Noble Drilling (U.S.) LLC v. Eric Wheeler

CourtCourt of Appeals of Texas
DecidedJune 6, 2024
Docket14-22-00185-CV
StatusPublished

This text of Noble Drilling (U.S.) LLC v. Eric Wheeler (Noble Drilling (U.S.) LLC v. Eric Wheeler) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Noble Drilling (U.S.) LLC v. Eric Wheeler, (Tex. Ct. App. 2024).

Opinion

Reversed and Remanded and Memorandum Opinion filed June 6, 2024.

In The

Fourteenth Court of Appeals

NO. 14-22-00185-CV

NOBLE DRILLING (U.S.) LLC, Appellant

V.

ERIC WHEELER, Appellee

On Appeal from the 434th Judicial District Court Fort Bend County, Texas Trial Court Cause No. 21-DCV-287270

MEMORANDUM OPINION

Noble Drilling (U.S.), LLC brings this interlocutory appeal challenging the trial court’s temporary injunction order requiring Noble to pay increased maintenance and cure benefits under general maritime law to seaman Eric Wheeler. Concluding that the trial court erred in so doing, we reverse and remand the temporary injunction order. Background

Wheeler reported experiencing severe neck and back pain while working on a drillship for Noble. He was removed from the vessel on August 6, 2021 and taken ashore for further evaluation. The parties disagree regarding the cause and extent of Wheeler’s injuries as well as whether he has fully recovered. In this lawsuit, Wheeler has sued Noble for (1) negligence under the Jones Act, (2) unseaworthiness, and (3) maintenance and cure benefits. Noble began paying Wheeler maintenance benefits of $35 per day, but Wheeler filed a motion to compel, requesting the amount of maintenance be increased to $120.21 a day. Wheeler also requested that Noble be ordered to pay for his medical care with a physician of his choosing, even though his preferred doctor is apparently not in- network for his health insurance and another doctor apparently cleared him to return to work with no restrictions. The trial court granted Wheeler’s motion and issued a temporary injunction requiring Noble to pay Wheeler maintenance of $121.21 a day until maximum medical improvement has been reached and requiring it to pay all of his reasonable and necessary medical expenses. Noble then brought this interlocutory appeal. 1

Discussion

Noble challenges the trial court’s temporary injunction in three issues, asserting that (1) the trial court erred in ordering maintenance and cure in a temporary injunction, (2) the trial court’s order did not meet the requirements for such orders in Texas Rule of Civil Procedure 683, and (3) Wheeler did not satisfy the elements for issuance of a temporary injunction. We will begin by setting forth the general law governing our analysis before briefly addressing whether the order

1 The trial court entered a series of four temporary injunction orders. The order at issue here is the fourth and final order that is currently in place.

2 in this case satisfies the requirements of Rule 683. We will then turn to the key question of whether the trial court abused its discretion in entering a temporary injunction order requiring an increase in maintenance and cure benefits.

I. Governing Law

A. Standard of Review

We review the grant or denial of a temporary injunction for an abuse of discretion. Davis v. Huey, 571 S.W.2d 859, 861–62 (Tex. 1978); EMSL Analytical, Inc. v. Younker, 154 S.W.3d 693, 696 (Tex. App.—Houston [14th Dist.] 2004, no pet.). The trial court abuses its discretion if it acts arbitrarily and unreasonably, without reference to guiding rules or principles, or if it misapplies the law to the established facts of the case. Law v. William Marsh Rice Univ., 123 S.W.3d 786, 792 (Tex. App.—Houston [14th Dist.] 2003, pet. denied).

B. Maintenance and Cure

Although, as was done here, a claim for maintenance and cure is typically brought in conjunction with a Jones Act negligence claim or unseaworthiness claim, it is a separate and distinct cause of action. See Weeks Marine, Inc. v. Garza, 371 S.W.3d 157, 163 (Tex. 2012); Hewitt v. Ryan Marine Servs., Inc., No. 14-09- 00227-CV, 2012 WL 3525408, at *7 (Tex. App.—Houston [14th Dist.] Aug. 16, 2012, no pet.) (mem. op.). The obligation to pay maintenance and cure benefits is based on the vessel owner’s duty to provide food, lodging, and medical services to a seaman who is injured in service to the ship. See Weeks Marine, 371 S.W.3d at 163. “Maintenance is a daily stipend for living expenses, whereas cure is the payment of medical expenses.” Meche v. Doucet, 777 F.3d 237, 244 (5th Cir. 2015) (internal quotations and citations omitted). A seaman is entitled to maintenance and cure until the date of maximum possible cure, or the date beyond

3 which further treatment would not improve the condition. E.g., Mar. Overseas Corp. v. Ellis, 886 S.W.2d 780, 795 (Tex. App.—Houston [14th Dist.] 1994), aff’d, 971 S.W.2d 402 (Tex. 1998). The obligation has been a feature of maritime law for centuries and is grounded in humanitarian and economic concerns. See Weeks Marine, 371 S.W.3d at 163. “A claim for maintenance and cure is considered contractual in nature and arises from the relationship between seaman and employer.” Id.

