This text of 873 So. 2d 392 (Levitt-Ansca Towne Park Partnership v. Smith & Co., Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Levitt-Ansca Towne Park Partnership v. Smith & Co., Inc., 873 So. 2d 392, 2004 WL 784491 (Fla. Ct. App. 2004).

Opinion

873 So.2d 392 (2004)

LEVITT-ANSCA TOWNE PARK PARTNERSHIP, Bellagio by Levitt Homes, Inc., Bellagio by Ansca, Inc., a/k/a Bellaggio by Ansca Homes Inc., and Liberty Mutual Insurance Company, Appellants,
v.
SMITH & COMPANY, INC. and American Home Assurance Company, Appellees.

No. 4D02-2572.

District Court of Appeal of Florida, Fourth District.

April 14, 2004.
Rehearing Denied June 8, 2004.

*394 William R. Scherer and James F. Carroll of Conrad & Scherer, LLP, Fort Lauderdale, for appellants.

Mary Piccard Vance of Vezina, Lawrence & Piscitelli, Tallahassee, and Joseph W. Lawrence, II, Michael A. Piscitelli of Vezina, Lawrence & Piscitelli, P.A., Fort Lauderdale, for appellee, Smith & Company, Inc., Robert E. Morris and David Scott Knight of Robert E. Morris, P.A., Tampa, for appellee American Home Assurance Company.

MAY, J.

A contract between a developer and a contractor hired to perform earthwork ran amuck, resulting in litigation. The contractor filed a complaint against the developer and Liberty Mutual Insurance Company. The developer counter-claimed. The jury returned a verdict in favor of the contractor and awarded damages. It is from the Amended Final Judgment entered following post-trial motions that the developer and Liberty Mutual appeal. The developer argues that the trial court erred in denying its motion for new trial. We agree and reverse.

The developer solicited a price from the contractor for earthwork to be performed at the construction site of Bellagio. The contractor initially submitted a proposal of $4,000,000, which contained a 50% credit to the developer for each cubic yard of surplus fill that the contractor removed from the site. The developer rejected the proposal and requested a flat price to perform the work. The contractor submitted a new price of $2,000,000, anticipating that it would also receive 1.6 million cubic yards of surplus fill.

The contract, however, was silent on the quantity of surplus fill. An exhibit attached to the contract included a paragraph which provided that "[a]ll surplus fill that is not needed for the Project is the property of the Contractor." The contractor intended to use the surplus fill in the reconstruction of U.S. 441 under a contract with the Department of Transportation and other projects. It anticipated selling any remaining surplus fill.

The contractor immediately began hauling fill from the site for use on the U.S. 441 project. According to the developer, the contractor was taking too much fill from the site and not finishing the work on time. According to the contractor, the developer was asking it to perform work not included in the contract price and would not approve change orders submitted by the contractor.

By the time the developer terminated the contractor, a little over 50% of the earthwork had been performed. At that time, the contractor had already removed 571,781 cubic yards of fill from the site with an estimated worth in excess of $1.5 million. The developer paid the contractor *395 $342,859, but invoices totaling $714,903.26 remained outstanding.

Of the many disagreements that arose between the developer and the contractor, the most significant dispute concerned the contractor's removal of large quantities of fill early in the project. This evolved into another dispute over who was responsible for obtaining special permitting required when more than 10% of the land was excavated. In legal terms, the disputes boiled down to who breached the contract.

The contractor sued the developer and requested the following damages.

Unpaid Invoices          $  714,903.36
Work Performed
(w/o payment)            $  352,263.72
Added Bond Premium       $   11,424.00
Idle Equipment           $  654,292.50
Un-funded Equipment
Mobilization             $   37,698.84
Anticipated Profit       $3,266,077.70
                         _____________
TOTAL                    $5,036,660.04

The developer claimed that the contractor breached the agreement, no amount of surplus fill had been guaranteed, and the contractor was required to deduct its costs from any anticipated lost profits. The jury found the developer in breach of the contract and awarded the contractor $2,959,638.54 in damages for the breach. This included a $714,903.36 lien for work performed, and $352,263.72 for work performed outside the parameters of the agreement based upon the theory of quantum meruit.

