Opinion
GRUENDEL, J.
In this contract interpretation action, the plaintiff, Nipmuc Properties, LLC, appeals from the judgment of the trial court denying its claim for a declaratory judgment against the defendants, PDC-E1 Paso Meriden, LLC (PDC-E1 Paso), Meriden Gas Turbines, LLC (Meriden Gas Turbines), Thomas P. Cadden, trustee of the 1998 Real Estate Trust, and the city of Meriden (Meriden), for the delivery of a lease held in escrow. On appeal, the plaintiff claims that the court improperly construed the contract to include provisions not agreed to by the parties and made findings that were unsupported by the record.
We affirm the judgment of the trial court.
The record reveals the following relevant facts as set forth by the court in its memorandum of decision. “The plaintiff held title to a parcel of land comprised of approximately 845 acres along the Metacomet ridgeline in . . . Meriden and Berlin. Due to the size and nature of the parcel, as well as its proximity to the Algonquin gas pipeline, the land became the subject of a proposal to build a 544 megawatt gas fired electric generation facility in the late 1990s, shortly after [the General
Assembly] enacted legislation deregulating the generation of electric power. In furtherance of this proposal, the plaintiff entered into a contract with Summitwood [Development, LLC, (Summitwood)]. Pursuant to this contract, Summitwood obtained the exclusive right to purchase the property. Summitwood then entered into an agreement to sell the land to PDC-E1 Paso. PDC-E1 Paso then initiated the process to obtain permits necessary to build an electric generation facility on this property, including a certificate of environmental compatibility and public need issued by the [Connecticut siting council (siting council)], pursuant to General Statutes § 16-50g et seq. All of the parties to this action understood that the construction of such an electric generation facility involved an extensive permitting process and was ultimately subject to the approval of the [siting council].
“The original purchase and sale agreement called for the buyer, PDC-E1 Paso, to return thirty acres of the 845 acre parcel to Summitwood after the closing. The intent was for Summitwood to retain this property on behalf of, and for development by the plaintiff, the original owner of the 845 acre parcel. The precise location of the thirty acres was to be determined by the parties at a future date.
“PDC-E1 Paso was unable to perform its contract to purchase the land from Summitwood, which required closing on the title to the property no later than December 31, 2000. PDC-E1 Paso was unable to perform the contract in a timely manner primarily because its gas turbine manufacturer could not supply the necessary gas turbines to power the electric generation facility. This problem required a significant change in the design of the facility. All of the parties agreed that this design change required the further consideration and approval by the [siting council].
“With the understanding that PDC-E1 Paso would default under the contract if it failed to close by December 31, 2000, the parties negotiated an amendment to the purchase and sale agreement, dated December 21, 2000 (amendment). The parties, through their representatives, further memorialized their understanding in a letter dated December 21,2000 (letter).
The interpretation of the language of these full exhibits is of critical importance to the determination of the rights and obligations of the parties to this action.
“Pursuant to the amendment, the parties generally agreed to extend the closing date to January 10, 2001. If the closing occurred on or before this date, the purchase price of $12 million would be reduced by $500,000. The amendment also provided that PDC-E1 Paso would lease approximately fifty-two acres of the 845 acre parcel back to Summitwood on behalf of the plaintiff. The lease of the fifty-two acre parcel was for a period of ninety-nine years with the possibility of extension for an additional ninety-nine years. This long-term lease of the fifty-two acres replaced the provision in the original agreement in which Summitwood had the right to retain thirty acres on behalf of the plaintiff. None of the parties dispute these provisions in the amendment to the agreement.
“This vigorously negotiated amendment further provided that the lease would be placed in escrow pending
the outcome of [siting council] approval. The specific language of § 2 (a) of the amendment provides that ‘[t]he Escrow Agent shall deliver the Lease to Sum-mitwood upon the approval of the [siting council] of the Buyer’s application to amend the decision and order issued by the [siting council] for the Power Plant described in the Purchase Agreement.’ . . .
“In addition to the amendment dated December 21, 2000, the parties further memorialized their agreement in a letter, also dated December 21, 2000. The letter states that ‘notwithstanding anything contained in the agreement to the contrary, in the event of a denial by the [siting council] of PDC-E1 Paso[’s] . . . application for approval of the transactions described in Section 2 (a) of the Amendment, the undersigned shall pay to Summitwood the additional sum of Seven Hundred Sixty Thousand ($760,000) Dollars.’ Section 2 (a) of the amendment primarily describes the fifty-two acre leaseback agreement, the escrow and the permitted uses of the leasehold property by Summitwood. The letter also describes two circumstances under which the $760,000 payment would not be due to Sum-mitwood: (1) if the siting council ‘approves the transactions described in Section 2 (a) of the Amendment,’ or (2) ‘if no closing occurs.’ . . .
