Newman Partners v. Cfc Const. Ltd, No. Cv91-0318137-S (Nov. 28, 1994)

1994 Conn. Super. Ct. 11804, 13 Conn. L. Rptr. 154
CourtConnecticut Superior Court
DecidedNovember 28, 1994
DocketNo. CV91-0318137-S
StatusUnpublished

This text of 1994 Conn. Super. Ct. 11804 (Newman Partners v. Cfc Const. Ltd, No. Cv91-0318137-S (Nov. 28, 1994)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Newman Partners v. Cfc Const. Ltd, No. Cv91-0318137-S (Nov. 28, 1994), 1994 Conn. Super. Ct. 11804, 13 Conn. L. Rptr. 154 (Colo. Ct. App. 1994).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION This is a dispute arising out of the planning and construction of the New Haven City Hall.

The predecessor in interest to the defendant CFC Construction Limited Partnership (hereinafter CFC) hired the plaintiff Herbert S. Newman and Partners (Newman) to provide architectural services for the development of a design concept for the site in downtown New Haven to be designated as the Government Center. Included on the site was the sole remaining structure of the old City Hall complex. A new City Hall was contemplated for the site, incorporating in part the old City Hall building.

Eventually, the plaintiff was hired to design the structure and the City entered into an agreement with another Chase entity to act as contractor. CFC assumed all obligations under the Owner-Contractor Agreement on February 11, 1989. CT Page 11805

The City required that CFC provide a bond to guarantee payment to all who performed work or supplied material to the project. CFC obtained a surety bond from the National Union Fire Insurance Company (hereinafter National Union). In pertinent part, the bond provided that:

"Any party, whether a subcontractor or otherwise, who furnishes materials or supplies or performs labor or services in the prosecution of the work under said contact, and who is not paid therefore, may bring a suit on this bond in the name of the person suing, prosecute the same to a final judgment, and have execution thereon for such sum or sums as may be justly due. [Emphasis added.]"

Until June 30, 1988, there was apparent harmony between CFC and Newman. Then, on June 30, the parties agreed that monthly billings would not exceed $6,000.00. This apparent modification of the contract was never implemented by either party and invoices were submitted and paid without incident until 1990 when CFC became delinquent.

The parties then had discussions and exchanged letters over a purported settlement of all outstanding arrearages, and according to a CFC principal, all services to be rendered. When CFC failed to pay according to the Newman understanding of their agreement, Newman resumed the prior billing process.

At no time did CFC protest these billings, assert its version of the "settlement", or indicate any dissatisfaction with the plaintiff's services.

On June 21, 1990, the City terminated CFC's participation in the project because of a lack of progress toward completion. The final day for CFC's presence on the site was July 2, 1990. Newman continued to do project representation on several aspects of the work. Both CFC and National Union protested the City's action and both declined to pay the plaintiff for the balance it claims is due.

I. THE SURETY BOND

In a case of first impression in Connecticut, the defendant National Union seeks to avoid liability on its performance bond for CT Page 11806 the amount due to the plaintiff because the plaintiff failed to distinguish between work it performed on-site and work it performed off site.

According to this defendant, "architects and other design professionals may only recover for on-site supervisory or inspection service." (Brief, p. 10.) The defendant concedes that no Connecticut case adopts this view but argues that this is well settled under federal law and federal law controls this case.

The defendant relies heavily on two federal court cases,United States v. Butt Head. Inc., 535 F. Sup. 1155 (S.D. Ohio 1982), and United States v. W. H. Cates Construction Co., Inc.,972 F.2d 987 (8th Cir. 1992). Both these and other federal court cases cited support the position of the defendant.

The Miller Act, which is the subject of these federal cases, reads in pertinent part as follows:

"Before any contract, exceeding $25,000 in amount, for the construction, alteration, or repair of any public building or public work of the United States is awarded to any person, such person shall furnish to the United States the following bonds, which shall become binding upon the award of the contract to such person, who is hereinafter designated as "contractor":

Section 270b of the Miller Act states in pertinent part:

(a) Every person who has furnished labor or material in the prosecution of the work provided for in such contract, in respect of which a payment bond is furnished under Sections 270a to 270d of this title and who has not been paid in full therefor before the expiration of a period of ninety days after the day on which the last of the labor was done or performed by him or material was furnished or supplied by him for such claim is made, shall have the right to use on such payment bond for the amount, or the balance thereof. . . . CT Page 11807

The Connecticut General Statutes governing contracts for the construction of public structures includes § 49-41, captioned "Public structures. Bonds for protection of employees and materialmen." It proceeds to mirror the language of the Miller Act and § 49-42 is virtually identical to § 270b(a) recited above.

