Nida v. Echols

31 F. Supp. 2d 1358, 1998 U.S. Dist. LEXIS 20710, 1998 WL 939332
CourtDistrict Court, N.D. Georgia
DecidedSeptember 15, 1998
Docket1:97-cv-00350
StatusPublished
Cited by5 cases

This text of 31 F. Supp. 2d 1358 (Nida v. Echols) is published on Counsel Stack Legal Research, covering District Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nida v. Echols, 31 F. Supp. 2d 1358, 1998 U.S. Dist. LEXIS 20710, 1998 WL 939332 (N.D. Ga. 1998).

Opinion

ORDER

CARNES, District Judge.

This case is presently before the Court on defendants S. Cleve Ray, Charlene Echols and BellSouth Telecommunications, Inc.’s (hereinafter “BellSouth”) Motion for Summary Judgment [12] and Motion to Strike the Expert Affidavit of Roger A. Roemmich [16]. After reviewing the record and the arguments of the parties, the Court concludes that defendants’ Motion for Summary Judgment [12] should be GRANTED IN PART AND DENIED IN PART and Motion *1361 to Strike the Expert Affidavit of Roger A. Roemmieh [16] should be GRANTED.

BACKGROUND

In August of 1995, plaintiffs in this case, Ruth Cummings, Norman Conner, John Lin-ster and Ronald Nida, were all employees of defendant BellSouth, and were all over 40 years old. Conner had worked for BellSouth since May 12,1969, Cummings since July 13, 1974, Linster since November 1, 1976 and Nida since August 13, 1973. (See Defs.’ Statement of Material Facts [12] at ¶ 24.) On August 30, 1995, each plaintiff was fired for “misconduct and dishonesty including misrepresenting work schedules and falsification of records.” (Id. at ¶ 22.)

In March and April of 1995, plaintiffs Conner, Linster and Nida worked as specialists in BellSouth’s Network Management Center (hereinafter “the Center”). (Id. at ¶ 5.) As specialists, plaintiffs reported to Cleve Ray, the manager of the Center. (Id. at ¶ 2.) Ray had the responsibility of running the Center on a day-to-day basis. (Id.) Ray’s supervisor was Charlene Echols, a director for Bell-South, who in turn reported to William' Stacy, a regional general manager at the time in question. (Id.)

When Ray first began to manage the Center it did not operate on a 24-hour basis because BellSouth did not employ enough people to cover such a schedule. (Id. at ¶ 6.) When the Center was not operating on a 24-hour basis, specialists worked a four-day week, ten hours per day. (Id.) Over time, the Center added employees and began to operate on a twenty-four hour basis. (Id.)

In 1995 the Center was operating on a 24-hour basis. (Id.) While on such a schedule, specialists worked either of three separate eight-hour shifts, denominated as the day, evening and night shifts. (Id.) Ordinarily, the day shift ran from 8:00 am. to 4:00 p.m., the evening shift ran from 4:00 p.m. to 12:00 a.m., and the night shift ran from 12:00 am. to 8:00 a.m. (Id. at ¶ 4.) Each specialist routinely worked a five-day week, eight hours per day. 1 (Id. at ¶ 6.)

At the beginning of 1995, there were four specialists covering the evening shift at the Center. At some point prior to March of 1995, the evening shift lost one employee and only plaintiffs Conner, Linster and Nida were left to cover the five-day evening shift. These three individuals did not want to work a five day week. Instead, they desired to work a four-day, ten-hour shift schedule, as they had done in the past. (See, e.g., Nida Dep. at 143.) Plaintiffs allege that Ray was aware that they were working this altered schedule and that he acquiesced in this arrangement around the beginning of April. (See Linster Dep. at 99-100; Nida Dep. at 112; Conner Dep. at 94.)

Defendants vigorously deny that Ray gave plaintiffs permission to work anything other than a five-day schedule. Rather, defendants allege that Ray denied plaintiffs’ request to work a four-day schedule and that plaintiffs then conspired among themselves to work a four-day schedule and hide that fact from Ray. (See Defs.’ Statement of Material Facts [12] at ¶ 10-11.) Indeed, defendants submit signed statements from each of the plaintiffs in which plaintiffs signed as true and correct the fact that they had changed their schedule to a four-day schedule without Ray’s permission. (Id. at ¶ 11-12.)

In May of 1995, plaintiff Linster transferred to another work group and was replaced by plaintiff Cummings. (See Defs.’ Statement of Material Facts [12] at ¶ 5.) When Cummings went to the evening shift, Conner and Nida explained to her that they were working a four-day week and that they had Ray’s permission to work this schedule. (See Cummings Dep. at 29-31.)

In July of 1995, BellSouth’s ombudsman line 2 received a call complaining that plaintiff Nida was not at the Center when he was scheduled to work. (See Defs.’ Statement of Material Facts [12] at ¶ 8.) Specifically, the complainant alleged that Nida was flying his airplane when he was supposed to be at work. (See Fielder Dep. at 9.) Gary Fielder, *1362 a manager in BellSouth’s security department, responded to the ombudsman complaint and spoke with Nida on July 20, 1995. (See Defs.’ Statement of Material Facts [12] at ¶ 8.) This conversation, along with Fielder’s independent investigation, caused Fielder to come to the conclusion that the complaint concerning Nida was unsubstantiated. (Id.) During the course of this investigation, however, Nida made a statement that caused Fielder concern. Nida, in an apparent attempt to defend himself, told Fielder that “three co-workers had done the same thing he had done, that they were scheduled a five-day week and were working a four-day week.” (Fielder Dep. at 12; see also Defs.’ Statement of Material Facts [12] at ¶ 9.)

The sequence of events that followed this revelation and the investigation to which it led is not entirely clear. Apparently, Ray was informed of Nida’s statement, passed this information on to Echols (see Ray Dep. at 29), and then Echols requested that Fielder investigate whether plaintiffs were working their posted schedule. (See Defs.’ Mot. for Summ. J. [12] at Ex. 2, Ray Aff. ¶ 9.) Fielder then spoke with each of the plaintiffs on July 26, and with Ray, concerning plaintiffs’ schedule. (See Fielder Dep. at 13, 22-24.) Ray informed Fielder that he had not given plaintiffs permission to work anything other than a five-day week (see Fielder Dep. at 22), and- each plaintiff signed as true and correct a statement written by Fielder which stated that the four plaintiffs had worked a four-day schedule without permission from Ray. 3 (See Fielder Dep. at Exs. 1, 2, 3, 4.)

Plaintiffs now claim that they had Ray’s tacit permission to work a four-day week and that their schedule was not hidden from him. (See, e.g., Nida Dep. at 136-37 (“We didn’t hide it [their four-day schedule] from him, sir. We told him that we had our own schedule.”); see also supra, at 1361.) Plaintiffs Linster and Nida state that they signed the statements prepared by Fielder because he told them that it would be in their best interests to do so. (See Linster Dep. at 91; Nida Dep.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lee v. Necco, LLC
S.D. Georgia, 2025
H&R BLOCK EASTERN ENTERPRISES, INC. v. Morris
606 F.3d 1285 (Eleventh Circuit, 2010)
Wolf v. Ramsey
253 F. Supp. 2d 1323 (N.D. Georgia, 2003)
Gullatte v. Westpoint Stevens, Inc.
100 F. Supp. 2d 1315 (M.D. Alabama, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
31 F. Supp. 2d 1358, 1998 U.S. Dist. LEXIS 20710, 1998 WL 939332, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nida-v-echols-gand-1998.