“On January 10, 2001, PDC-E1 Paso assigned all of its rights and obligations under the amended purchase and sale agreement to [Meriden Gas Turbines]. On the same day, [Meriden Gas Turbines] closed on the 845 acre parcel. The [Meriden Gas Turbines] deed indicates that its title is subject to the fifty-two acre lease held in escrow. The lease, however, was not recorded at that time.
“Subsequently, on September 12, 2001, the [siting council] approved the proposed changes to the electric generation facility but rejected the proposed leaseback
of fifty-two acres to Summitwood. Instead, the [siting council] directed that title to the fifty-two acres be donated to Meriden.
Despite several public hearings and numerous public records concerning the application for the project, covering the span of several years, the first specific request made to the [siting council] for approval of land to be retained by the plaintiff was made on September 7, 2001. This representation was made just five days prior to its rejection by the [siting council], although correspondence between PDC-E1 Paso and the plaintiff indicates that this land was identified on a map dated April 26, 2001, and presumably submitted to the [siting council].”
Free access — add to your briefcase to read the full text and ask questions with AI
Opinion
GRUENDEL, J.
In this contract interpretation action, the plaintiff, Nipmuc Properties, LLC, appeals from the judgment of the trial court denying its claim for a declaratory judgment against the defendants, PDC-E1 Paso Meriden, LLC (PDC-E1 Paso), Meriden Gas Turbines, LLC (Meriden Gas Turbines), Thomas P. Cadden, trustee of the 1998 Real Estate Trust, and the city of Meriden (Meriden), for the delivery of a lease held in escrow. On appeal, the plaintiff claims that the court improperly construed the contract to include provisions not agreed to by the parties and made findings that were unsupported by the record.
We affirm the judgment of the trial court.
The record reveals the following relevant facts as set forth by the court in its memorandum of decision. “The plaintiff held title to a parcel of land comprised of approximately 845 acres along the Metacomet ridgeline in . . . Meriden and Berlin. Due to the size and nature of the parcel, as well as its proximity to the Algonquin gas pipeline, the land became the subject of a proposal to build a 544 megawatt gas fired electric generation facility in the late 1990s, shortly after [the General
Assembly] enacted legislation deregulating the generation of electric power. In furtherance of this proposal, the plaintiff entered into a contract with Summitwood [Development, LLC, (Summitwood)]. Pursuant to this contract, Summitwood obtained the exclusive right to purchase the property. Summitwood then entered into an agreement to sell the land to PDC-E1 Paso. PDC-E1 Paso then initiated the process to obtain permits necessary to build an electric generation facility on this property, including a certificate of environmental compatibility and public need issued by the [Connecticut siting council (siting council)], pursuant to General Statutes § 16-50g et seq. All of the parties to this action understood that the construction of such an electric generation facility involved an extensive permitting process and was ultimately subject to the approval of the [siting council].
“The original purchase and sale agreement called for the buyer, PDC-E1 Paso, to return thirty acres of the 845 acre parcel to Summitwood after the closing. The intent was for Summitwood to retain this property on behalf of, and for development by the plaintiff, the original owner of the 845 acre parcel. The precise location of the thirty acres was to be determined by the parties at a future date.
“PDC-E1 Paso was unable to perform its contract to purchase the land from Summitwood, which required closing on the title to the property no later than December 31, 2000. PDC-E1 Paso was unable to perform the contract in a timely manner primarily because its gas turbine manufacturer could not supply the necessary gas turbines to power the electric generation facility. This problem required a significant change in the design of the facility. All of the parties agreed that this design change required the further consideration and approval by the [siting council].
“With the understanding that PDC-E1 Paso would default under the contract if it failed to close by December 31, 2000, the parties negotiated an amendment to the purchase and sale agreement, dated December 21, 2000 (amendment). The parties, through their representatives, further memorialized their understanding in a letter dated December 21,2000 (letter).
The interpretation of the language of these full exhibits is of critical importance to the determination of the rights and obligations of the parties to this action.
