Nijel Young Versus Hard Rock Construction, L.L.C., Hard Rock Construction of Louisiana, L.L.C., and All South Consulting Engineers, L.L.C.

Louisiana Court of Appeal·Decided March 17, 2020·No. 19-CA-484·Unknown

Opinion

NIJEL YOUNG NO. 19-CA-484 VERSUS FIFTH CIRCUIT

HARD ROCK CONSTRUCTION, L.L.C., COURT OF APPEAL HARD ROCK CONSTRUCTION OF LOUISIANA, L.L.C., AND ALL SOUTH STATE OF LOUISIANA CONSULTING ENGINEERS, L.L.C.

ON APPEAL FROM THE FORTIETH JUDICIAL DISTRICT COURT PARISH OF ST. JOHN THE BAPTIST, STATE OF LOUISIANA NO. 68,583, DIVISION "C"

HONORABLE J. STERLING SNOWDY, JUDGE PRESIDING

March 17, 2020

JUDE G. GRAVOIS

JUDGE

Panel composed of Judges Susan M. Chehardy, Jude G. Gravois, and Stephen J. Windhorst

AFFIRMED JGG SMC SJW

COUNSEL FOR PLAINTIFF/APPELLANT, NIJEL YOUNG Harry E. Forst

COUNSEL FOR DEFENDANT/APPELLEE, ALL SOUTH CONSULTING ENGINEERS, L.L.C.

David K. Persons

GRAVOIS, J.

This case arises out of an accident at a construction site at East St. John High School, in LaPlace, Louisiana, owned by the St. John the Baptist Parish School Board. Plaintiff, Nijel Young, was injured when the walls of a trench in which he was laying drainage pipe collapsed. He sued both his employer, Hard Rock Construction LLC/Hard Rock Construction of Louisiana, LLC (“Hard Rock”), and All South Consulting Engineers, LLC, the engineering and construction management firm hired by the School Board to provide engineering and construction management services to the project.1 Ultimately, the trial court granted summary judgment in favor of All South, finding that no genuine issues of material fact existed as to All South’s non-liability to plaintiff under the explicit provisions of All South’s contract with the School Board, and that All South was entitled to judgment as a matter of law. This appeal followed. For the following reasons, we affirm.

FACTS AND PROCEDURAL HISTORY On the date of the accident, October 20, 2014, plaintiff was employed as a laborer by Hard Rock, the contractor, who had entered into a contract with the School Board to install sections of 48-inch underground drainage pipes at East St. John High School. The School Board also contracted with All South to provide engineering and construction management services at the construction site.2 All South’s construction manager for this job, Scott Greig, testified in his deposition that his job was observing the work of the contractor, and to make sure that the work proceeded according to the plans and specifications of the contract between Hard Rock and the School Board, as well as to monitor the construction’s

1 Hard Rock was dismissed from this tort suit after summary judgment was rendered in Hard Rock’s favor, finding that plaintiff’s exclusive remedy against Hard Rock was workers’ compensation. Thus, the remainder of this opinion will pertain to plaintiff’s case against All South.

2 The trial court’s reasons for judgment erroneously state that All South was hired by Hard Rock.

progress and the delivery and use of construction materials. Mr. Greig testified that All South’s job was to be present, but not in communication with the contractor unless they observed something not being done to standards or the contract specifications. Mr. Greig’s job duties also included overseeing All South’s inspectors at other jobsites.3 The onsite inspector for this particular site was Gerard Kelly, who reported to Mr. Greig and who had over 30 years’ experience in construction and around six years’ experience as an inspector. Because Mr. Greig had been at another site in the morning, he did not arrive at the East St. John site until the afternoon, at around 2:00 p.m., where Mr. Kelly had been present observing Hard Rock’s trench crew since the beginning of the work day. Mr. Kelly left shortly before the accident, after conferring with Mr. Greig about the work performed by the trench crew that day.

The accident which injured plaintiff occurred on the first or second day of work at the site at around 3:00 p.m. (witness testimony varied as to the exact time, but all agreed it was in the afternoon), where Hard Rock was installing 8-foot-long sections of 48-inch underground cement drainage pipes in a trench. Installation of the pipe sections involved digging a trench and preparing the bedding soil according to contract specifications on which the pipe would lay, and laying the pipe. Mr. Young was injured when the trench in which he was working caved in or collapsed.4

3 Though Mr. Greig was an engineer by education, he emphasized in his deposition that he was not licensed in Louisiana, nor was he the All South “engineer” referred to by plaintiff, and that he was not employed by All South to perform any engineering services on this job. The All South project engineer was Chris Sanchez. No All South witness identified Mr. Sanchez as being present on the subject site that day.

4 OSHA cited and fined Hard Rock for an OSHA violation regarding the trench following plaintiff’s injury. The OSHA notice of violation, found in the record, stated that the trench was at least 8 feet deep. It appears that the depth of the trench varied, though this fact is not material to the issue in this appeal.

Testimony indicated that the trench plans may not have been stamped by an engineer, but the record is unclear as to whether the trench was of sufficient depth for OSHA to require such an engineering stamp. This fact is also not material to the legal issue in this appeal.