When an employer receives a demand for maintenance and cure, it is not required to immediately begin making payments but may conduct a reasonable investigation and require corroboration. E.g., Boudreaux v. Transocean Deepwater, Inc., 721 F.3d 723, 728 (5th Cir. 2013). In addition, an employer may rely on certain legal defenses to deny a claim for maintenance and cure. Brown v. Parker Drilling Offshore Corp., 410 F.3d 166, 171 (5th Cir. 2005). However, if a shipowner wrongly fails to provide maintenance and cure benefits, the seaman may be entitled to compensatory damages for any injuries caused by such failure, in addition to the amount of the withheld benefits, and may even be entitled to punitive damages if the failure to pay is deemed willful and wanton. Weeks Marine, 371 S.W.3d at 165.

While claims for maintenance and cure are based in federal substantive law, state law governs procedural matters in such cases in state courts. See, e.g., Helix Energy Sols. Grp., Inc. v. Howard, 452 S.W.3d 40, 43–44 (Tex. App.—Houston [14th Dist.] 2014, no pet.) (noting but not addressing question of whether maintenance and cure benefits can be granted via temporary injunction); see also W & T Offshore, Inc. v. Fredieu, 610 S.W.3d 884, 890 (Tex. 2020). There are numerous potential fact questions involved in maintenance and cure cases to be decided by a jury in a jury trial and by the judge in a bench trial; these include the

4 correct per diem amount for maintenance benefits, the allowable expenses for cure, the timeframe for such benefits, whether the plaintiff qualified as a seaman, whether the seaman was entitled to any such benefits at all, and the amount of any compensatory or punitive damages. See generally Fitzgerald v. U.S. Lines Co., 374 U.S. 16, 21 (1963); Socony-Vacuum Oil Co. Inc. v. Aderhold, 150 Tex. 292, 298, 240 S.W.2d 751, 754–55 (1951); Cepeda v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hall v. Noble Drilling (U.S.) Inc.
242 F.3d 582 (Fifth Circuit, 2001)
Brown v. Parker Drilling Offshore Corp.
410 F.3d 166 (Fifth Circuit, 2005)
Fitzgerald v. United States Lines Co.
374 U.S. 16 (Supreme Court, 1963)
Wallace Boudreaux v. Transocean Deepwater, Inc.
721 F.3d 723 (Fifth Circuit, 2013)
EMSL Analytical, Inc. v. Younker
154 S.W.3d 693 (Court of Appeals of Texas, 2004)
Law v. William Marsh Rice University
123 S.W.3d 786 (Court of Appeals of Texas, 2003)
Interfirst Bank San Felipe, N.A. v. Paz Construction Co.
715 S.W.2d 640 (Texas Supreme Court, 1986)
Maritime Overseas Corp. v. Ellis
886 S.W.2d 780 (Court of Appeals of Texas, 1994)
Maritime Overseas Corp. v. Ellis
971 S.W.2d 402 (Texas Supreme Court, 1998)
Butnaru v. Ford Motor Co.
84 S.W.3d 198 (Texas Supreme Court, 2002)
Socony-Vacuum Oil Co. v. Aderhold
240 S.W.2d 751 (Texas Supreme Court, 1951)
RP & R, Inc. v. Territo
32 S.W.3d 396 (Court of Appeals of Texas, 2000)
Davis v. Huey
571 S.W.2d 859 (Texas Supreme Court, 1978)
Willie Meche v. Key Energy Services, L.L.C.
777 F.3d 237 (Fifth Circuit, 2015)
Inocente Cepeda v. Orion Marine Construction, Inc.
499 S.W.3d 579 (Court of Appeals of Texas, 2016)
Weeks Marine, Inc. v. Garza
371 S.W.3d 157 (Texas Supreme Court, 2012)
Helix Energy Solutions Group, Inc. v. Howard
452 S.W.3d 40 (Court of Appeals of Texas, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Noble Drilling (U.S.) LLC v. Eric Wheeler, Counsel Stack Legal Research, https://law.counselstack.com/opinion/noble-drilling-us-llc-v-eric-wheeler-texapp-2024.