“Pursuant to the amendment, the parties generally agreed to extend the closing date to January 10, 2001. If the closing occurred on or before this date, the purchase price of $12 million would be reduced by $500,000. The amendment also provided that PDC-E1 Paso would lease approximately fifty-two acres of the 845 acre parcel back to Summitwood on behalf of the plaintiff. The lease of the fifty-two acre parcel was for a period of ninety-nine years with the possibility of extension for an additional ninety-nine years. This long-term lease of the fifty-two acres replaced the provision in the original agreement in which Summitwood had the right to retain thirty acres on behalf of the plaintiff. None of the parties dispute these provisions in the amendment to the agreement.
“This vigorously negotiated amendment further provided that the lease would be placed in escrow pending
the outcome of [siting council] approval. The specific language of § 2 (a) of the amendment provides that ‘[t]he Escrow Agent shall deliver the Lease to Sum-mitwood upon the approval of the [siting council] of the Buyer’s application to amend the decision and order issued by the [siting council] for the Power Plant described in the Purchase Agreement.’ . . .
“In addition to the amendment dated December 21, 2000, the parties further memorialized their agreement in a letter, also dated December 21, 2000. The letter states that ‘notwithstanding anything contained in the agreement to the contrary, in the event of a denial by the [siting council] of PDC-E1 Paso[’s] . . . application for approval of the transactions described in Section 2 (a) of the Amendment, the undersigned shall pay to Summitwood the additional sum of Seven Hundred Sixty Thousand ($760,000) Dollars.’ Section 2 (a) of the amendment primarily describes the fifty-two acre leaseback agreement, the escrow and the permitted uses of the leasehold property by Summitwood. The letter also describes two circumstances under which the $760,000 payment would not be due to Sum-mitwood: (1) if the siting council ‘approves the transactions described in Section 2 (a) of the Amendment,’ or (2) ‘if no closing occurs.’ . . .
“On January 10, 2001, PDC-E1 Paso assigned all of its rights and obligations under the amended purchase and sale agreement to [Meriden Gas Turbines]. On the same day, [Meriden Gas Turbines] closed on the 845 acre parcel. The [Meriden Gas Turbines] deed indicates that its title is subject to the fifty-two acre lease held in escrow. The lease, however, was not recorded at that time.
“Subsequently, on September 12, 2001, the [siting council] approved the proposed changes to the electric generation facility but rejected the proposed leaseback
of fifty-two acres to Summitwood. Instead, the [siting council] directed that title to the fifty-two acres be donated to Meriden.
Despite several public hearings and numerous public records concerning the application for the project, covering the span of several years, the first specific request made to the [siting council] for approval of land to be retained by the plaintiff was made on September 7, 2001. This representation was made just five days prior to its rejection by the [siting council], although correspondence between PDC-E1 Paso and the plaintiff indicates that this land was identified on a map dated April 26, 2001, and presumably submitted to the [siting council].”
On April 25, 2003, the plaintiff filed an amended complaint, in which it requested that the court “[determine and enter judgment declaring that the [fifty-two acre lease] is valid and in effect . . . .’’In addition, it requested that Cadden be directed to deliver the lease, and that the court “[e]nter such further orders and relief as may be necessary and just.” On June 27, 2003, PDC-E1 Paso filed an answer to the plaintiffs amended complaint, and on July 2, 2003, Meriden Gas Turbines filed a separate answer, which included special defenses and a counterclaim.
Evidence was presented at a trial to
the court on December 2 and 17,2004, at the conclusion of which the court ordered the simultaneous filing of posttrial briefs.
Final arguments were heard on July 15, 2005, and the court filed a memorandum of decision on August 11, 2005, denying the plaintiffs claim for a declaratory ruling. The court found in favor of the defendants on their first special defense after concluding that the condition precedent for delivery of the lease had not been met. This appeal followed.
The plaintiff contends that the factual findings on which the court relied in rejecting its declaratory judgment action were clearly erroneous. “Whether a contract has been breached ordinarily is a question of fact, subject to the clearly erroneous standard of review.”
De La Concha of Hartford, Inc.
v.
Aetna Life Ins. Co.,
269 Conn. 424, 431 n.5, 849 A.2d 382 (2004). Accordingly, “[t]o the extent that the trial court has made findings of fact, our review is limited to deciding whether such findings were clearly erroneous. ... A finding of fact is clearly erroneous when there is no evidence in the record to support it ... or when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed. ... In making this determination, every reasonable presumption must be given in favor of the trial court’s ruling.” (Citation omitted; internal quotation marks omitted.)
