner, the City of San Benito and the Public. These deficiencies caused many extra delays and additional costs to the owner to bring additional resources to complete this project.

Garza Engineering moved to dismiss the Carmonas’ lawsuit against them, alleging Myers’s affidavit was insufficient to satisfy the certifieate-of-merit requirements found in Texas Civil Practice and Remedies Code section 150.002. See id. § 150.002. After a hearing, the trial court denied Garza Engineering’s motion to dismiss. This accelerated appeal followed.

*394 II. STANDARD OF REVIEW

We review a trial court’s denial of a motion to dismiss filed pursuant to Texas Civil Practice and Remedies Code section 150.002 for an abuse of discretion. WCM Group, Inc. v. Brown, 305 S.W.8d 222, 229 (Tex.App.-Corpus Christi 2009, pet. dism’d); Landreth v. Las Brisas Council of Co-Owners, Inc.,

Related

Jaster-Quintanilla & Assocs., Inc. v. Prouty
549 S.W.3d 183 (Court of Appeals of Texas, 2018)
Melden & Hunt, Inc. v. East Rio Hondo Water Supply Corporation
520 S.W.3d 887 (Texas Supreme Court, 2017)
Melden & Hunt, Inc. v. East Rio Hondo Water Supply Corp.
511 S.W.3d 743 (Court of Appeals of Texas, 2015)
Toby Paul Couchman and Pro-Surv v. Elizabeth Cardona
471 S.W.3d 20 (Court of Appeals of Texas, 2015)
Packard Engineering Associates v. Sally Group, L.L.C.
398 S.W.3d 389 (Court of Appeals of Texas, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
390 S.W.3d 391, 2012 WL 1134014, 2012 Tex. App. LEXIS 2714, Counsel Stack Legal Research, https://law.counselstack.com/opinion/noe-garza-and-noe-garza-engineers-inc-v-joe-carmona-and-celina-carmona-texapp-2012.