On appeal, the developer argues the damages exceed those permitted by law and are not supported by the evidence. The argument has many sub-parts, including the value of the surplus fill, the contractor's failure to account for its costs in determining lost profits, and the duplicitous nature of the damage awards. The developer seeks a reversal of the final judgment with directions to the trial court to enter a judgment in its favor. In the alternative, it seeks a new trial on all issues claiming the damages and breach issues are so intertwined they cannot be considered separately.

Although the contractor maintains that the evidence supports the damages awarded, at oral argument, it candidly admitted an inability to account for the jury's calculation of the precise amount awarded for the breach. We too are unable to justify the damages awarded in this case.

The proper measure of damages for breach of a partially performed construction contract [is] "either quantum meruit or the contractor's lost profit together with the reasonable cost of labor and materials incurred in good faith in the course of partial performance of the contract."
Teca, Inc. v. WM-TAB, Inc., 726 So.2d 828, 830 (Fla. 4th DCA 1999) (quoting Nico Indus., Inc. v. Steel Form Contractors, Inc., 625 So.2d 1252, 1252 (Fla. 4th DCA 1993). See also Frenz Enters., Inc. v. Port Everglades, 746 So.2d 498 (Fla. 4th DCA 1999) (discussing burden of proof for lost profits). See also Sampley Enters., Inc. v. Laurilla, 404 So.2d 841 (Fla. 5th DCA 1981)) (reversing damage award because court awarded out of pocket expenses when lost profits was the proper measure of damages).

In this case, however, the contractor sought both damages on the contract and an additional sum for work performed outside the contract under the theory of quantum meruit. We hold that because the contract provided the method for obtaining payment for additional work, the contractor could not seek equitable relief for additional work at the same time it sought legal relief in the form of lost profits for the breach. Sundie v. Lindsay, 166 So.2d 152 (Fla. 3d DCA 1964) ("It is incorrect for evidence to be introduced as to *396 both methods, the injured party must make an election in regard to which method he seeks to recover, and pursue that method only."); Ballard v. Krause, 248 So.2d 233, 235 (Fla. 4th DCA 1971) (Quantum meruit "is not available to a contractor if the contractor is suing on the contract."). See also Corn v. Greco, 694 So.2d 833 (Fla. 2d DCA 1997). Therefore, on remand the contractor must elect between legal damages on the contract and equitable relief under quantum meruit.

We now turn our attention to the jury's determination of lost profit damages under the contract. Lost profits must be proven "with a reasonable degree of certainty" before they are recoverable. Shadow Lakes, Inc. v. Cudlipp Constr. and Dev. Co., 658 So.2d 116, 117 (Fla. 2d DCA 1995). "The mind of a prudent impartial person should be satisfied that the damages are not the result of speculation or conjecture." Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Standard Jury Instructions—Contract & Business Cases
116 So. 3d 284 (Supreme Court of Florida, 2013)
Devon Medical, Inc. v. Ryvmed Medical, Inc.
60 So. 3d 1125 (District Court of Appeal of Florida, 2011)
Vance v. Gallagher
280 F. App'x 533 (Seventh Circuit, 2008)
Aronowitz v. Health-Chem Corp.
513 F.3d 1229 (Eleventh Circuit, 2008)
Bodygear Activewear, Inc. v. Counter Intelligence Services
946 So. 2d 1148 (District Court of Appeal of Florida, 2006)
Meadows v. English, McCaughan & O'Bryan, P.A.
909 So. 2d 926 (District Court of Appeal of Florida, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
873 So. 2d 392, 2004 WL 784491, Counsel Stack Legal Research, https://law.counselstack.com/opinion/levitt-ansca-towne-park-partnership-v-smith-co-inc-fladistctapp-2004.