Nissan North America v. Jim M'Lady Olds

CourtCourt of Appeals for the Seventh Circuit
DecidedMay 11, 2007
Docket05-1786
StatusPublished

This text of Nissan North America v. Jim M'Lady Olds (Nissan North America v. Jim M'Lady Olds) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nissan North America v. Jim M'Lady Olds, (7th Cir. 2007).

Opinion

In the United States Court of Appeals For the Seventh Circuit ____________

No. 05-1786 NISSAN NORTH AMERICA, INCORPORATED, Plaintiff-Appellant, v.

JIM M’LADY OLDSMOBILE, INCORPORATED d/b/a JIM M’LADY NISSAN, Defendant-Appellee. ____________ Appeal from the United States District Court for the Northern District of Illinois, Eastern Division. No. 01 C 1290—Joan B. Gottschall, Judge. ____________ ARGUED JUNE 5, 2006—DECIDED MAY 11, 2007 ____________

Before BAUER, ROVNER and WILLIAMS, Circuit Judges. ROVNER, Circuit Judge. In this successive appeal, Nissan North America, Inc. (“Nissan”) challenges the district court’s grant of summary judgment in favor of Jim M’Lady Oldsmobile d/b/a/ Jim M’Lady Nissan (“M’Lady”).1 The first time the case was before us, we vacated the district court’s order compelling arbitration,

1 We will use “M’Lady” to refer to the dealership and “Jim M’Lady” to refer to the individual who was the principal owner and president of the M’Lady dealership at all relevant times. 2 No. 05-1786

finding that Nissan had failed to produce sufficient evidence of arbitrability and the court had not given M’Lady an adequate opportunity to rebut Nissan’s evi- dence. See Nissan North America, Inc. v. Jim M’Lady Oldsmobile, Inc., d/b/a Jim M’Lady Nissan, 307 F.3d 601 (7th Cir. 2002) (hereafter “Nissan I”). With the benefit of a more developed record on remand, the district court found that Nissan failed to demonstrate that it was entitled to arbitration and entered judgment in favor of M’Lady. We affirm.

I. Because the record is considerably more developed than when last we visited this dispute, we recount the rele- vant facts anew. See Nissan I, 307 F.3d at 602-03. Nissan filed this suit to compel arbitration of a dispute regard- ing Nissan’s termination of M’Lady’s car dealership. In 1992, Nissan and M’Lady entered into a written dealership contract that allowed M’Lady to operate as an authorized dealer of Nissan cars and trucks. This initial agreement, titled “Nissan Dealer Term Sales & Service Agreement,” (hereafter “Dealer Agreement”) was set to expire on April 1, 1995. The Dealer Agreement specified that it would automatically terminate at the end of the stipulated term without any action by either party. Another provision required that any amendments be made in a writing executed by both parties. In 1994, the parties extended the termination date to November 1, 1996 by executing “Amendment No. 1 to Nissan Dealer Term Sales and Service Agreement.” Second and third amendments effected changes to certain terms of the Dealer Agreement that are not at issue here, but did not modify the termina- tion date. November 1, 1996 came and went without the parties signing any extension to the Dealer Agreement. Until May 1998, M’Lady continued operating as a dealer of No. 05-1786 3

