NewSun Energy LLC v. Public Untility Comm.

337 Or. App. 79
CourtCourt of Appeals of Oregon
DecidedDecember 26, 2024
DocketA180896
StatusUnpublished
Cited by1 cases

This text of 337 Or. App. 79 (NewSun Energy LLC v. Public Untility Comm.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NewSun Energy LLC v. Public Untility Comm., 337 Or. App. 79 (Or. Ct. App. 2024).

Opinion

No. 930 December 26, 2024 79

This is a nonprecedential memorandum opinion pursuant to ORAP 10.30 and may not be cited except as provided in ORAP 10.30(1).

IN THE COURT OF APPEALS OF THE STATE OF OREGON

NEWSUN ENERGY LLC, Petitioner, v. PUBLIC UTILITY COMMISSION OF OREGON, Alliance of Western Energy Consumers, Idaho Power Company, Northwest & Intermountain Power Producers Coalition, Obsidian Renewables, Oregon Solar + Storage Industry Association, PacifiCorp, Portland General Electric, Staff of the Public Utility Commission of Oregon Respondents, and COMMUNITY RENEWABLE ENERGY ASSOCIATION and Renewable Energy Coalition, Intervenors below. Public Utility Commission of Oregon UM2032; A180896

Argued and submitted November 8, 2024. Tyler R. Whitney argued the cause for petitioner. Also on the briefs were Richard G. Lorenz, Casey M. Nokes, and Cable Huston LLP. Jordan R. Silk, Assistant Attorney General, argued the case for respondents Public Utility Commission of Oregon and Staff of the Public Utility Commission of Oregon. Also on the brief were Ellen F. Rosenblum, Attorney General, and Benjamin Gutman, Solicitor General. Jordan Schoonover argued the cause for respondents Idaho Power Company, PacifiCorp, and Portland General 80 NewSun Energy LLC v. Public Utility Comm.

Electric. Also on the brief were Adam Lowney and McDowell Rackner Gibson PC. Gregory M. Adams and Richardson Adams, PLLC, Idaho, and Irion A. Sanger, Ellie Hardwick, and Sanger Law, PC filed the brief amicus curiae for Community Renewable Energy Association and Renewable Energy Coalition. No appearance for Obsidian Renewables. No appearance for Alliance of Western Energy Consumers, Northwest & Intermountain Power Producers Coalition, and Oregon Solar + Storage Industry Association. Before Tookey, Presiding Judge, Lagesen, Chief Judge, and Kamins, Judge. LAGESEN, C. J. Affirmed. Nonprecedential Memo Op: 337 Or App 79 (2024) 81

LAGESEN, C. J. Petitioner seeks judicial review of final Public Utility Commission Order No. 23-005 and subsequent clar- ifying Order No. 23-164. Petitioner raises two assignments of error: (1) the Public Utility Commission of Oregon (com- mission) erred by discriminating against qualifying facili- ties (QFs) “regarding the allocation of network upgrade costs in violation of the Public Utility Regulatory Policies Act’s (PURPA) express requirements and those of Oregon’s statu- tory regulations”;1 and (2) the commission erred by making conclusions in its final orders that were not supported by substantial reason. We affirm. Discriminatory Treatment. In its first assignment of error, petitioner contends that the commission’s order is discriminatory, in violation of both PURPA and Oregon’s “mini-PURPA” statute. We review the commission’s orders to determine “whether the PUC correctly applied the appli- cable law and whether it acted within the scope of its discre- tion.” Northwest Public Communications Council v. Qwest, 279 Or App 626, 643, 379 P3d 633 (2016). As we understand it, petitioner’s theory as to why the commission’s order is discriminatory is that it places “on-system” QFs, like petitioner, at a “unique economic disadvantage” vis-à-vis “off-system” QFs by continuing to make “on-system” QFs presumptively responsible for the cost of network upgrades associated with interconnection.2 Petitioner appears to contend that by continuing to keep the presumptive cost burden of network upgrades on QFs, 1 Per the Federal Energy Regulatory Commission’s (FERC) pro forma large generator interconnection procedures and agreements, Network Upgrades are defined as “the additions, modifications, and upgrades to the Transmission Provider’s Transmission System required at or beyond the point at which the Interconnection Facilities connect to the Transmission Provider’s Transmission System to accommodate the interconnection of the Large Generating Facility to the Transmission Provider’s Transmission System.” 2 “On system” QFs refer to facilities that sell their total output to a state electric utility and are thus subject to state authority “over the interconnec- tion and the allocation of interconnection costs.” Conversely, “off system” QFs are facilities that elect to sell some or all of their power output to utilities other than the one with which they are directly interconnected and are thus subject to FERC authority. Standardization of Generator Interconnection Agreement and Procedures, Order No. 2003, 68 Fed Reg 49,846, at 49,918 (Aug 19, 2003), 104 FERC ¶ 61,103, at 165 (2003). 82 NewSun Energy LLC v. Public Utility Comm.

the commission is establishing a discriminatory scheme because, were those QFs under FERC jurisdiction, they would be subject to a different—and more beneficial—cred- iting policy. That argument—which hinges on the commission’s decision to adopt a policy for QFs subject to its regulation that differs from the policy choice made by FERC with respect to QFs subject to its regulation—is unpersuasive for two reasons. First, federal regulations explicitly give state regulatory authorities the power to “determine the man- ner for payments of interconnection costs” as well as assess the interconnection costs due from QFs. 18 CFR § 292.306 (a), (b). Thus, federal law explicitly grants state regulatory authorities the power to make policy choices regarding interconnection costs that diverge from the choices made by FERC. Additionally, petitioner cites to no basis in law for the assertion that it is legally cognizable discrimination for one regulatory authority to make policy choices that differ from those made by a different regulatory authority. Petitioner also points to CED Wheatland, LLC v. Montana Department of Public Service Regulation, 408 Mont 268, 284, 509 P3d 19 (2022), in support of its argument that the commission’s policy is discriminatory. But that case did not address the issue here, which is what framework should apply for determining who should bear the cost of network upgrades required to accommodate the interconnection of a QF. Rather, it involved a fact-specific determination that it would be impermissibly discriminatory to require the QF in that case to bear the costs—upwards of $237 million—for a network upgrade that benefited the utility’s system as a whole. CED Wheatland, 408 Mont at 277. This case involves a challenge to the commission’s policy for determining when the costs of a network upgrade may be shifted away from the QF—a policy that expressly allows a QF to demonstrate that, on the facts of a particular case, it should not be responsible for network upgrade costs required to permit interconnection. In addition, petitioner asserts that the commission’s decision exceeds its authority because, in petitioner’s view, it is inconsistent with ORS 758.515 and with PURPA more generally. ORS 758.515 does not assist petitioner, because Nonprecedential Memo Op: 337 Or App 79 (2024) 83

it recites legislative findings and does not impose substan- tive limitations on the commission’s authority. See Urban Renewal Comm. of Oregon City v. Williams, 322 Or App 615, 633, 521 P3d 494 (2022), rev den, 371 Or 127 (2023) (stating that legislative findings may provide context but are “not conclusive * * * because they are not operative directives” in statutes). While the energy goals outlined in ORS 758.515

Free access — add to your briefcase to read the full text and ask questions with AI

Related

NewSun Energy LLC v. Public Untility Comm.