NikSoft Systems Corp.

CourtArmed Services Board of Contract Appeals
DecidedOctober 2, 2024
Docket63423-ADR
StatusPublished

This text of NikSoft Systems Corp. (NikSoft Systems Corp.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NikSoft Systems Corp., (asbca 2024).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) NikSoft Systems Corp. ) ASBCA No. 63423-ADR ) Under Contract No. FA8771-17-F-0017 )

APPEARANCES FOR THE APPELLANT: Kristen L. Loesch, Esq. Josh S. Cergas, Esq. Praemia Law, PLLC Reston, VA

APPEARANCE FOR THE GOVERNMENT: Caryl A. Potter III, Esq. Air Force Deputy Chief Trial Attorney

SUMMARY BINDING DECISION BY ADMINISTRATIVE JUDGE SMITH

The parties requested that entitlement in this appeal be decided by Alternative Dispute Resolution (ADR) using a one-judge summary proceeding with a binding decision. We approved the request along with the May 20, 2024, ADR agreement. Per that agreement this “decision [is] final, conclusive, not subject to reconsideration or appeal, and may not be set aside, except for fraud.” Similarly, this decision has no value as precedent and cannot be cited in any other proceeding. We have reviewed the entire record and the two ADR briefs from each party. We find no entitlement and deny the appeal.

SUMMARY OF FACTUAL FINDINGS

Appellant (NikSoft) was awarded a contract for “life cycle sustainment” (the sustainment work) of respondent United States Air Force’s (USAF’s) Cargo Movement Operations System (CMOS), which is an IT system that, as its name indicates, helps coordinate USAF’s movement of cargo. After NikSoft had earned over $8.3 million of the contract’s $9.4 million total value, USAF changed its future plans with a command directive to migrate CMOS to a cloud-based IT environment (the migration work). Once given the task to migrate CMOS, there was considerable discussion within USAF and between USAF and NikSoft regarding how the migration work would be accomplished.

NikSoft asserted that the migration work was outside the scope of its sustainment contract and offered to negotiate an added-cost change order to perform the work. USAF considered whether the migration work was within the scope (and cost) of the sustainment contract but ultimately agreed that the migration work was outside NikSoft’s scope. After more consideration, USAF determined that it could not have NikSoft perform the migration work either within the bounds of the sustainment contract or as a change order. Without either of those options, USAF terminated of NikSoft’s contract for convenience and the migration work was performed by a different contractor, Ignite. NikSoft’s termination settlement was bilaterally resolved for an additional payment of $46,188.58 and is not disputed in this appeal. The termination settlement reserved NikSoft’s right to pursue this claim for lost profit of $629,576.16.

NikSoft claims bad faith by USAF when it “acted to harm NikSoft through various means and ultimately forced an early end to the Contract on pretextual grounds.” NikSoft asserts that a patchwork of USAF personnel independently, or in cahoots, terminated Niksoft’s sustainment contract in order to award the migration work to Ignite. NikSoft alleges that USAF illicitly removed the migration work from the Small Business Administration’s (SBA) 8(a) program. Niksoft also argues that USAF’s “satisfactory” CPARS rating of NikSoft, which NikSoft characterizes as “negative”, was also bad faith.

According to NikSoft, these bad acts were perpetrated for various reasons, some explained in conclusory fashion by NikSoft and some not explained at all. Most prominently, NikSoft argues that USAF decided (for a reason that NikSoft does not explain despite its many allegations regarding purported motivations of USAF personnel or groups) to terminate NikSoft’s contract as “punishment” and “retaliation” against NikSoft for its position that the migration work was outside the scope of the sustainment contract – a position that USAF eventually agreed with. Another alleged reason for terminating NikSoft was to steer the migration work to the contracting specialist’s (COR’s) “close friend’s company, Ignite.” To support its numerous allegations of bad faith, NikSoft relies a lot upon two affidavits from its own personnel. NikSoft also cites some internal USAF documents where USAF personnel debated and then decided on its final courses of action, including when and how to do the migration work, whether NikSoft’s contract could or should be used, the resulting termination for convenience, and the CPARS ratings.

As an example, to support NikSoft’s contention about the COR’s “very close personal friend” at Ignite, NikSoft cites only to a paragraph in its own affidavit where conclusory and trivial “facts” are depicted. These include that the COR and an Ignite employee were overly familiar and “referred to themselves using familial terms such as “family,” “brother,” “sister” and “father” and “daughter,”” and that they had “social lunches.”

2 SUMMARY OF CONCLUSIONS OF LAW

NikSoft correctly states that “the [US]AF is required to act in good faith and deal fairly with any contractor. Metcalf Constr. Co. v. United States, 742 F.3d 984, 990 (Fed. Cir. 2014); see FAR 1.602-2 (‘Contracting officers shall . . . [e]nsure that contractors receive impartial, fair, and equitable treatment.’).” But NikSoft does not even mention, much less argue how it meets, the high burden of clear and convincing evidence (or so-called “irrefragable proof”) for a claim of bad faith against the government. 1

USAF’s briefs do not address NikSoft’s many factual contentions and conclusory statements point-by-point, but simply argues globally that “NikSoft has failed to provide the required ‘clear and convincing’ evidence that the termination for convenience . . . was a bad-faith action by the government with specific intent to harm NikSoft.” USAF cites Exceed Resources, Inc., which reiterated long standing precedent on the standard of proof and noted that “a bad faith termination for convenience [is] ‘almost impossible to prove.’” ASBCA No. 61652, 20-1 BCA ¶ 37,634 at 182,720 (quoting 33 Nash & Cibinic Rep. NL ¶ 32, Contract Disputes Act Claims: Minimal Requirements, (June 2019)). We agree that the precedent regarding clear and convincing evidence, which is a particularly high burden, applies here. See Am-Pro Protective Agency, Inc. v. United States, 281 F.3d 1234, 1239-40 (Fed. Cir. 2002); Nexagen Networks, Inc., ASBCA No. 60641, 19-1 BCA ¶ 37,258 at 181,328 (citing SWR, Inc., ASBCA No. 56708, 15-1 BCA ¶ 35,832 at 175,222; William Green Constr. Co. v. United States, 477 F.2d 930, 936 (Ct. Cl. 1973)).

DECISION

Our review of the documents relied upon by NikSoft, and of the entire record whether cited or not, shows that all of USAF’s actions originated with the command directive to migrate CMOS, a decision which NikSoft does not allege was targeted at NikSoft or made in bad faith. After the migration decision, USAF’s contracting section was delegated the task of accomplishing it on a tight time schedule and that is where NikSoft focuses its claim. But the record consists largely of routine and unremarkable emails, meeting notes, data, and presentation slides — all aimed at the required migration of CMOS. In sum, the record shows a fairly typical institutional command and contract decision and implementation process. NikSoft’s termination for convenience was a rational consequence of the overall migration decision.

To be sure, some of the record documents show a degree of confusion and iterative decision-making, including disagreements as to what was contractually

1 The omission of the clear and convince evidence requirement is glaring, especially because it does not appear in the “standard of proof” section of NikSoft’s brief.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Am-Pro Protective Agency, Inc. v. United States
281 F.3d 1234 (Federal Circuit, 2002)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
William Green Construction Co. v. United States
477 F.2d 930 (Court of Claims, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
NikSoft Systems Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/niksoft-systems-corp-asbca-2024.