Nkihtaqmikon v. Impson

585 F.3d 495, 40 Envtl. L. Rep. (Envtl. Law Inst.) 20242, 2009 U.S. App. LEXIS 23714, 2009 WL 3448231
CourtCourt of Appeals for the First Circuit
DecidedOctober 28, 2009
Docket08-2122
StatusPublished
Cited by5 cases

This text of 585 F.3d 495 (Nkihtaqmikon v. Impson) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nkihtaqmikon v. Impson, 585 F.3d 495, 40 Envtl. L. Rep. (Envtl. Law Inst.) 20242, 2009 U.S. App. LEXIS 23714, 2009 WL 3448231 (1st Cir. 2009).

Opinion

BOUDIN, Circuit Judge.

This appeal is the second in continuing litigation by a group of members of the Passamaquoddy Tribe called Nulankeyutmonen Nkihtaqmikon — the phrase means “We Protect the Homeland,” and we refer to the group as NN — to challenge a Bureau of Indian Affairs (“BIA”) decision; the decision approved a lease of a plot of Passamaquoddy land for the construction and operation of a liquefied natural gas (“LNG”) facility, contingent on federal regulatory approval being obtained from the Federal Energy Regulatory Commission (“FERC”). The relevant facts, which have been discussed in previous decisions, 1 are as follows.

In May 2005, the tribal authorities in charge of the Pleasant Point reservation agreed to a lease with Quoddy Bay, LLC (“Quoddy Bay”), that would allow Quoddy Bay to construct a LNG facility on a 3/4 acre portion of the tribe’s land known as *497 Split Rock. The lease contemplates four phases: permitting, construction, operations, and removal and remediation. In the first “permitting” phase, Quoddy Bay is entitled to test and survey the land as needed to obtain FERC approval for construction, and the latter phases, if the project moves ahead, allow for construction and operation of the LNG facility. Absent FERC approval, the project cannot proceed and the lease can be terminated by the Tribe.

The lease was submitted to the BIA for approval in May 2005 under the Indian Long-Term Leasing Act (“Leasing Act”), 25 U.S.C. § 415 (2006), and the BIA approved it approximately one week later, on June 1, 2005. The BIA did not prepare an environmental impact statement, consult with other agencies or conduct other inquiries before approving the lease. It said, however, that its lease approval allowed only site investigation and that anything more would require approval by FERC, see 15 U.S.C. § 717b(e)(l); the more thorough analyses required by the National Environmental Policy Act (“NEPA”), 42 U.S.C. § 4321 et seq., and other statutes would be part of that approval process. 2 The BIA stated that

lease approval is solely for the site investigation required for the [FERC] permitting process in the development of [the required environmental assessment (“EIS”) ] .... Continuing the lease beyond the investigation period is contingent upon FERC permit approval, acceptability of the EIS analysis and insignificant impact on the leased property.

Seeking to forestall the surveying and testing, NN filed suit in November 2005: it alleged that the BIA approved the lease in violation of NEPA, the National Historic Preservation Act, 16 U.S.C. § 470 et seq., the Leasing Act, and the Administrative Procedure Act (“APA”), 5 U.S.C. §§ 701-706, by failing to conduct environmental reviews; consider the historical, religious, and cultural significance of the leased land; prepare a fair market appraisal; and provide an opportunity for public comment. NN later sued to enjoin the lease under a citizen-suit provision of the Endangered Species Act, 16 U.S.C. § 1540(g), and the two actions were consolidated.

The BIA moved to dismiss on multiple grounds: that what it described as preliminary approval was not “final” agency action, that NN lacked standing, and that the case was not yet ripe for judicial review. The district court agreed, NN I, 462 F.Supp.2d at 112, but on appeal, the BIA conceded that its lease approval was technically final, albeit no construction or operation could be undertaken without FERC approval, NN II, 503 F.3d at 26. Still, the BIA argued that the law suit was premature because NN had not exhausted administrative review within the Interior Department available under its regulations. See 25 C.F.R. §§ 2.4(e), 2.6; 43 C.F.R. § 4.331.

*498 Rejecting other BIA objections (standing, ripeness), this court held that exhaustion of agency remedies was “mandatory” under governing precedent, subject only to the possibility that one of the established exceptions to the exhaustion requirement applied. NN II, 503 F.3d at 33-34. The court then remanded the case to the district court with instructions to “consider whether [NN] merit[s] an exception to the exhaustion requirement.” Id. at 34. Back in the district court, NN preserved its administrative remedies, 3 and then, instead of arguing any “exception” excused its failure to exhaust, told the district court that this court had erred by imposing the exhaustion requirement in the first place.

The district court replied that this court had declared exhaustion “mandatory” unless an exception applied, and it found no exception applicable: the exceptions mooted but rejected by the district court were those based on exceptional circumstances, see White Mountain Apache Tribe v. Hodel, 840 F.2d 675, 677 (9th Cir.1988), and on equitable considerations like waiver or estoppel, see Frederique-Alexandre v. Dep’t of Natural and Envtl. Res., 478 F.3d 433, 440 (1st Cir.2007). Accordingly, the district court dismissed the ease — leaving NN to pursue its internal Interior Department appeals before resuming (if necessary) litigation in the district court. NN III, 573 F.Supp.2d at 314, 318.

On this second appeal, NN does not argue that any exception to the exhaustion requirement applies; instead it takes issue, as it did in the district court, with our earlier decision that exhaustion was mandatory unless an exception applied. Yet the remand order was quite clear that exhaustion was required unless excused, see NN II, 503 F.3d at 33-34, and any request that it be reconsidered should have been made by a timely petition for rehearing in this court, see United States v. DeJesus, 752 F.2d 640, 643 (1st Cir.1985); when our mandate issued, it established the law of the case. United States v. Moran, 393 F.3d 1, 7 (1st Cir.2004).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ms. S. v. Regional School Unit 72
916 F.3d 41 (First Circuit, 2019)
Kashner Davidson Securities Corp. v. Mscisz
601 F.3d 19 (First Circuit, 2010)
OLAMIDE OLORUNNIYO ORE v. Clinton
675 F. Supp. 2d 217 (D. Massachusetts, 2009)
NKIHTAQMIKON v. Bureau of Indian Affairs
672 F. Supp. 2d 154 (D. Maine, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
585 F.3d 495, 40 Envtl. L. Rep. (Envtl. Law Inst.) 20242, 2009 U.S. App. LEXIS 23714, 2009 WL 3448231, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nkihtaqmikon-v-impson-ca1-2009.