Nexamp, Inc. v. Consolidated Edison, Inc.

CourtDistrict Court, S.D. New York
DecidedMarch 25, 2025
Docket1:24-cv-01502
StatusUnknown

This text of Nexamp, Inc. v. Consolidated Edison, Inc. (Nexamp, Inc. v. Consolidated Edison, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nexamp, Inc. v. Consolidated Edison, Inc., (S.D.N.Y. 2025).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK NEXAMP, INC., Plaintiff, -against- 24-CV-1502 (JGLC) CONSOLIDATED EDISON, INC., and ORANGE AND ROCKLAND UTILITIES, OPINION AND ORDER INC., Defendants.

JESSICA G. L. CLARKE, United States District Judge: Plaintiff Nexamp, Inc. brings this action against Defendants Consolidated Edison, Inc. and Orange and Rockland Utilities, Inc. for breach of contract, or in the alternative, promissory estoppel related to an energy storage project. For the reasons stated herein, Defendants’ motion to dismiss for failure to state a claim is GRANTED. BACKGROUND The following facts are, unless otherwise noted, taken from the First Amended Complaint and presumed to be true for the purposes of this motion. See LaFaro v. N.Y. Cardiothoracic Grp., PPLC, 570 F.3d 471, 475 (2d Cir. 2009). Defendant Consolidated Edison, Inc. (“ConEd”) is an energy company in the United States. ECF No. 30 (“FAC”) ¶ 3. Defendant Orange Rockland Utilities, Inc. (“O&R”) is a gas and electric utility company wholly owned by ConEd. Id. On July 1, 2022, O&R issued a Request for Proposal (“RFP”) for a stand-alone battery project (the “Project”) that would provide relief to the electric grid by drawing from stored energy. Id. ¶¶ 4–5. Plaintiff Nexamp, Inc. (“Nexamp”) is a company founded in 2007 that offers renewable generation, energy efficiency, and carbon reduction solutions. Id. ¶ 6. Plaintiff submitted a response to O&R’s RFP (“RFP Response”) on August 26, 2022. Id. ¶ 6. In the following months, Plaintiff and Defendants discussed land site options for the Project. Id. ¶ 7. During this time, Defendants communicated that only one of Plaintiff’s proposed options, 148 Saddle River Road, Rampao, New York (the “Land”), was workable. Id. ¶ 8. The lease for the Land required a non-

refundable payment of $600,000. Id. ¶ 10. Aware of this fact, Defendants continued to stress, via email, that securing the Land was a requirement for a project award. See id. ¶¶ 11, 14, 18. Plaintiff remained uncertain about whether to lease the Land up to early April 2023. Id. ¶ 22. In early April 2023, Defendants orally informed Plaintiff that Defendants had internally approved of awarding the Project to Plaintiff. Id.; see ECF No. 46 (“Opp.”) at 1. Plaintiff alleges that this communication moved Plaintiff to enter into a lease agreement for the Land on April 17, 2023. FAC ¶ 23. The following day, Defendants confirmed by email that Plaintiff had been awarded the project. Id. ¶ 24. The email confirmation states: “Congratulations, RFQ 4997519 – Monsey 2.0 Load Relief & Reliability will be awarded to NEXAMP INC! The Blanket Purchase Agreement will be for a 10 year term.” ECF No. 30-1.

Plaintiff alleges that the oral communication and the email communication, separate and together, constitute the acceptance of RFP Response and the formation of a binding contract. Id. ¶¶ 24, 38–41. Specifically, Plaintiff states: “Nexamp’s proposal itself did not establish an obligation on part of Defendants to enter a contract. However, Nexamp’s proposal was a sufficiently definite offer such that its unequivocal acceptance would give rise to an enforceable contract.” Id. ¶¶ 39–40. On May 2, 2023, Plaintiff made a non-refundable payment on their Lease for $600,000. Id. ¶ 21, 25. Plaintiff and Defendants began exchanging drafts of a term sheet, but no term sheet was ultimately signed. Id. ¶ 27. Instead, on July 17, 2023, Defendants informed Plaintiff they

were cancelling the Project. Id. On or about August 30, 2023, Defendants also informed Plaintiff that they would not reimburse Plaintiff for any of its third-party costs related to the Project, including but not limited to the $600,000 lease payment. Id. ¶ 29. On February 27, 2024, Plaintiff brought this action against Defendants, claiming breach of contract, or alternatively, promissory estoppel. ECF No. 1. Plaintiff’s First Amended

