This text of Nexagen Networks, Inc. (Nexagen Networks, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nexagen Networks, Inc., (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Nexagen Networks, Inc. ) ASBCA No. 60641 ) Under Contract No. Wl5P7T-13-D-E077/KX01 )

APPEARANCES FOR THE APPELLANT: David A. Rose, Esq. Rose Consulting Law Firm Valdosta, GA

Kendall R. Enyard, Esq. Caitlin T. Conroy, Esq. Steptoe & Johnson LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Scott N. Flesch, Esq. Army Chief Trial Attorney Dana J. Chase, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE O'CONNELL ON THE GOVERNMENT'S MOTION FOR PARTIAL SUMMARY JUDGMENT

The Army has filed its second motion for partial summary judgment. In Nexagen Networks, Inc., ASBCA No. 60641, 19-1BCA137,258, the Board granted the government's first motion for summary judgment in part with respect to the majority of the damages sought in Nexagen's claim for consequential damages. In its new motion, the Army contends: 1) that appellant's claim is barred by the doctrine of res judicata as a result of the Court of Federal Claims' decision in Nexagen Networks, Inc. v. United States, 124 Fed. Cl. 645 (2015); and 2) the damages Nexagen seeks for the task order option year are too remote and uncertain to be recoverable.

Nexagen has filed a lengthy opposition in which it disputes some of the government's proposed facts and proposes 96 additional facts, and contests the government's legal arguments. The government has not filed a reply brief or otherwise disputed any ofNexagen's 96 proposed findings. Because the Board believes it is not necessary for purposes of the pending motion to detail Nexagen's proposed findings, it suffices to state that Nexagen has a long list of grievances with respect to the government's handling of the task order. STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

A longer description ofNexagen's claims is included in the Board's first opinion in this appeal (Nexagen, 19-1BCA137,258). The Board supplements the facts from that opinion where necessary, including with facts drawn from the Court of Federal Claims' opinion, which has not been appealed and is now final.

As described in the Board's first decision, in May 2013 the Army awarded Nexagen a multiple award indefinite-delivery/indefinite quantity contract to provide software and systems engineering services. The appeal arises from a task order for data strategy service and software support awarded in February 2015. The task order contained base and option years and provided that "[t]he Government reserves the right to exercise the option pursuant to FAR 52.217-9, 'Option to Extend the Term of the Contract' found in Section I of the basic contract." (R4, tab 2 at 2) This clause provides that the government "may" exercise the option but must give the contractor notice at least 60 days before the contract expires. However, even if the government gives this notice, it is not obligated to exercise the option. FAR 52.2 l 7-9(a).

As related in our first opinion, on May 4, 2015, (that is, during the base year) the contracting officer terminated the task order for default. He changed it to a termination for convenience less than two weeks later. Nexagen, 19-1BCA137,258 at 181,325; (R4, tab 13-15).

On May 6, 2015, a different contracting officer canceled the task order because she had concluded that material flaws in the evaluation record made a re-evaluation and subsequent award impossible. The Army subsequently issued a new task order request. Nexagen, 124 Fed. CL at 649-50; (R4, tabs 60-61).

On June 26, 2015, Nexagen filed a complaint at the Court of Federal Claims. The action was in part a bid protest challenging the decision to issue a new task order, and in part a claim for damages arising from the canceled task order. Nexagen, 124 Fed. CL at 652-54.

On August 1, 2015, Nexagen for the first time submitted a certified claim to the contracting officer seeking $40,244,379.94 related to the termination and an alleged breach of the contract. The contracting officer notified Nexagen two weeks later that she did not possess jurisdiction to consider the claim due to the pending action at the Court of Federal Claims. Nexagen, 124 Fed. CL at 649, 652.

On December 21, 2015, the Court dismissed Nexagen's claim for damages for lack of jurisdiction because it had not submitted a claim to the contracting officer before it filed suit. The Court further ruled that, to the extent that the action could be read to challenge the termination for default, that claim was moot due to the

2 contracting officer's conversion of the termination to one for the convenience of the government prior to Nexagen filing the law suit.* Nexagen, 124 Fed. Cl. at 652-54.

On December 22, 2015, Nexagen submitted to the contracting officer the claim at issue in this appeal (R4, tab 20). It sought $37,597,526.94 for "Compensatory Consequential Damages: Breach of implied covenant of good faith and fair dealing," and $2,646,853 for "Compensatory Expectation Damages: Breach of contract based upon wrongful termination" (id. at 9). The contracting officer denied the claim except for a prorated fee (profit) on the base year of$151,424.54 (R4, tab 22). Nexagen timely appealed this decision to the Board.

DECISION

I. Nexagen 's Claim is Not Barred by the Doctrine of Res Judicata

After the Board's decision on the government's first summary judgment motion, Nexagen's $2,646,853 claim for expectation damages remained pending. With respect to Nexagen's consequential damages claim, $7,409,260 remained pending. The government contends that these claims are barred by the doctrine of res judicata based on the Court of Federal Claims opinion described above.

A claim is barred by res judicata when "( 1) the parties are identical or in privity; (2) the first suit proceeded to a final judgment on the merits; and (3) the second claim is based on the same set of transactional facts as the first." Cunningham v. United States, 748 F.3d 1172, 1179 (Fed. Cir. 2014) (citation omitted). The second prong of this test is clearly a problem for the government because the Court of Federal Claims dismissed Nexagen's money claim for lack of jurisdiction. Nexagen, 124 Fed. Cl. at 652.

The government points to the section of the Court of Federal Claims opinion where it stated that it possesses jurisdiction to consider challenges to default terminations. While that is correct, the Court never reached the merits of the termination because it observed that the contracting officer had already provided the only relief it could have awarded - conversion to a termination for convenience. This was the only relief that the Court believed it could provide because a challenge to a termination for default (a government claim) does not grant the Court jurisdiction to consider a money claim that the contractor failed to submit to the contracting officer. Nexagen, 124 Fed. Cl. at 652-54; DePonte Investments, Inc. v. United States, 54 Fed. Cl. 112, 115 (2002).

* The Court also dismissed Nexagen's challenge to the corrective action for lack of jurisdiction. Nexagen, 124 Fed. Cl. at 654.

3 Based on its determination that there was no relief it could provide, the Court dismissed as moot the portion of the complaint raising allegations challenging the termination. Nexagen, 124 Fed. Cl. at 654. The government contends that this was an adjudication on the merits ofNexagen's claim that the termination was wrongful (gov't mot. at 9) and, therefore, it bars litigation ofNexagen's claim that it is entitled to damages as a result of a wrongful termination. The government does not cite precedent supporting its position.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

T & M Distributors, Inc. v. United States
185 F.3d 1279 (Federal Circuit, 1999)
Already, LLC v. Nike, Inc.
133 S. Ct. 721 (Supreme Court, 2013)
Cunningham v. United States
748 F.3d 1172 (Federal Circuit, 2014)
Nexagen Networks, Inc. v. United States
124 Fed. Cl. 645 (Federal Claims, 2016)
United States v. Sanchez-Gomez
584 U.S. 381 (Supreme Court, 2018)
Deponte Investments, Inc. v. United States
54 Fed. Cl. 112 (Federal Claims, 2002)
Trafalgar House Construction, Inc. v. United States
274 F. App'x 898 (Federal Circuit, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Nexagen Networks, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/nexagen-networks-inc-asbca-2020.