Nextel Communications of the Mid-Atlantic, Inc. v. Manchester-By-The-Sea

115 F. Supp. 2d 65, 2000 U.S. Dist. LEXIS 17763, 2000 WL 1289494
CourtDistrict Court, D. Massachusetts
DecidedAugust 23, 2000
DocketC.A. 00-10102
StatusPublished
Cited by7 cases

This text of 115 F. Supp. 2d 65 (Nextel Communications of the Mid-Atlantic, Inc. v. Manchester-By-The-Sea) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nextel Communications of the Mid-Atlantic, Inc. v. Manchester-By-The-Sea, 115 F. Supp. 2d 65, 2000 U.S. Dist. LEXIS 17763, 2000 WL 1289494 (D. Mass. 2000).

Opinion

MEMORANDUM AND ORDER

WOLF, District Judge.

This memorandum is based upon the transcript of the decision rendered orally on August 16, 2000, allowing the plaintiffs motion for summary judgment. This memorandum adds citations, deletes some colloquy, and clarifies some language.

J¡: :¡: „ ;H ‡

I. SUMMARY

The plaintiff, Nextel Communications of the Mid-Atlantic, Inc. (“Nextel”), has sued Manchester-By-The-Sea (“Manchester”) for violations of the Telecommunications Act of 1996 (the “TCA” or the “Act”). The Act, among other things, requires that the court hear and decide the case on an expedited basis. See 47 U.S.C. § 332(c)(7)(B)(v). The court has done so.

Nextel alleges that the Manchester Planning Board violated provisions of the *66 Act by refusing to grant a special permit for the construction of a telecommunications tower in a boatyard in Manchester Harbor. Among other things, Nextel asserts that Manchester violated 47 U.S.C. § 332(c)(7)(B)(iii) because the Planning Board’s decision to deny Nextel’s application for a special permit was not based on substantial evidence in the record.

The substantial evidence question is ordinarily resolved on the record before the court and no trial is required. See Town of Amherst v. Omnipoint Communications, 173 F.3d 9, 16 n. 7 (1st Cir.1999). The parties have agreed that it is appropriate to resolve this issue on the basis of the administrative record that was before the Planning Board. See Transcript of August 16, 2000 Hearing (“Tr.”) at 2-3.

For the reasons explained below, the court concludes that the Manchester Planning Board’s decision to deny Nextel’s special permit was not supported by substantial evidence. Therefore, Nextel’s motion for summary judgment is being allowed with regard to Count One of its Complaint. As a result, Manchester is being ordered to issue the permits necessary for the construction of an 80-foot tower that is 24 inches in diameter from top to bottom, as previously authorized by the Manchester Zoning Board of Appeals.

II. ANALYSIS

In TCA cases alleging violations of 47 U.S.C: § 332(c)(7)(B)(iii), the Court of Appeals for the First Circuit has instructed that it is appropriate to employ the substantial evidence standard that it recently described in Penobscot Air Services v. Federal Aviation Administration. See Town of Amherst, 173 F.3d at 16 (citing Penobscot Air Services v. Federal Aviation Administration, 164 F.3d 713, 718 (1st Cir.1999)). In Penobscot Air Services the First Circuit wrote:

[Substantial evidence review is conducted on the record considered as a whole. Substantial evidence is such relevant evidence as a reasonable mind might accept as adequate to support a conclusion. The reviewing court must take into account contradictory evidence in the record. But the possibility of drawing two inconsistent conclusions from the evidence does not prevent an administrative agency’s finding from being supported by substantial evidence.
In Allentown Mack Sales & Serv., Inc. v. N.L.R.B., 522 U.S. 359, 118 S.Ct. 818, 139 L.Ed.2d 797 (1998), the Court equated the substantial evidence standard with whether on this record it would have been possible for a reasonable jury to reach the [agency’s] conclusion. The substantial evidence test gives the agency the benefit of the doubt, since it requires not the degree of evidence which satisfies the court that the requisite fact exists, but merely the degree that could satisfy a reasonable factfinder. This is an objective test, so, for example when the agency purports to be engaged in simple factfinding, ... it is not free to prescribe what inferences from the evidence it will accept and reject, but must draw all those inferences that the evidence fairly demands. The agency’s findings must ... be set aside when the record before a Court ... clearly precludes the [agency’s] decision from being justified by a fair estimate of the worth of the testimony of witnesses or its informed judgment on matters within its special competence or both.

Penobscot Air Services, 164 F.3d at 718 (additional citations and internal quotation marks omitted).

The Court of Appeals for the Second Circuit has also emphasized the importance of lpoking at the record in its entirety. See Cellular Telephone Company v. Town of Oyster Bay, 166 F.3d 490, 494-95 (2nd Cir.1999).

Thus, the substantial evidence test requires, among other things, means that the court take into account evidence unfavorable to the agency’s decision as well as the evidence that tends to support it. See Town of Oyster Bay, 166 F.3d at 494 *67 (“[T]he record should be viewed in its entirety, including evidence opposed to the Town’s view.”); Omnipoint Corporation v. Zoning Hearing Board of Pine Grove Township, 181 F.3d 403, 408 (3rd Cir.1999) (“[A] court views the record in its entirety and takes account of evidence unfavorable to the agency’s decision.”); Illinois RSA No. 3, Inc. v. County of Peoria, 963 F.Supp. 732, 744 (C.D.Ill.1997) (“[T]he Court must consider all evidence in the record, the evidence in favor of the decision under review, as well as the evidence opposed to the decision.”).

The substantial evidence test is intended to reconcile the tensions between the competing aims of the TCA. As the Court of Appeals for the Third Circuit has described:

Congress enacted the Telecommunications Act to provide for a pro competitive, de-regulatory national policy framework designed to accelerate rapidly private-sector deployment of advanced telecommunications and information technologies and services to all Americans by opening all telecommunications markets to competition.... Among the telecommunications technologies addressed was wireless telephone service. Congress found that siting and zoning decisions by non-federal units of government have created an inconsistent and, at times, conflicting patchwork of requirements which will inhibit the deployment of Personal Communications Services as well as the rebuilding of a digital technology-based cellular telecommunications network.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New Cingular Wireless PCS, LLC v. City of Cambridge
834 F. Supp. 2d 46 (D. Massachusetts, 2011)
Global NAPS, Inc. v. Verizon New England, Inc.
447 F. Supp. 2d 39 (D. Massachusetts, 2006)
Kramer v. Zoning Board of Appeals
837 N.E.2d 1147 (Massachusetts Appeals Court, 2005)
ATC Realty, LLC v. TOWN OF KINGSTON, NEW HAMPSHIRE
173 F. Supp. 2d 118 (D. New Hampshire, 2001)
Garcia v. City of Boston
First Circuit, 2001
Southwestern Bell Mobile Systems, Inc. v. Todd
244 F.3d 51 (First Circuit, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
115 F. Supp. 2d 65, 2000 U.S. Dist. LEXIS 17763, 2000 WL 1289494, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nextel-communications-of-the-mid-atlantic-inc-v-manchester-by-the-sea-mad-2000.