This text of 385 F.3d 915 (Nischwitz v. Miskovic (In Re Airspect Air, Inc.)) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nischwitz v. Miskovic (In Re Airspect Air, Inc.), 385 F.3d 915, 2004 WL 2211609 (6th Cir. 2004).

Opinion

SILER, Circuit Judge.

The bankruptcy court authorized Air-spect Air, Inc. (“Airspect”), then in Chapter 11 proceedings, to retain Jeffrey Nis-chwitz as special counsel in order to prosecute a breach of contract action against the City of Akron (the “City”). Airspect retained Nischwitz under a contingency fee agreement, and, after the lawsuit settled, Nischwitz filed an application for his contingency fee. The bankruptcy court denied the application, however, finding pursuant to § 330 of the Bankruptcy Code that the fee sought by Nischwitz was unreasonable. Nischwitz appealed to the Bankruptcy Appellate Panel of the Sixth Circuit (the “BAP”), which held that the bankruptcy court had “pre-approved” the contingency fee agreement under § 328 of the Bankruptcy Code and, thus, was obligated to hon- or the agreement unless intervening circumstances had rendered the agreement “improvident.” On remand, the bankruptcy court held that an intervening circumstance had, in fact, rendered the agreement “improvident,” but, on a second appeal, the BAP disagreed. Spasoje Miskovic, the sole interest holder in Air-spect, appeals, arguing that (1) the bankruptcy court never “pre-approved” the contingency fee agreement, and alternatively that (2) the termination of the lease by operation, of law rendered the agreement “improvident.” We hold that the bankruptcy court never “pre-ap-proved” the contingency fee agreement and REVERSE and REMAND.

BACKGROUND

Airspect entered into a long-term lease with the City to operate a “fixed-based operation” at the Akron-Fulton International Airport. In compliance with the lease, Airspect constructed a 28,500 square foot building, hangar, ramp, and fuel farm (collectively, the “Improvements”). After various disputes concerning the terms of *918 the lease, Airspect withheld payments from the City.

In June 1994, Airspect sued in the Court of Common Pleas of Summit County, Ohio. It asserted claims for breach of contract, misrepresentation, and constructive eviction, and prayed for $10 million in compensatory damages and rescission of the lease. The City, in turn, alleged that Airspect had materially breached the lease, and sought to recover damages, to evict Air-spect from its leasehold, and to recover the Improvements.

In December 1995, Airspect’s counsel withdrew from the litigation, so Airspect retained Nischwitz. 1 In March 1996, Air-spect filed a voluntary Chapter 11 petition in the bankruptcy court. The state lawsuit was stayed and then transferred to the bankruptcy court as an adversary proceeding in the Chapter 11 reorganization.

In May 1996, Airspect, acting as a debt- or in possession, applied to the bankruptcy court for authorization to employ Nis-chwitz as special counsel for the purpose of litigating Airspect’s suit against the City. The application requested a $7,000 retainer and stated that the parties had reached á contingency fee agreement with the following terms: “Fees, other than expenses, are to be paid on a contingency basis and are subject to approval by this court. The fee agreement states 38% if settled at least two weeks before trial; 40% if within two weeks of trial or, after commencement of trial; 50% if post-trial or re-trial.” The bankruptcy court issued an order authorizing Nischwitz’s employment. Specifically, the order provided that “Airspect is authorized to pay the sum of $7,000 of corporate funds as partial retainer for expenses” and that Nischwitz must “submit application for fees to this Court for approval.”

The City filed a motion for a termination of the automatic stay, arguing that the lease had terminated by operation of law pursuant to 11 U.S.C. § 365(d)(4) 2 when Airspect failed to assume or reject the lease within sixty days after the date of the order for relief. The bankruptcy court agreed that the lease was rejected pursuant to § 365(d)(4). The court determined, however, that Airspect had significant equity in the Improvements, and denied the City’s motion for relief from the stay and allowed Airspect to remain in possession of the property. The City appealed to the United States District Court for the Northern District of Ohio. In July 1998, the district court reversed the bankruptcy court’s denial of relief from the stay, holding that Airspect’s rejection of the lease meant that the City was entitled to immediate possession of the leased premises. The parties settled the matter during the pendency of an appeal to this court.

Meanwhile, the adversary proceeding between Airspect and the City proceeded. In 1997, the bankruptcy court transferred the matter to the district court. In 1999, the parties reached a settlement whereby the City agreed to (1) accept the sale of Airspect’s assets to a new fixed base operator found by Airspect, or (2) pay Airspect the sum of $575,000 in exchange for Air-spect’s surrender of the leased premises and the Improvements. The bankruptcy *919 court approved the settlement and the district court dismissed the lawsuit. Eventually, the City elected to pay $575,000 to Airspect.

In 2000, Nischwitz filed a fee application in the bankruptcy court. Nischwitz requested $189,750 per the contingency fee agreement. Airspect’s sole interest-holder, Spasoje Miskovic, filed objections to Nischwitz’s fee application. The trustee had no objection to Nischwitz’s application.

The bankruptcy court approved only $37,050 in fees for Nischwitz. It denied Nischwitz’s request for payment under the contingency fee agreement, finding that the contingency (a trial or settlement) had not been met because the lawsuit had been resolved incidental to a “sale” of the lease and the Improvements as part of a “global settlement” between the parties. Consequently, the court awarded what it deemed reasonable compensation to Nischwitz pursuant to § 330(a) of the Bankruptcy Code. 3 It found that only those services rendered prior to September 9, 1996, when the bankruptcy court ruled that Airspect had rejected the lease, conferred a benefit upon the estate. Accordingly, the court awarded Nischwitz fees of $37,050 for the 247 hours worked prior to September 9, 1996.

The BAP reversed, holding that Nis-chwitz had satisfied the contingency agreement by settling the case and rejecting the bankruptcy court’s characterization of the settlement as a “sale.” The BAP found that the bankruptcy court had approved the contingency agreement pursuant to § 328 of the Bankruptcy Code 4 and, thus, was required to honor the agreement unless it proved “improvident” in light of subsequent events. This decision was not appealed.

On remand, the bankruptcy court found that it had improvidently approved the contingency fee agreement in light of the lease rejection by operation of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robert Betancourt
D. New Mexico, 2022
Cook and Sons Mining, Inc.
E.D. Kentucky, 2020
In re: William Aubiel v.
Sixth Circuit, 2015
In re Aubiel
534 B.R. 300 (Sixth Circuit, 2015)
In re Youngquist
501 B.R. 877 (D. Kansas, 2013)
In re Prosser
50 V.I. 359 (Virgin Islands, 2008)
In Re: Airspect Air, Inc.
385 F.3d 915 (Sixth Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
385 F.3d 915, 2004 WL 2211609, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nischwitz-v-miskovic-in-re-airspect-air-inc-ca6-2004.