Maharishi School of Vedic Sciences, Inc. (Connecticut)
v.
Connecticut Constitution Associates Ltd. Partnership,
260 Conn. 598, 605, 799 A.2d 1027 (2002).
The plaintiff claims that the court improperly construed the contract to include provisions to which the
parties had not agreed. Specifically, it claims that it did not agree that the retained leasehold interest of fifty-two acres was subject to siting council approval. We are not persuaded.
“A contract must be construed to effectuate the intent of the parties, which is determined from the language used interpreted in the light of the situation of the parties and the circumstances connected with the transaction. . . . [T]he intent of the parties is to be ascertained by a fair and reasonable construction of the written words and . . . the language used must be accorded its common, natural, and ordinary meaning and usage where it can be sensibly applied to the subject matter of the contract. . . . Where the language of the contract is clear and unambiguous, the contract is to be given effect according to its terms. A court will not torture words to import ambiguity where the ordinary meaning leaves no room for ambiguity .... Similarly, any ambiguity in a contract must emanate from the language used in the contract rather than from one party’s subjective perception of the terms.” (Internal quotation marks omitted.)
Tallmadge Bros., Inc.
v.
Iroquois Gas Transmission System, L.P.,
252 Conn. 479, 498, 746 A.2d 1277 (2000).
Because the parties to this action were sophisticated business entities, represented by counsel throughout the negotiating process, the court concluded that if the contract had been clearer regarding the result of a bifurcated decision by the siting council, the case would have been akin to
Tallmadge Bros., Inc.,
in which a presumption of definitiveness of the contract was raised. The court in this case stated in its memorandum of decision: “The question here is whether the parties tied the question of the delivery of the lease to its approval by the [siting council]. In this case, the intensive negotiations of the parties led to language that could have been more clearly expressed.
Neither side was successful in succinctly stating the specific result of a denial of the lease by the [siting council]. . . . Nonetheless, the court finds the letter to be most instructive on the question before the court.”
The amendment considered only the approval of the application and lease. Section 2 (a) provides in relevant part: “The Escrow Agent shall deliver the Lease to Sum-mitwood
upon the approval
by the [siting council] of the Buyer’s application to amend the decision and order issued by the [siting council] for the Power Plant described in the Purchase Agreement.” (Emphasis added.) Although the plaintiff argues that it never agreed that the leasehold interest was subject to siting council approval, the concurrently written letter signed by all parties
belies the plaintiffs contention. The letter, “notwithstanding anything contained in the Agreement to the contrary,” directly addressed the possibility of the siting council’s
denial
of PDC-E1 Paso’s application. Upon such occurrence, it confirmed that the defendants “shall pay to Summitwood the additional sum of Seven Hundred Sixty Thousand ($760,000) Dollars.”
The letter continues by specifying that “[n]o additional sums shall be due to Summitwood if the [siting council] approves the transactions described in Section 2 (a) of the Amendment or if no Closing occurs.” Because the amendment specifically addressed the fifty-two acres that would be held in escrow for delivery
to Summitwood, the letter’s reference to “the transactions described in Section 2 (a) of the Amendment” undoubtedly included the lease. As the court noted, “[ujnder either scenario [under which the $760,000 would not be due], Summitwood and the plaintiff would retain an ownership interest in the land in question ”
The plaintiff cites
Tallmadge Bros., Inc.,
for the well settled principle that “[although parties might prefer to have the court decide the plain effect of their contract contrary to the agreement,
it is not within its power to make a new and different agreement . . .
.” (Emphasis in original; internal quotation marks omitted.)
Tallmadge Bros., Inc.
v.
Iroquois Gas Transmission System, L.P.,
supra, 252 Conn. 506. In this case, however, the letter was signed by all parties, and the court found that “[credible evidence was presented to the court that Joseph F. Carabetta, a principal of the plaintiff and agent for Summitwood, clearly understood that the fifty-two acre lease required [siting council] approval. . . . Credible evidence was also presented to the court that Carabetta understood that Meriden’s support for the fifty-two acre lease was essential for [siting council] approval and that he personally undertook that responsibility.”
We decline to revisit the
court’s credibility determinations. See
Mattson
v.
Mattson,
74 Conn. App. 242, 246, 811 A.2d 256 (2002). A thorough review of the record supports the court’s conclusion that approval by the siting council was a condition precedent to the delivery of the lease, and the court’s findings of fact in arriving at that conclusion were not clearly erroneous.
The judgment is affirmed.
In this opinion the other judges concurred.