Complaint filed on June 14, 2024, is the operative complaint. ECF No. 30. Defendants moved to dismiss under Rule 12(b)(6) and 9(b) on July 30, 2024. ECF No. 38, 41 (“Mot.”). In support of this motion, Defendants filed O&R’s RFP, Plaintiff’s RFP Response, and a redlined term sheet— documents that Defendants contend have been incorporated by reference into the FAC. ECF No. 39-1 (“RFP”), 39-2 (“RFP Response”), 39-3 (“Term Sheet”); Mot. at 2 n.1. The RFP states in relevant part: RFP § 5.4. This RFP shall not be construed to establish an obligation on the part of O&R to enter into any contract, or to serve as a basis for any claim whatsoever for reimbursement of costs for efforts expended by Respondent. Furthermore, the scope of this RFP may be revised at the option of O&R at any time, or this RFP may be withdrawn or cancelled by O&R at any time. O&R shall not be obligated by any statements or representations, whether oral or written, that may be made by the Company, its employees, principals, or agents in connection with this RFP. RFP § 5.7. The duration of the Agreement will be for a term determined during contract negotiations and will depend on the parameters of the proposed solution(s) such as their ability to defer traditional capital investments for as long as possible while meeting BCA criteria. Agreements will typically commence upon the completion of construction unless otherwise provided herein. In the event that the Company determines not to proceed with the project, the successful respondent will be paid in accordance with the amounts as agreed by the Respondent and the Company. Plaintiff’s Response to the RFP, which Plaintiff alleges to define the terms of the purported contract at issue, states in relevant part: RFP Response at 2. Please note that the Nexamp has read, understands, and agrees to all provisions of the RFP.

RFP Response at 35. Following RFP selection, Nexamp and O&R will collaborate on the negotiation and execution of a contract in the form of an energy storage services agreement. Engineering site visits, surveys, and inspections will proceed in parallel with these agreement negotiations and will inform the system design. Once the final design and location is approved, Nexamp will work with the local fire department, conservation commission, planning boards, and others to secure approvals before beginning construction on site. Nexamp’s proposal has assumed that the costs of securing permitting approvals will be borne by Nexamp. Defendants additionally move to seal certain exhibits. ECF Nos. 22, 34. Plaintiff opposes the motion to dismiss, ECF No. 46, and takes no position on the request to seal certain exhibits. LEGAL STANDARD In reviewing a motion to dismiss under Rule 12(b)(6), the Court must “constru[e] the complaint liberally, accepting all factual allegations in the complaint as true, and drawing all reasonable inferences in the plaintiff’s favor.” Goldstein v. Pataki, 516 F.3d 50, 56 (2d Cir. 2008) (internal citation omitted). A claim will survive a Rule 12(b)(6) motion only if the plaintiff alleges facts sufficient “to state a claim to relief that is plausible on its face.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007). A claim is facially plausible “when the plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (citing Twombly, 550 U.S. at 556). “Determining whether a complaint states a plausible claim for relief will . . . be a context-specific task that requires the reviewing court to draw on its judicial experience and common sense.” Id. at 679.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Goldstein v. Pataki
516 F.3d 50 (Second Circuit, 2008)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
DiFolco v. MSNBC Cable L.L.C.
622 F.3d 104 (Second Circuit, 2010)
Goldman v. Belden
754 F.2d 1059 (Second Circuit, 1985)
United States v. Amodeo
71 F.3d 1044 (Second Circuit, 1995)
Lugosch v. Pyramid Co. of Onondaga
435 F.3d 110 (Second Circuit, 2006)
Faulkner v. Beer
463 F.3d 130 (Second Circuit, 2006)
LaFaro v. New York Cardiothoracic Group, PLLC
570 F.3d 471 (Second Circuit, 2009)
DeLuca v. AccessIT Group, Inc.
695 F. Supp. 2d 54 (S.D. New York, 2010)
Randolph Equities, LLC v. Carbon Capital, Inc.
648 F. Supp. 2d 507 (S.D. New York, 2009)
Helprin v. Harcourt, Inc.
277 F. Supp. 2d 327 (S.D. New York, 2003)
Jordan Panel Systems Corp. v. Turner Construction Co.
45 A.D.3d 165 (Appellate Division of the Supreme Court of New York, 2007)
Krumme v. WestPoint Stevens Inc.
238 F.3d 133 (Second Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Nexamp, Inc. v. Consolidated Edison, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/nexamp-inc-v-consolidated-edison-inc-nysd-2025.