Nissan products without a written contract in place to govern the parties’ relationship. On May 8, 1998, the parties entered into “Amendment No. 4 to Nissan Dealer Term Sales and Service Agreement” (“Amendment 4”). Amendment 4 changed the expiration date of the Dealer Agreement to May 1, 1999 and changed certain deadlines for M’Lady to complete construction of an exclusive Nissan showroom. To effect the latter of these changes, “Article Twelfth” of the original Dealer Agreement was amended to provide that M’Lady would (1) submit for Nissan’s approval plans for the construction of the new showroom by July 1, 1998; (2) submit to Nissan a signed contract for the construction of the showroom by September 1, 1998; (3) commence construction of the new showroom by November 1, 1998; and (4) complete construc- tion of the new showroom by May 1, 1999. Amendment 4 also contained a provision subjecting the parties to binding arbitration as the “exclusive mechanism for resolving any dispute, controversy or claim arising out of or relating in any way to this agreement and Amendment No. 4, including but not limited to claims under any state or federal statutes (hereinafter “Disputes”).” All Disputes were to be submitted to the independent arbi- tration service JAMS/ENDISPUTE unless arbitration was waived in writing by both parties. Amendment 4 marked the first time the parties agreed to arbitration. On April 14, 1999, two weeks before the Dealer Agree- ment was set to expire, Nissan sent M’Lady a “Notice of Default,” charging M’Lady with failing to meet three of the four Amendment 4 deadlines for constructing the exclusive Nissan showroom. The Notice of Default required M’Lady to either complete the showroom within sixty days or provide a commitment within sixty days to complete the showroom in an acceptable amount of time. If M’Lady failed to complete these new requirements within sixty days, Nissan stated it would consider the Dealer Agree- 4 No. 05-1786

ment to be in breach and that this breach “may result in Nissan issuing a Notice of Termination” under the relevant provisions of the Dealer Agreement. This was a curious threat given that the agreement was set to expire on its own terms approximately two weeks later, on May 1, 1999. On May 17, 1999, M’Lady responded to the Notice of Default by explaining that a lawsuit with its landlord delayed construction, that the suit had been resolved six months earlier and that M’Lady had since contracted with an architect to begin the planning process for the new facility. M’Lady hoped to have a final set of plans by August 1999 and planned to begin construction by the end of 1999 or the spring of 2000.2 Nissan responded on June 25, 1999, by offering “an additional period to substantially correct [M’Lady’s] failure to fulfill its re- sponsibilities under Article Twelfth (d) of the Agreement with respect to the new exclusive Nissan Showroom.” The June 25th letter offered “an additional one hundred-eighty (180) day extension, expiring on December 14, 1999, upon which to either commence construction or provide Nissan with a new Nissan Exclusive Showroom Facility.” Nothing in this letter addressed the larger issue of the expiration of the Dealer Agreement and its amendments. M’Lady apparently did not meet the new deadlines set by the June 25th letter, and Nissan consequently sent a “Notice of Termination Pursuant to the Nissan Dealer Sales and Service Agreement and Chapter 815, Sections 710 et seq. of the Illinois Compiled Statutes” (hereafter “Notice of Termination”) on January 19, 2000. This letter purported to terminate the Dealer Agreement and also to

2 M’Lady’s May 17th letter began by stating, in relevant part, “As you are aware, Jim M’Lady Nissan has agreed to provide an extensive showroom area for our Nissan line to fulfill our original agreement.” The letter then explained the cause of the delays and a new tentative schedule for the showroom. No. 05-1786 5

terminate M’Lady as a dealer, effective sixty days from receipt of the letter. The Notice of Termination directed M’Lady, among other things, to stop selling Nissan products, and to remove the Nissan name and trademark from the dealership, including from all signs and all advertising materials. Jim M’Lady met with representatives of Nissan on April 14, 2000, and informed them that he was trying to sell the Nissan dealership. As a result, on May 8, 2000, Nissan sent M’Lady a letter that purported to extend the effective date of the termination by ninety days to give M’Lady an opportunity to complete negotiations and to present an acceptable buy-sell agreement to Nissan.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brody v. Finch University of Health Sciences/the Chicago Medical School
698 N.E.2d 257 (Appellate Court of Illinois, 1998)
British Motor Car Distributors, Ltd. v. New Motor Vehicle Board
194 Cal. App. 3d 81 (California Court of Appeal, 1987)
Div. of Labor Law Enf't v. Transpacific Transp. Co.
69 Cal. App. 3d 268 (California Court of Appeal, 1977)
IDS Life Insurance v. SunAmerica, Inc.
103 F.3d 524 (Seventh Circuit, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Nissan North America v. Jim M'Lady Olds, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nissan-north-america-v-jim-mlady-olds-ca7-2007.