Nico Industries, Inc. v. Steel Form Contractors, Inc.

625 So. 2d 1252, 1993 Fla. App. LEXIS 9185, 1993 WL 349923
CourtDistrict Court of Appeal of Florida
DecidedSeptember 15, 1993
Docket92-1550, 92-2641 & 92-3407
StatusPublished
Cited by8 cases

This text of 625 So. 2d 1252 (Nico Industries, Inc. v. Steel Form Contractors, Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nico Industries, Inc. v. Steel Form Contractors, Inc., 625 So. 2d 1252, 1993 Fla. App. LEXIS 9185, 1993 WL 349923 (Fla. Ct. App. 1993).

Opinion

625 So.2d 1252 (1993)

NICO INDUSTRIES, INC. and General Insurance Company of America, Appellants,
v.
STEEL FORM CONTRACTORS, INC., Appellee.

Nos. 92-1550, 92-2641 & 92-3407.

District Court of Appeal of Florida, Fourth District.

September 15, 1993.
Rehearing Denied November 12, 1993.

Patrick A. Thompson of Smith, Currie & Hancock, Atlanta, GA, for appellants.

Marjorie Gadarian Graham of Marjorie Gadarian Graham, P.A., and Jerome R. Craft of Craft & Craft, West Palm Beach, for appellee.

KLEIN, Judge.

Appellants, a general contractor and its bonding company, appeal a final judgment for damages entered in favor of a subcontractor for work performed on a construction project. They argue that the sub did not present the kind of evidence necessary to recover damages for breach of a partially performed construction contract. We agree and reverse.[1]

The sub acknowledges that the measure of damages for breach of a partially performed construction contract is, "either quantum meruit or the contractor's lost profit together with the reasonable cost of labor and materials incurred in good faith in the course of partial performance of the contract." Brooks v. Holsombach, 525 So.2d 910, 911 (Fla. 4th DCA 1988). See also, Marshall Construction, Ltd. v. Coastal Sheet Metal & Roofing, Inc., 569 So.2d 845 (Fla. 1st DCA 1990).

The sub presented the testimony of two of its officers; however, their testimony was based on the percentage of work completed. Percentage of completion is not competent evidence to prove damages for breach of a partially performed construction contract. First Atlantic Building Corp. v. Neubauer Construction Co., 352 So.2d 103 (Fla. 4th DCA 1977). The sub also relies on an exhibit which is a payment application form prepared by the contractor in order to receive *1253 payment from the owner. This exhibit suffers from the same deficiency as the testimony of the officers because it is also based on percentage of completion.

The sub also argues that a deposition of an engineer supplies the proof; however, the engineer gave his opinion in response to being asked the "market value of that product." Moreover, his opinion only related to a portion of the work performed and did not include a deduction for items which he admitted were proper back charges. Nor did the court utilize the opinion of the expert in calculating the sub's recovery. As the sub recognizes, the court arrived at the amount due the sub by subtracting the cost to complete incomplete work from the contract price.

We therefore conclude that, there having been no proof of either quantum meruit or the reasonable cost of labor and materials plus lost profit, judgment should be entered for defendants.

Reversed.

ANSTEAD and HERSEY, JJ., concur.

NOTES

[1] We consolidate the appeals from the orders awarding attorney's fees and costs and reverse those also.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Levy v. Ben-Shmuel
255 So. 3d 493 (District Court of Appeal of Florida, 2018)
Plumbing Service Co. v. Progressive Plumbing, Inc.
46 So. 3d 144 (District Court of Appeal of Florida, 2010)
Emerald Pointe Prop. v. Commercial Const.
978 So. 2d 873 (District Court of Appeal of Florida, 2008)
Puya v. SUPERIOR POOLS, SPAS & WATERFALLS
902 So. 2d 973 (District Court of Appeal of Florida, 2005)
Levitt-Ansca Towne Park Partnership v. Smith & Co., Inc.
873 So. 2d 392 (District Court of Appeal of Florida, 2004)
Renaissance Stoneworks, Inc. v. Ocean Beach 167, Inc.
744 So. 2d 522 (District Court of Appeal of Florida, 1999)
Teca, Inc. v. WM-Tab, Inc.
726 So. 2d 828 (District Court of Appeal of Florida, 1999)
Coastal Development & Construction I, Inc. v. T.P. Trucking & Excavation
708 So. 2d 1017 (District Court of Appeal of Florida, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
625 So. 2d 1252, 1993 Fla. App. LEXIS 9185, 1993 WL 349923, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nico-industries-inc-v-steel-form-contractors-inc-fladistctapp-1993.