According to plaintiff, Mr. Greig, and Mr. Kelly, earlier that day, George Gautreaux, who was Hard Rock’s crew foreman and whom Mr. Greig described as the “trench expert,” called “Carl,” Hard Rock’s owner, to request a metal “trench box,” because he felt that the shoring system being used by the crew to secure the trench from cave-ins was not adequate, as the crew had experienced minor cave-ins several times already that day.5 A trench box is a metal device with sides and lateral bracing used to shore the trench to protect the crew from cave-ins. The shoring system being used by the crew that day consisted of 2x12 or 2x10 oak boards driven into the sides of the trench with approximately 24 inches of space between them, all covered by black “geotechnical material,” described as looking similar to black garbage bags. According to Mr. Kelly and Mr. Greig, Carl visited the site at least once, and perhaps twice, after getting Mr. Gautreaux’s call, but after inspecting the trench did not approve a trench box and told the crew to get back to work without one.

Plaintiff and his father, Morris Young, who was also working on the same crew, testified in depositions that the trench had experienced other cave-ins that day, though none causing injury, which had prompted Mr. Gautreaux to call Carl. Plaintiff also testified in his deposition that an All South “engineer,” whom he did not name, had come over prior to the cave-in that injured plaintiff to inspect the trench and measure the distance between the boards. However, it is unclear who this person actually was.6 Mr. Greig, who testified in his deposition he was not the project engineer, said that while he did look at the boards in the trench, he did not

5 The cave-ins were also described as “clumps” of dirt falling or sloughing off into the trench.

Mr. Greig testified that he saw clumps of dirt filling in the bottom of the trench with some water accumulation.

6 Mr. Morris Young also briefly referred to an engineer being present at the site, along with other construction personnel that he could not identify. His reference to the engineer’s presence was not detailed and he did not describe him as measuring the distance between the boards.

take any measurements. Mr. Greig testified that he was present when the subject cave-in occurred and assisted in the crew’s efforts to free Mr. Young.

Free access — add to your briefcase to read the full text and ask questions with AI

Nijel Young Versus Hard Rock Construction, L.L.C., Hard Rock Construction of Louisiana, L.L.C., and All South Consulting Engineers, L.L.C., (La. Ct. App. 2020).

Nijel Young Versus Hard Rock Construction, L.L.C., Hard Rock Construction of Louisiana, L.L.C., and All South Consulting Engineers, L.L.C. (Nijel Young Versus Hard Rock Construction, L.L.C., Hard Rock Construction of Louisiana, L.L.C., and All South Consulting Engineers, L.L.C.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Crane v. Exxon Corp., USA
613 So. 2d 214 (Louisiana Court of Appeal, 1992)
Brewer v. J.B. Hunt Transport, Inc.
35 So. 3d 230 (Supreme Court of Louisiana, 2010)
Wooley v. Lucksinger
14 So. 3d 311 (Louisiana Court of Appeal, 2009)
Black v. Gorman-Rupp
791 So. 2d 793 (Louisiana Court of Appeal, 2001)
Brewer v. J.B. Hunt Transport, Inc.
9 So. 3d 932 (Louisiana Court of Appeal, 2009)
Taylor v. Voigtlander
833 So. 2d 1204 (Louisiana Court of Appeal, 2002)
Bujol v. Entergy Services, Inc.
922 So. 2d 1113 (Supreme Court of Louisiana, 2006)
Muller v. Carrier Corp.
984 So. 2d 883 (Louisiana Court of Appeal, 2008)
Harris v. Pizza Hut of Louisiana, Inc.
455 So. 2d 1364 (Supreme Court of Louisiana, 1984)
Yocum v. City of Minden
649 So. 2d 129 (Louisiana Court of Appeal, 1995)
Pizani v. Progressive Ins. Co.
719 So. 2d 1086 (Louisiana Court of Appeal, 1998)
Hebert v. Rapides Parish Police Jury
974 So. 2d 635 (Supreme Court of Louisiana, 2008)
Socorro v. City of New Orleans
579 So. 2d 931 (Supreme Court of Louisiana, 1991)
Day v. National US Radiator Corporation
128 So. 2d 660 (Supreme Court of Louisiana, 1961)
Irwin v. Hunnewell
21 So. 2d 485 (Supreme Court of Louisiana, 1945)
Lomark, Inc. v. Lavignebaker Petroleum, L.L.C.
110 So. 3d 1107 (Louisiana Court of Appeal, 2013)
Sarasino v. State ex rel. Department of Public Safety & Corrections
215 So. 3d 923 (Louisiana Court of Appeal, 2017)
Plaisance v. Jefferson Parish Sch. Bd.
252 So. 3d 996 (Louisiana Court of Appeal, 2018)
Azaretta v. Manalla
768 So. 2d 179 (Louisiana Court of Appeal, 2000)
Enterprise v. American Manufactures Mutual Insurance Co.
847 So. 2d 717 (Louisiana Court of Appeal, 2003)