Nix v. Heald

203 P.2d 847, 90 Cal. App. 2d 723
CourtCalifornia Court of Appeal
DecidedMarch 21, 1949
DocketCiv. 16747
StatusPublished
Cited by5 cases

This text of 203 P.2d 847 (Nix v. Heald) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nix v. Heald, 203 P.2d 847, 90 Cal. App. 2d 723 (Cal. Ct. App. 1949).

Opinion

MOORE, P. J.

Plaintiff was denied damages for an alleged breach of contract while defendants were awarded damages for plaintiff’s violation of the same contract. Plaintiff and his assignor, the cross-defendant, appeal.

Community Building Company, a corporation, sometimes referred to herein as builder, was at the time of executing the contract engaged in constructing and selling single residence homes in Los Angeles. Respondents were then subcontracting plumbers. On July 7, 1945, the builder and the plumbers executed a writing whereby the latter agreed to do all the necessary plumbing in 100 homes to be constructed by the builder.

Under the terms of the contract the builder was obliged to notify the plumbers to commence delivery “approximately August 1, 1945.” Instead, it did not give them notice until September 5,1945, whereupon respondents immediately began to install the plumbing. Such delay of 35 days was serious. It caused respondents to lose their war-time priorities for plumbing supplies and equipment, necessitating their resort to the open market in an effort to obtain the required materials greatly in demand and scarce in quantity. The unavoidable results were respondents’ delay in the installation of the plumbing, and their inability to comply with their agreement “to supply material and install same at rate of one house per day.” Although tardy, respondents completed the installation of the plumbing in 45 houses and were paid in full therefor. Having asserted that respondents were in default under the contract, in October, 1945, the builder *726 employed another plumber to complete the plumbing subcontract. .At no time did respondents refuse to carry out their contract prior to the builder’s employment of the other concern. On September 4, 1946, the builder assigned its contract to appellant Nix who sued to recover as damages the excess of the amount paid the new plumber for completing the installation over the price to have been paid under the contract. Respondents filed a general denial and their cross-complaint.

The theory of appellant’s action was that respondents’ performance was not a substantial compliance with the contract in that they had failed to complete the plumbing at the rate of one house per day. Therefore, they contended, they were justified in terminating the contract, in employing another plumber, and in recovering damages in the amount suffered by reason of the employment of the new subcontractor. The theory of respondents’ answer was that if they were behind their prescribed schedule, the delay was occasioned by the builder’s tardiness in notifying respondents to commence operations; the builder could not take advantage of its own delinquency to declare the contract at an end. By their cross-complaint respondents alleged and thereafter contended that since the builder could not invoke the termination clause of the contract, it was not warranted in employing another plumber, thereby depriving respondents of anticipated profits.

The trial court submitted 11 special interrogatories to the jury for answer, and of these, number 7 and the answer thereto are alone sufficient to sustain both judgments.

(7) If defendants were behind schedule on either of the said dates [September 21 or October 18,1945], was their delay proximately caused by failure of Community Building Company to commence work or to make it possible for defendants to commence work on or about August 1, 1945, with resultant loss of frozen plumbing materials? Answer Yes.”

Inasmuch as respondents’ delay was in turn caused by the builder’s delay, the latter was in no position to declare a forfeiture of respondents’ rights to fulfill the contract. It follows that since the builder’s hiring of another plumber was in derogation of respondents’ contractual rights, Community Building Company was properly held to answer for damages proximately caused thereby.

Appellants contend that the jury’s answers to other special interrogatories demonstrate that respondents’ judgment on their cross-complaint rests only upon an alleged oral modification of the written contract. .Not so. Admittedly, the jury *727 found that the contract had been modified in that the builder waived the right to terminate the contract for any and all delays of respondents in consideration of respondents’ doing additional work. But the same judgment could have been entered even if the jury had found that there was no oral modification. Assuming as appellants contend that there was no waiver of the covenant permitting the builder to procure other plumbers if respondents were too slow, still the builder would have been in no position to invoke that provision because the jury found that the delay which would have permitted its invocation was caused by the building company. Thus, the builder could not say, “We are terminating this contract because you are not complying” for the good reason that the builder itself was the cause of respondents’ noncompliance.

Appellants contend that respondents by commencing work under the contract waived any default of the builder caused by its tardy notification to commence performance. Admitting such contention, arguendo, yet respondents’ waiver of one default did not concede to appellants the right subsequently to breach the contract by hiring another plumber. Nor would respondents’ waiver of the builder’s first default preclude respondents’ action against the builder for a subsequent breach of the contract. Also, appellants contend that respondents’ allegedly belated commencement of installing the plumbing was a breach of a mere independent covenant. This is not sustained by a fair construction of the issues. Neither respondents’ defense to the original action nor their contentions on the cross-complaint were predicated ón the builder’s initial delay. Both were founded on the builder’s breach of the contract by hiring another plumber to complete the project.

Appellants contend that respondents should not have been permitted to recover on their cross-complaint because there was no showing that the plumbers were able to complete their contract. To buttress this argument appellants cite the testimony of Jerome Heald to the effect that respondents did not have the materials wherewith to finish the remaining 55 houses. But by the contract respondents guaranteed the availability of materials for only the first 45 houses. It does not follow that because respondents did not have materials on hand they were unable to complete their contract. They could as in the construction of the first 45 houses resort to the open market, such as it was in 1945, to procure their supplies.

*728 Appellants next contend that the court improperly permitted the jury to interpret the terms of the contract by submitting special interrogatories 1 and 12 and by giving instructions pertinent thereto.

Special Interrogatory 1 and the Answer

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Simms
10 Cal. App. 3d 299 (California Court of Appeal, 1970)
Bate v. Marsteller
232 Cal. App. 2d 605 (California Court of Appeal, 1965)
Gerstner v. Scheuer
204 P.2d 937 (California Court of Appeal, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
203 P.2d 847, 90 Cal. App. 2d 723, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nix-v-heald-calctapp-1949.