Newhall-Herkner Construction Co. v. United States

89 F. Supp. 321, 116 Ct. Cl. 419, 1950 U.S. Ct. Cl. LEXIS 95
CourtUnited States Court of Claims
DecidedApril 3, 1950
DocketNo. 46074
StatusPublished
Cited by1 cases

This text of 89 F. Supp. 321 (Newhall-Herkner Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Newhall-Herkner Construction Co. v. United States, 89 F. Supp. 321, 116 Ct. Cl. 419, 1950 U.S. Ct. Cl. LEXIS 95 (cc 1950).

Opinion

Whitaker, Judge,

delivered the opinion of the court:

Plaintiffs entered into a contract with the defendant for the construction of Pleasant Hill Dam, located on Clear Fork, Mohican River, near Perrysville, Ohio. Except for the items which have been abandoned, plaintiffs sue for certain excess costs and for damages for delays caused by various things.

RECESS JOINT CLAIM

Plaintiffs’ first claim is for the excess cost of leaving a recess in the floor slab of the operating house.

[447]*447The plans indicated that the floor slab of the operating house might be constructed with but one pouring of concrete. The plaintiffs so interpreted them, and the resident engineer, who was the representative of the contracting officer assigned to supervise this particular job, agreed.

The contractors, accordingly, installed the necessary forms and reinforcing steel for one pour of concrete. However, before the pour was made, the District Engineer, having been apprized of the contractors’ plans, ruled that it would be necessary to leave a recess around a slot in the floor designed to receive the gate stems for the hoists for the gate of the dam. The contractors were required to provide this recess. They sue for the excess cost of doing so.

The District Engineer, who was the contracting officer, approved the claim for these excess costs, but he was reversed by the Chief of Engineers, who held that the plans, properly interpreted, showed the necessity for this recess.

The Commissioner has found that this ruling was arbitrary and unreasonable. We concur. The plans did not show this recess. Plaintiffs may recover the excess cost of doing this work, in the sum of $242.62.

FLOOD DAMAGE CLAIM

After plaintiffs had made the necessary excavation for the impervious section of the dam, but before the upstream cofferdam had been completed, a flood came which washed into the excavated area some 8,000 cubic yards of material. Plaintiffs sue for the cost of removing it. This was disallowed by the contracting officer and, on appeal, by the Chief of Engineers.

Plaintiffs base their claim on paragraph 1-12 (b) of the specifications which reads:

1.12. Flooding of Cofferdams and/or Protection henees. * * *
(b) In the event that a flood overtops the cofferdams and/or levees where built and maintained to full effective height, and in accordance with the approved drawings, with resultant injury to the permanent work within the cofferdam and/or levees, the contractor will be required to restore such work at the unit contract prices.

[448]*448Plaintiffs say that the foundation for tbe dam was a part of “the permanent work within the cofferdam,” that the washing of these materials into it damaged it, and therefore that they are entitled to the cost of removing them.

It is at least doubtful whether plaintiffs can bring their claim within this paragraph since the upstream cofferdam had not been completed, as the commissioner’s 22nd finding shows, to which no exception was taken and which we have adopted as a correct finding. Paragraph 1-12 (b) related to damage to the permanent work after the cofferdams had been “built and maintained to full effective height.” Before that time it seems probable that it was contemplated that the contractor would have to run the risk of flood damage.

Defendant, on the contrary, says plaintiffs’ rights are determined by paragraph 5-01 (e) (2) of the specifications relating to “common excavation.” This paragraph provides for surveys for excavations to be made and for payment based on these surveys, and then’ says:

* * * The contractor shall remove material which has been deposited subsequent to the above-mentioned survey by floods, rains, or other causes, and no payment will be made for such excavation. * * *

It is at least plausible to say that this paragraph is determinative of plaintiffs’ rights.

This case arises under one of those government contracts which in article 15 gives finality to the decisions of the contracting officer, affirmed on appeal, not only as to questions of fact, but as to all “questions arising under this contract.” Under the Supreme Court’s decision in Moorman v. United States, 338 U. S. 457, these questions include the interpretation of the requirements of the contract. By the contracting officer’s decision on such a question we are bound, unless it is arbitrary or capricious or evidently lacking in that good faith required of an impartial arbiter. Plaintiffs do not bring their case within this exception. The decision of the contracting officer appears to us to have been a reasonable one and, hence, we are bound by it.

[449]*449LABOR CLAIM

This contract was entered into for the purpose, in part, of relieving unemployment. It required that:

To the fullest extent possible, labor required for the project and appropriate to be secured through employment services shall' be chosen from the lists of qualified workers submitted by local employment agencies designated by the United States Employment Service.

However, plaintiffs were notified by paragraph 1-35 of the specifications that sufficient labor was not available in the immediate vicinity of the work. The nearest United States Employment Service office was-at Ashland, Ohio, some twenty miles from the site of the work. Plaintiffs’ requests for labor were submitted to this office. • ■

The proof shows that this agency did all it could do to supply plaintiffs with the labor they required and that, when it was unable to do so, the contracting officer gave plaintiffs permission to get skilled labor wherever they could, although he. still required them to first apply to the Employment Service for unskilled labor before permitting them to secure it elsewhere.

We are of opinion the contracting officer fairly administered this provision of the contract. Plaintiffs were put on full notice of the requirements of the contract relative to the procurement of labor, and we think that no more than this was demanded of them. They are not entitled to recover on this item of their claim.

DELAY IN REMOVAL OE OIL EIRE LINE

The findings show that it was necessary to remove a pipe line before plaintiffs could construct the inlet and outlet works. This pipe line was to be removed by another contractor under a separate contract. There was a delay of 35 days in removing it due to a delay in securing the necessary right-of-way to which the pipe line was to be removed. This right-of-way was to be provided by the Muskingum Watershed Conservancy District, an agency of the State of Ohio. [450]*450Defendant bad nothing to do with the securing of this right-of-way, and since the delay in removal of the oil pipe line was occasioned by the delay in securing it, defendant is not liable therefor.

It is true that paragraph 3-01 (c) of the specifications provided, “The gas and oil pipe lines will be moved outside the work area by other agencies sufficiently in advance of construction as to not interfere with the contractor’s operations and this work will not be included in this contract.” This must be construed to mean, however, we think, that it was expected

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Long v. United States
102 F. Supp. 134 (D. Montana, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
89 F. Supp. 321, 116 Ct. Cl. 419, 1950 U.S. Ct. Cl. LEXIS 95, Counsel Stack Legal Research, https://law.counselstack.com/opinion/newhall-herkner-construction-co-v-united-states-cc-1950.