The Court does not dispute the defendants' claim that § 49-41 should operate in general conformity with the Miller Act and that in deciding issues of first impression under it, the federal Miller Act cases should be examined. However, a close reading of these federal cases reveals a decided awareness on the part of federal court judges that there are distinct limits to the application of the Miller Act as well as an awareness that the federal case law on the subject is different from state case law. Thus, in Butt Head, Inc., the Court notes:

"However, it is also true that federal case law has adopted an admittedly somewhat narrow definition of the term `labor' in § 270b(a), that is, covering only skilled professional work which involves actual superintending, supervision, or inspection at the job site."

Id. at 1160.

In that same case, at page 1158, this excerpt from footnote 2 is revealing:

. . . The Rich decision has been subsequently interpreted to mean that state law is not an appropriate reference when the Miller Act itself, rather than the contract between the parties, is to be interpreted. . . .

(Emphasis added.) Consequently, in this case, state law is appropriate as this is not a Miller Act case and the contract between the parties is at issue.

There is no question that the defendant National Union, the surety, by executing the bond acquires obligations which are coextensive with that of the principal. Star ContractingCorporation v. Manway Construction Co., 32 Conn. Sup. 64, 66-67 (1973). (Citations omitted.) CT Page 11808

The bond in question here was filed pursuant to § 49-42. The defendant CFC was principal and National Union was surety. Protection was guaranteed to "any party, whether a subcontractor or otherwise, who furnishes materials or supplies or performs labor or services in the prosecution of work under said contract." (Exhibit K.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. W.H. Cates Construction Co.
972 F.2d 987 (Eighth Circuit, 1992)
International Harvester Co. v. L. G. DeFelice & Son, Inc.
197 A.2d 638 (Supreme Court of Connecticut, 1964)
Nicholson & Loup v. Carl E. Woodward
596 So. 2d 374 (Louisiana Court of Appeal, 1992)
Kelly v. Kowalsky
442 A.2d 1355 (Supreme Court of Connecticut, 1982)
Bridgeport Pipe Engineering Co. v. DeMatteo Construction Co.
268 A.2d 391 (Supreme Court of Connecticut, 1970)
W. H. McCune, Inc. v. Revzon
193 A.2d 601 (Supreme Court of Connecticut, 1963)
State v. Menillo
368 A.2d 136 (Supreme Court of Connecticut, 1976)
Taft v. Valley Oil Co., Inc.
9 A.2d 822 (Supreme Court of Connecticut, 1939)
McGovern Granite Co. v. Veterans' Home Commission
199 A. 441 (Supreme Court of Connecticut, 1938)
Hoffman v. Fidelity & Casualty Co.
6 A.2d 357 (Supreme Court of Connecticut, 1939)
Zahornacky v. Edward Chevrolet, Inc.
436 A.2d 47 (Connecticut Superior Court, 1981)
Crucible Steel Co. of America v. Premier Manufacturing Co.
110 A. 52 (Supreme Court of Connecticut, 1920)
Riverside Coal Co. v. American Coal Co.
139 A. 276 (Supreme Court of Connecticut, 1927)
Pelton & King, Inc. v. Town of Bethlehem
147 A. 144 (Supreme Court of Connecticut, 1929)
New Britain Lumber Co. v. American Surety Co.
154 A. 147 (Supreme Court of Connecticut, 1931)
Halloran v. Fischer
9 A.2d 290 (Supreme Court of Connecticut, 1939)
Girasulo v. Consolidated Motor Lines, Inc.
5 Conn. Super. Ct. 245 (Connecticut Superior Court, 1937)
Star Contracting Corporation v. Manway Construction
337 A.2d 669 (Connecticut Superior Court, 1973)
Montgomery v. Smith
499 A.2d 444 (Connecticut Superior Court, 1985)
Goodrich v. Stanley
24 Conn. 613 (Supreme Court of Connecticut, 1856)

Cite This Page — Counsel Stack

Bluebook (online)
1994 Conn. Super. Ct. 11804, 13 Conn. L. Rptr. 154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/newman-partners-v-cfc-const-ltd-no-cv91-0318137-s-nov-28-1994-connsuperct-1994.